throbber
UNITED STATES PATENT AND TRADEMARK OFFICE
`_______________
`
`BEFORE THE PATENT TRIAL AND APPEAL BOARD
`_______________
`
`TIANMA MICROELECTRONICS CO. LTD.,
`Petitioner,
`v .
`JAPAN DISPLAY INC. AND
`PANASONIC LIQUID CRYSTALDISPLAY CO., LTD.,
`Patent Owner
`_______________
`Case IPR No: IPR2021-01060
`Patent No. 10,330,989
`_______________
`
`PATENT OWNER JAPAN DISPLAY INC. AND
`PANASONIC LIQUID CRYSTAL DISPLAY CO., LTD.’S
`PRE-INSTITUTION SUR-REPLY
`
`

`

`Patent Owner’s Pre-Institution Sur-Reply
`
`Contrary to Petitioner’s argument, “[a] holistic evaluation of the Fintiv
`factors,” which would weigh all six Fintiv factors, favors discretionary denial.
`Paper 8 at 1 (“Reply”). Petitioner has never argued, nor could it, that factor 5
`(“whether the petitioner and the defendant in the parallel proceeding are the same
`party”) weighs in favor of institution. Apple Inc. v. Fintiv, Inc., IPR2020-00019,
`Paper 15 at 8 (P.T.A.B. May 13, 2020). In its Reply, Petitioner appears to have
`abandoned its argument that factor 1 (“whether the court granted a stay or evidence
`exists that one may be granted if a proceeding is instituted”) “is, at best, neutral”
`given that its motion to transfer was denied. Id. at 7; Paper 2 at 6 (“Petition”); see
`also Ex. 2002 (Order denying transfer motion). Further, an analysis of Fintiv factors
`2, 3, 4, and 6 demonstrates why Petitioner’s argument should be rejected.
`Fintiv Factor 2 considers the proximity of the court’s trial date to the projected
`statutory deadline for the Board’s final written decision. See Fintiv, Paper 11 at 9.
`Petitioner recognizes that the district court trial date will precede the Board’s
`statutory deadline for a final written decision, Reply at 1, but ignores the eleven full
`months between the district court trial date (February 7, 2022) and the Board’s final
`written decision (January 8, 2023). To evade this reality, Petitioner cites Samsung
`Electronics Co., Ltd., v. Acorn Semi, LLC, IPR2020-01183, Paper 17 at 38-39, 47
`(P.T.A.B. Feb. 10, 2021) as a single example in which the Board instituted review
`despite a ten-month gap between the district court trial and the final written decision
`dates in the IPR. But Petitioner’s reliance is misplaced because the two Fintiv factors
`that supported institution in Samsung swing the other way here. First, the Board
`found that the Samsung Petitioners’ Sotera-like stipulation preventing overlap of
`
`–1–
`
`

`

`Patent Owner’s Pre-Institution Sur-Reply
`
`arguments between the Board and district court weighed in favor of institution under
`Fintiv Factor 4. Id. at 43. But more recent cases establish that these types of
`stipulations are not always dispositive of institution, and, as Patent Owner explains
`in detail below, Petitioner’s stipulation here does not appreciably simplify the district
`court case. Second, the Board found that the Samsung Petitioners had presented “a
`strong unpatentability challenge to every challenged claim” under Fintiv Factor 6.
`Id. at 46. But here, as Patent Owner explains in its preliminary response (Paper 7 at
`16-49), Petitioner has only presented weak challenges to every challenged claim.
`Third, the Samsung decision made no mention of (1) an extensive prior art products
`invalidity defense like the one put forward by Petitioner in the district court
`proceeding, which will require the district court to analyze the same prior art
`references asserted in the petitions, or (2) an order granting Petitioner permission to
`add prior art references from the Petition in the district court case. See Ex. 2012 at
`9-16 (Defendant’s Preliminary Invalidity Contentions); Ex.2004.
`Additionally, a more recent Samsung decision, Samsung Elecs. Co., Ltd. v.
`Clear Imaging Research LLC, IPR2020-01551, Paper 12 at 13 (P.T.A.B. Feb. 17,
`2021) (“Samsung II”), denied institution when the trial was scheduled to begin more
`than ten months before the due date of the final written decision, and is more closely
`aligned with the facts here. Id. at 13. In Samsung II, the Board noted that the original
`trial date had never changed and was unlikely to ever be delayed. Id. at 11-14. The
`Board agreed with the Patent Owner that this factor weighed heavily in favor of
`denying institution, quoting Fintiv, Paper 11 at 9 (emphasis added) (“If the court’s
`trial date is earlier than the projected statutory deadline, the Board generally has
`
`–2–
`
`

