throbber
Case 1:20-cv-00393-LO-TCB Document 740 Filed 06/17/21 Page 1 of 15 PageID# 20283
`
`IN THE UNITED STATES DISTRICT COURT
`FOR THE EASTERN DISTRICT OF VIRGINIA
`ALEXANDRIA DIVISION
`
`RAI STRATEGIC HOLDINGS, INC. and
`R.J. REYNOLDS VAPOR COMPANY,
`
`Plaintiffs and Counterclaim Defendants,
`
`v.
`
`ALTRIA CLIENT SERVICES LLC; PHILIP
`MORRIS USA INC.; and PHILIP MORRIS
`PRODUCTS S.A.,
`
`Defendants and Counterclaim Plaintiffs.
`
`Case No. 1:20-cv-00393-LO-TCB
`
`REDACTED
`
`REYNOLDS’S REPLY IN SUPPORT OF MOTION FOR RELIEF FROM STIPULATION ON
`DEPOSITION DATES IN LIGHT OF NEW INJUNCTION-RELATED CONTENTIONS FROM
`PHILIP MORRIS PRODUCTS S.A.
`
`

`

`Case 1:20-cv-00393-LO-TCB Document 740 Filed 06/17/21 Page 2 of 15 PageID# 20284
`
`
`
`I.
`II.
`
`III.
`
`TABLE OF CONTENTS
`
`B.
`
`INTRODUCTION ............................................................................................................. 1
`ARGUMENT ..................................................................................................................... 2
`A.
`There is no question that PMP added its injunction-related contentions
`around VEEV for the first time on June 8, weeks after the Court entered
`the stipulation setting Dr. Figlar’s deposition ........................................................ 2
`PMP should not be allowed to simultaneously rely on VEEV as a basis for
`injunctive relief, while refusing to respond to discovery about it .......................... 5
`Permitting Dr. Figlar the courtesy of sitting for deposition only once will
`not prejudice PMP.................................................................................................. 9
`CONCLUSION ................................................................................................................ 10
`
`
`
`C.
`
`
`
`i
`
`

`

`Case 1:20-cv-00393-LO-TCB Document 740 Filed 06/17/21 Page 3 of 15 PageID# 20285
`
`
`I.
`
`INTRODUCTION
`
`Reynolds’s motion is simple, and should not be controversial. Dr. James Figlar, who is
`
`retired and lives abroad, has been designated under Rule 30(b)(6) to testify on behalf of Reynolds
`
`relating to its contentions about why PMP is not entitled to injunctive relief. By stipulation (Dkt.
`
`668), Dr. Figlar is scheduled to testify about these issues on June 24. After that stipulation was
`
`entered, however, PMP altered and materially expanded its injunction contentions—adding claims
`
`around an entirely new product (VEEV) that has never before featured in its contentions, or in this
`
`case generally. Indeed, PMP waited to lodge its new VEEV contentions until the day after this
`
`Court partially denied Reynolds’s motion to stay injunction-related discovery, which motion PMP
`
`had resisted by assuring the Court that fact discovery on these issues was “within weeks of”
`
`completion. (Dkt. 666 at 1.)
`
`To the extent that PMP’s statement to the Court was ever true, it is certainly not true now.
`
`PMP’s introduction of the VEEV product as a new basis for injunctive relief required Reynolds to
`
`serve discovery requests related to that product, which it did promptly on June 11, just three days
`
`after receiving PMP’s new contentions. Reynolds must digest the information that PMP produces
`
`in response and then amend its own counter-contentions accordingly (right now, Reynolds’s
`
`counter-contentions only address IQOS). Only once all of this work is complete can Dr. Figlar
`
`offer complete testimony about Reynolds’s injunction-related contentions. The discovery cannot
`
`be completed by June 24—indeed, PMP’s responses are not even due until June 25, and PMP
`
`apparently has no intention of complying by that date, or any other (Dkt. 724 at 13, n.7)—and so
`
`Reynolds respectfully requests relief from the stipulation (Dkt. 668), so that Dr. Figlar is only
`
`deposed one time, at a mutually convenient date after the parties complete the written and
`
`document discovery occasioned by PMP’s new claims.
`
`PMP’s opposition to this eminently reasonable request lacks merit, especially given that
`
`
`
`1
`
`

