3/5/2019 | | Recordation of Patent Grant Mailed |
3/5/2019 | | Application ready for PDX access by participating foreign offices |
2/14/2019 | | Email Notification |
2/13/2019 | | Issue Notification Mailed |
1/18/2019 | | Dispatch to FDC |
1/15/2019 | | Application Is Considered Ready for Issue |
1/14/2019 | | Issue Fee Payment Verified |
1/14/2019 | | Issue Fee Payment Received |
10/15/2018 | | Electronic Review |
10/15/2018 | | Email Notification |
10/15/2018 | | Mail Notice of Allowance |
10/10/2018 | | Notice of Allowance Data Verification Completed |
9/26/2018 | | Reasons for Allowance |
8/28/2018 | | Date Forwarded to Examiner |
8/20/2018 | | Response after Final Action |
8/20/2018 | | New or Additional Drawing Filed |
6/18/2018 | | Electronic Review |
6/18/2018 | | Email Notification |
6/18/2018 | | Mail Final Rejection (PTOL - 326) |
6/13/2018 | | Final Rejection |
4/9/2018 | | Date Forwarded to Examiner |
3/22/2018 | | New or Additional Drawing Filed |
3/22/2018 | | Response after Non-Final Action |
12/26/2017 | | Electronic Review |
12/23/2017 | | Email Notification |
12/22/2017 | | Mail Non-Final Rejection |
12/20/2017 | | Non-Final Rejection |
12/19/2017 | | Information Disclosure Statement considered |
11/2/2017 | | Date Forwarded to Examiner |
10/26/2017 | | Change in Power of Attorney (May Include Associate POA) |
10/25/2017 | | Correspondence Address Change |
10/24/2017 | | Response to Election / Restriction Filed |
10/24/2017 | | Preliminary Amendment |
10/24/2017 | | Incoming Letter Pertaining to the Drawings |
10/24/2017 | | Information Disclosure Statement (IDS) Filed |
10/24/2017 | | Information Disclosure Statement (IDS) Filed |
8/28/2017 | | Mail Restriction Requirement |
8/25/2017 | | Restriction/Election Requirement |
10/7/2016 | | Case Docketed to Examiner in GAU |
9/8/2016 | | Case Docketed to Examiner in GAU |
6/24/2016 | | Change in Power of Attorney (May Include Associate POA) |
6/24/2016 | | Application Dispatched from OIPE |
6/24/2016 | | FITF set to YES - revise initial setting |
6/24/2016 | | Application Is Now Complete |
6/24/2016 | | Filing Receipt - Updated |
6/20/2016 | | Additional Application Filing Fees |
5/6/2016 | | Filing Receipt |
5/6/2016 | | Notice Mailed--Application Incomplete--Filing Date Assigned |
5/6/2016 | | Applicant Has Filed a Verified Statement of Micro Entity Status in Compliance with 37 CFR 1.29 |
5/1/2016 | | Cleared by OIPE CSR |
4/28/2016 | | IFW Scan & PACR Auto Security Review |
4/26/2016 | | ENTITY STATUS SET TO UNDISCOUNTED (INITIAL DEFAULT SETTING OR STATUS CHANGE) |
4/26/2016 | | Initial Exam Team nn |