`

`Patent Owner’s Pre-Institution Sur-Reply
`
`weighed this fact in favor of exercising authority to deny institution under NHK.”).
`Id. at 13. See also Cisco Systems, Inc. v. Oyster Optics, LLC, IPR2021-00319,
`Paper 9 at 10-12 (P.T.A.B. June 8, 2021) (finding that trial date seven months before
`Board’s written decision due date favored denial of petition). Such is also the case
`here—the judge in the district court has made clear his preference to maintain the
`current trial date. See Ex. 2001 (First Amended Docket Control Order).
`Petitioner speculates that “it is entirely possible” that Factor 2 may be
`rendered moot due to the district court’s order to narrow asserted claims. Reply at 1.
`This inappropriate speculation should be accorded little weight because it attempts
`to take advantage of Petitioner’s extreme delay in filing its Petition and the late stage
`of the parallel district court case. Petitioner is trying to have its cake and eat it, too—
`on the one hand, Petitioner complains about the scope of the district court case and
`demands the court there to force Patent Owner to narrow to a tiny fraction of the
`original case, then on the other, argues that the Board should rely on that narrowing
`demand to broaden Petitioner’s IPR case. This blatant gamesmanship is an attempt
`to waste the Board’s resources and should not be rewarded.
`Fintiv Factor 3 considers the timing of the petition and the investment in the
`proceeding by the court and the parties. Petitioner claims it “moved with speed and
`diligence” by filing the IPRs five months after Patent Owner served its infringement
`contentions. Reply at 2. Petitioner wrongly complains that Patent Owner “refused
`to narrow the number of claims and issues until service of its infringement
`contentions,” id., ignoring that (1) Petitioner had been on notice of its infringement
`since at least August 31, 2020, and (2) Patent Owner served infringement
`
`–3–
`
`

`

`Patent Owner’s Pre-Institution Sur-Reply
`
`contentions at the time specified by the district court’s docket control order. In any
`event, the relevant date is the date of filing the complaint, not the serving of
`infringement contentions. 35 U.S.C. §315(b). This Petition was filed on June 21,
`2021, nearly ten months after the complaint was filed. Further, this Petition was
`filed nearly four months after Petitioner served its invalidity contentions in the
`district court case. This cuts against Petitioner’s claim of “speed and diligence.”
`Fintiv factor 3 also considers “the amount and type of work already completed
`in the parallel litigation by the court and the parties at the time of the institution
`decision,” including whether “the district court has issued substantive orders related
`to the patent at issue in the petition, this fact favors denial,” and notes that “more
`work completed by the parties and court in the parallel proceeding tends to support
`the argument that the parallel proceeding is more advanced, a stay may be less likely,
`and instituting would lead to duplicative costs.” Fintiv, Paper 11 at 9-10.
`Petitioner’s statement that “[h]ere, by institution the court’s investment regarding
`the patentability of the ’989 patent will be nominal” is a gross understatement. Reply
`at 3. Petitioner recognizes that the district court has already expended resources
`addressing the parties’ claim construction positions and issuing a claim construction
`order.1 Id. But in arguing merely that “a substantial portion of work and trial is yet
`
`1 Petitioner states that the district court’s “construed no ’989 claim term,” Reply at 3,
`but in its expert report, Petitioner advocated for a specific construction of the term
`“common layer” as excluding a “counter line” like that shown in Ohta (a prior art
`reference asserted in the Petition). See Ex.2013 at 5-7 (Flasck Daubert Motion, Dkt.
`196). To the extent Petitioner’s untimely claim construction proposal is allowed,
`Patent Owner has requested additional claim construction briefing that will impact
`Petitioner’s prior-art mappings. See id.
`
`–4–
`
`