`

`Case 1:20-cv-00393-LO-TCB Document 740 Filed 06/17/21 Page 4 of 15 PageID# 20286
`
`
`trial in this matter is not scheduled until April 2022. Unable to defend its own actions, PMP levels
`
`various accusations at Reynolds, and seeks to place blame on Reynolds for supposedly
`
`“delay[ing]” Dr. Figlar’s deposition. (Dkt. 724 at 4.) But none of that can detract from the issue,
`
`which is simple. Reynolds had nothing to do with PMP’s decision to add injunction-related
`
`contentions about VEEV to this case for the first time on June 8. PMP did that, and its decision to
`
`do so has ordinary and predictable consequences—including that Reynolds now has to conduct
`
`additional discovery about those new contentions. Dr. Figlar should not have to sit for deposition
`
`until that discovery is complete, else PMP will surely demand that he be deposed twice. PMP’s
`
`opposition is groundless, and Reynolds’s motion should be granted.
`
`II.
`
`ARGUMENT
`
`A.
`
`There is no question that PMP added its injunction-related contentions
`around VEEV for the first time on June 8, after the Court entered the
`stipulation setting Dr. Figlar’s deposition.
`
`The stipulation fixing Dr. Figlar’s June 24 deposition date was submitted to the Court on
`
`May 27, 2021. (Dkt. 668.) The parties agreed to complete their respective productions of
`
`documents in response to injunction-related requests by June 7. (Dkt. 668.) After both of those
`
`dates passed, however, PMP amended its contentions on June 8, setting out for the first time the
`
`claim that an injunction barring Reynolds’s VUSE products from the U.S. market was justified not
`
`only by the supposed “irreparable harm” the VUSE products were causing to PMP’s IQOS
`
`products in the U.S., but also the future harm that VUSE might someday cause to a different PMP
`
`product (VEEV) that is not—and never has been—sold here. (See Dkt. 709-4.) June 8 is the very
`
`first time that the word VEEV appeared in PMP’s injunction contentions. Those are the facts.
`
`And those facts entitle Reynolds to relief from Dr. Figlar’s stipulated deposition date. (See Dkt.
`
`716 at 2-5.)
`
`PMP’s assertion that Reynolds “had full knowledge” that its claim for injunctive relief was
`
`
`
`2
`
`

`

`Case 1:20-cv-00393-LO-TCB Document 740 Filed 06/17/21 Page 5 of 15 PageID# 20287
`
`
`in fact grounded on the VEEV product as early as April 9, when PMP served its initial injunction
`
`contentions, strains credulity. (Dkt. 721 at 3.) Reynolds attached PMP’s April 9 contentions as
`
`Exhibit 1 to its Motion. (Dkt. 709-1.) As the Court can see for itself, PMP never mentioned the
`
`VEEV product. Not once. Instead, the only PMP product discussed in all 36 pages of those
`
`contentions as providing a basis for injunctive relief was IQOS. (Dkt. 709-1.) PMP nevertheless
`
`claims that Reynolds should have known that PMP’s injunction request was somehow tied to
`
`VEEV because—in addition to extensively discussing IQOS—the April 9 contentions also vaguely
`
`alluded to PMP’s other “past, present, and future non-combustible product offerings in the United
`
`States.” (Dkt. 721 at 8.) If it were true that Reynolds should have discerned from that hazy phrase
`
`that PMP planned to pin its injunction case on VEEV—indeed, if PMP even thought it were true—
`
`then one wonders why PMP felt any need to issue new contentions on June 8 that specifically
`
`spelled out PMP’s arguments around VEEV.
`
`The answer, of course, is that PMP’s assertion that it “disclosed its reliance” on VEEV on
`
`April 9 is not true. Reynolds did not know that PMP was putting forward the VEEV product as a
`
`basis for injunctive relief until PMP served contentions saying so, which it did for the first time on
`
`June 8.1 Indeed, after reviewing the April 9 contentions from PMP (which included only the vague
`
`reference to “future” PMP product “offerings”), Reynolds gave its responses to certain Requests
`
`for Admission that PMP had served, purportedly as part of discovery related to the claim for
`
`injunction relief. These included, for example, requests to “Admit that Reynolds is developing a
`
`product to compete against the VEEV e-cigarette”; and to “Admit that Reynolds has conducted
`
`
`1 PMP notes that it referenced possible arguments around VEEV in its opposition to Reynolds’s
`motion to stay (see Dkt. 666 at 11-12). That is true, and Reynolds replied the very next day that,
`if PMP went forward to actually add injunction-related contentions around VEEV—as opposed to
`merely threatening it in a brief, then Reynolds would have to serve new discovery requests relating
`to that product. (Dkt. 675 at 9.)
`
`
`
`3
`
`

`

`Case 1:20-cv-00393-LO-TCB Document 740 Filed 06/17/21 Page 6 of 15 PageID# 20288
`
`
`product evaluations of VEEV.” (See Reynolds Ex. 6, [Reynolds’s Objections and Responses to
`
`PMP’s Eighth Set of Requests for Admission (Nos. 360-405)], at 40-42.) As to these VEEV-
`
`specific requests, Reynolds objected and refused to answer on the ground that the requests were
`
`“not directed to discovery related to PMP’s claim for injunctive relief, which is the only topic for
`
`discovery permitted by the Court to be taken out of time.” (Id.) Reynolds served these responses
`
`on May 11, weeks after reviewing PMP’s April 9 injunctive-relief contentions, and clearly
`
`communicated its understanding that the VEEV product was not related to PMP’s claim for
`
`injunctive relief. PMP never pushed back on this response, nor sought to correct Reynolds’s
`
`understanding of the nature of PMP’s claims.
`
`The reason for PMP’s behavior is clear: As of May 11, when Reynolds served those
`
`responses, VEEV was not the subject of PMP’s claim for injunctive relief. IQOS was. The only
`
`reason that changed was because, on May 14, Judge Cheney issued the Initial Determination in
`
`the parallel ITC Investigation, finding that IQOS infringes two valid Reynolds patents and
`
`recommending a limited exclusion order prohibiting importation of the IQOS products into the
`
`United States. (See Dkt. 709 at 4.) As this Court appropriately recognized in ruling on Reynolds’s
`
`motion to stay, that Initial Determination, if upheld, “undercuts the irreparable harm undergirding
`
`PMP’s claim for injunctive relief.” (Dkt. 702.) So, on the very next day after the Court ruled, and
`
`despite assuring the Court that fact discovery on injunctive relief issues was mere “weeks” from
`
`completion (Dkt. 666 at 1), PMP served its new contentions, which for the first time articulated
`
`theories of irreparable harm based on the VEEV product.
`
`PMP’s attempt to brush off its newfound VEEV contentions as “neither ‘new’ nor ‘late-
`
`disclosed,’” nor anything that expands the scope of injunctive-related issues, does not hold water.
`
`(Dkt. 724 at 7-8.) The VEEV contentions are new; the Court need only compare the April 9
`
`
`
`4
`
`

`

`Case 1:20-cv-00393-LO-TCB Document 740 Filed 06/17/21 Page 7 of 15 PageID# 20289
`
`
`contentions (no VEEV) with the June 8 contentions (VEEV) to confirm this. And the new
`
`contentions absolutely change the scope of injunction-related issues. Previously, PMP linked its
`
`injunction request solely to IQOS, and Reynolds conformed its responsive counter-contentions
`
`accordingly.2 (See Dkt. 709-2.) Consistent with the Court’s instruction to “limit [discovery] as
`
`much as you can,” (Dkt. 532 at 10-11), Reynolds took PMP at its word that its case for injunctive
`
`relief would be limited to IQOS, the only product PMP identified. Now, PMP wants to shift its
`
`contentions to include VEEV—a vaping product that is not even sold in the United States, and its
`
`position is that Reynolds should have guessed this was so long before June 8, when PMP actually
`
`said it. That is not how civil discovery proceeds, and certainly not when the stakes are as high as
`
`they are here. The injunction that PMP seeks would bar Reynolds’s popular VUSE line of products
`
`from the marketplace entirely, which would inexorably cause serious harm to Reynolds.
`
`Accordingly, any change to PMP’s asserted grounds—and certainly one as significant as adding a
`
`wholly new product to the calculus—is important, notwithstanding PMP’s attempts to suggest
`
`otherwise. Reynolds should have a full and fair opportunity to meet and refute these new
`
`contentions through discovery.
`
`B.
`
`PMP should not be allowed to simultaneously rely on VEEV as a basis for
`injunctive relief, while refusing to respond to discovery about it.
`
`Now that PMP has introduced VEEV to the injunction case, Reynolds requires VEEV-
`
`related discovery to supplement its own response to PMP’s contention interrogatory and to explain
`
`
`2 PMP points to Reynolds’s response to its RFP 242, which sought VEEV documents, to claim
`that Reynolds’s need to collect and review VEEV-related documents is “meritless.” (Dkt. 724 at
`9.) That RFP was served March 26, and Reynolds responded April 9, all well before PMP ever
`proffered contentions suggesting that VEEV was a basis for its injunction request. Reynolds
`obviously needs to revisit the issue now that PMP’s contentions on VEEV have changed.
`Moreover, RFP 242 was directed by PMP to Reynolds; Reynolds has not yet had an opportunity
`to direct similar requests back to PMP. It had no reason to do so before seeing the new contentions
`on June 8, but it quickly moved to serve such requests on June 11. Once PMP responds and
`produces its own information, Reynolds can amend its own injunction-related contentions.
`
`
`
`5
`
`