`

`Patent Owner’s Pre-Institution Sur-Reply
`
`to come after institution,” Petitioner wholly discounts the significant efforts and
`resources the parties have expended and will expend prior to the institution date of
`January 8, 2022, and fails to provide any examples of the “substantial portion of
`work” that will occur later, apart from trial on February 7. The parties have already
`exchanged expert reports addressing infringement and validity of each of the 135
`originally asserted claims. The parties have taken a collective fourteen days of
`expert depositions, and will take two more in next week. Ex.2015, ¶5 (Klein Decl.).
`Seven of those days are focused solely on validity. Id. Further, by January 8, every
`deadline will have passed except the pretrial conference on January 10 and the
`trial itself. See Ex.2001 at 1-3; Ex.1015 at 3. Thus, all the work relevant to claim
`construction, infringement, validity, claim construction, fact discovery, and expert
`discovery will be completed by the institution date. See Samsung Elecs., IPR2020-
`01551, Paper 12 at 16 (finding significant investment when “some of the work
`relevant to patent validity, including claim construction, fact discovery, and expert
`discovery” had been completed).
`Fintiv Factor 4 evaluates the overlap between issues raised in the Petition and
`in the district court proceeding. “[I]f the petition includes the same or substantially
`the same claims, grounds, arguments, and evidence as presented in the parallel
`proceeding, this fact has favored denial.” Id. at 12. Petitioner leans heavily on its
`purported Sotera-like stipulation, but this stipulation will not serve to simplify the
`district court case. See Reply at 1-2, and 4. Petitioner has filed petitions against
`only seven of the fifteen patents in the district court case. For five of those seven
`patents, Petitioner’s invalidity case involves alleged prior art products in
`
`–5–
`
`

`

`Patent Owner’s Pre-Institution Sur-Reply
`
`combination with the same references asserted in the respective petitions and thus
`would be unaffected by the stipulation because the substance of those references will
`still be at issue. See Ex.2012 at 9-16 (Defendant’s Preliminary Invalidity
`Contentions); see also Ex.2003 at 7 (Defendant’s Motion for leave to Supplement
`Invalidity Contentions) (“Here, [Petitioner] intends to use Plaintiffs’ recently
`produced prior art products, as modified by references of which Plaintiffs have been
`long aware, to invalidate seven of the asserted patents”).
`Further, Patent Owner withdrew its opposition to Petitioner’s Motion for
`Leave to Supplement Invalidity Contentions so that any prior art raised in
`Petitioner’s IPRs could be in the district court case. See Ex.2012. Thus, the Board
`does not face the issue of whether the grounds overlap: they do completely.
`Fintiv Factor 6 considers other circumstances that may impact the Board’s
`exercise of discretion, including the merits. Petitioner’s argument that two of its
`prior art references should not be excluded under 35 U.S.C. § 103(c)(1) because
`“[c]ommon ownership of Abe and Kurahahshi has thus not been shown” is weak.
`JP2001-317147 names Hitachi Ltd. as the “Applicant” as of the “Date of
`Application,” October 15, 2001. See Ex.2007 at 362-64 (File History); see also
`Ex.2014 (English Translation of excerpt of File History Ex.2007). Regarding
`Petitioner’s rebuttal in support of its improper combinations of references, Patent
`Owner stands on the analysis provided in its preliminary response showing the
`merits of this Petition are weak, which further supports denying institution. See
`Paper 7 at 16-49.
`
`–6–
`
`

`

`Dated: November 15, 2021
`
`Respectfully submitted,
`
`Patent Owner’s Pre-Institution Sur-Reply
`
`/Eric J. Klein/
`Eric J. Klein (Reg. No. 51,888)
`Lead Counsel for Petitioner
`eklein@velaw.com
`VINSON & ELKINS L.L.P.
`2001 Ross Avenue, Suite 3900
`Dallas, TX 75201
`Customer No. 22892
`TEL: (214) 220-7700
`FAX: (214) 220-7716
`
`CERTIFICATE OF SERVICE
`The undersigned certifies that, in accordance with 37 C.F.R. §42.6(e) and 37
`
`C.F.R. §42.105, service was made on Petitioner as detailed below.
`
`Date of service November 15, 2021
`Manner of service Via electronic mail by agreement of the parties
`
`–7–
`
`

`

`Patent Owner’s Pre-Institution Sur-Reply
`
`Documents served Patent Owner Japan Display Inc.’s Pre-Institution Sur-Reply
`of United States Patent No. 9,310,654 Pursuant to 35 U.S.C.
`§ 313, 37 C.F.R. § 42.107
`
`Persons served
`
`Lead Counsel
`Joshua L. Goldberg (Reg. No. 59,369)
`joshua.goldberg@finnegan.com
`Finnegan, Henderson, Farabow,
`Garrett & Dunner, LLP
`901 New York Ave NW
`Washington, DC 20001
`Tel: 202-408-4000
`Fax: 202-408-4400
`
`Back-Up Counsel
`Qingyu Yin (Reg. No. 61,329)
`qingyu.yin@finnegan.com
`
`David C. Reese (Reg. No. 67,942)
`david.reese@finnegan.com
`
`Daniel F. Klodowski (Reg. No. 72,693)
`Daniel.klodowski@finnegan.com
`
`Gracie K. Mills (66,946)
`gracie.mills@finnegan.com
`
`Finnegan, Henderson, Farabow,
`Garrett & Dunner, LLP
`901 New York Ave NW
`Washington, DC 20001
`Tel: 202-408-4000
`Fax: 202-408-4400
`
`/Eric J. Klein/
`Eric J. Klein
`Lead Counsel for Petitioner
`Registration No. 51,888
`
`US 8431716
`
`–8–
`
`

This document is available on Docket Alarm but you must sign up to view it.


Or .

Accessing this document will incur an additional charge of $.

After purchase, you can access this document again without charge.

Accept $ Charge
throbber

Still Working On It

This document is taking longer than usual to download. This can happen if we need to contact the court directly to obtain the document and their servers are running slowly.

Give it another minute or two to complete, and then try the refresh button.

throbber

A few More Minutes ... Still Working

It can take up to 5 minutes for us to download a document if the court servers are running slowly.

Thank you for your continued patience.

This document could not be displayed.

We could not find this document within its docket. Please go back to the docket page and check the link. If that does not work, go back to the docket and refresh it to pull the newest information.

Your account does not support viewing this document.

You need a Paid Account to view this document. Click here to change your account type.

Your account does not support viewing this document.

Set your membership status to view this document.

With a Docket Alarm membership, you'll get a whole lot more, including:

  • Up-to-date information for this case.
  • Email alerts whenever there is an update.
  • Full text search for other cases.
  • Get email alerts whenever a new case matches your search.

Become a Member

One Moment Please

The filing “” is large (MB) and is being downloaded.

Please refresh this page in a few minutes to see if the filing has been downloaded. The filing will also be emailed to you when the download completes.

Your document is on its way!

If you do not receive the document in five minutes, contact support at support@docketalarm.com.

Sealed Document

We are unable to display this document, it may be under a court ordered seal.

If you have proper credentials to access the file, you may proceed directly to the court's system using your government issued username and password.


Access Government Site

We are redirecting you
to a mobile optimized page.





Document Unreadable or Corrupt

Refresh this Document
Go to the Docket

We are unable to display this document.

Refresh this Document
Go to the Docket