`

`Case 1:20-cv-00393-LO-TCB Document 740 Filed 06/17/21 Page 8 of 15 PageID# 20290
`
`
`why the VEEV product would not be a basis for granting PMP injunctive relief. Only once that is
`
`done can Reynolds prepare Dr. Figlar, its Rule 30(b)(6) designee, to testify about Reynolds’s
`
`contentions in full. (Dkt. 709 at 6.) If Dr. Figlar sits for deposition on June 24 as required by the
`
`stipulation, he will—through no fault of his own or of Reynolds—be unprepared to testify fully as
`
`to Reynolds’s contentions around VEEV, because Reynolds will not even be in a position to submit
`
`its counter-contentions by that date. This places Dr. Figlar, who is retired, at a clear risk of being
`
`forced to testify twice, which would be inefficient and prejudicial.
`
`PMP insists that the parties have already conducted “significant discovery on VEEV” and
`
`VEEV-related injunctive discovery “falls within the scope of” discovery to date, despite its failure
`
`to identify VEEV as a basis for injunctive relief until June 8. (Dkt. 724 at 9.) Discovery on its
`
`new theory, PMP says, is “unnecessary” or even “unwarranted.” (Dkt. 724 at 10-11.) PMP is
`
`wrong.
`
`First, and to be very clear, before seeing PMP’s new contentions on June 8, Reynolds did
`
`not serve any discovery requests directed to VEEV in this case. Period. The fact that VEEV may
`
`have been mentioned in stray documents produced by PMP that were otherwise responsive to
`
`requests that Reynolds did serve (because they also mentioned IQOS, for example) is a far cry
`
`from saying that Reynolds already conducted full discovery on the VEEV product. PMP suggests
`
`that VEEV discovery “falls within the scope of Reynolds’ already-served injunctive relief
`
`discovery,” but that is belied by PMP’s own responses to those very requests. For example,
`
`Reynolds served a request for all documents that “PMP relies on to support any contention that
`
`Plaintiffs’ VUSE products have taken away, are taking away, or are expected to take away sales
`
`of Defendants’ IQOS products in the United States.” (See Reynolds Ex. 7 [PMP’s Response to
`
`Plaintiffs’ Tenth Set of RFPS] at 11-13.) This request is totally consistent with Reynolds’s
`
`
`
`6
`
`

`

`Case 1:20-cv-00393-LO-TCB Document 740 Filed 06/17/21 Page 9 of 15 PageID# 20291
`
`
`understanding that IQOS was the sole subject of PMP’s injunction contentions.
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`7
`
`

`

`Case 1:20-cv-00393-LO-TCB Document 740 Filed 06/17/21 Page 10 of 15 PageID# 20292
`
`
`(Reynolds Ex. 8 [PMP’s Response to Reynolds’s First Set of Interrogatories], at 7-8.) As the Court
`
`can plainly see, VEEV is nowhere to be found. Again, the fact that PMP may have produced a
`
`handful of documents that mention VEEV is happenstance; this did not happen because Reynolds
`
`served requests directed to VEEV, or because PMP agreed to search for and provide them. That
`
`important task remains to be done, and in response to the requests served by Reynolds on June 11.
`
`Second, PMP’s claim that “VEEV is no surprise to Reynolds” is both true as a general
`
`matter, and also irrelevant to the dispute at hand. (Dkt. 724 at 10.) Reynolds never suggested that
`
`it was completely unaware of the existence of the VEEV product; it was aware of that product,
`
`just as it is aware of myriad other products that PMP and its affiliates offer throughout the world.
`
`But general market knowledge is one thing; the knowledge necessary to defend against a sweeping
`
`injunction claim in a lawsuit is quite another. Reynolds knew about the IQOS product independent
`
`of this litigation, too. Yet PMP has never suggested, nor could it, that this industry knowledge
`
`obviated the need for discovery in this case. The same holds true for VEEV. PMP introduced that
`
`product into its injunction contentions on June 8, which means Reynolds must now shift its focus
`
`on that product from that of a business industry observer to that of a litigant faced with a claim for
`
`injunctive relief. That is the purpose of discovery in this, and every other, case.
`
`Third, as Reynolds explained, it has taken no depositions directed to VEEV. (Dkt. 709 at
`
`10.) PMP points to
`
`
`
`8
`
`
`
`
`
`
`
`
`
`
`
`
`
`

`

`Case 1:20-cv-00393-LO-TCB Document 740 Filed 06/17/21 Page 11 of 15 PageID# 20293
`
`
`
`
`
`
`
`C.
`
`Permitting Dr. Figlar the courtesy of sitting for deposition only once will not
`prejudice PMP.
`
`Reynolds is not trying to avoid discovery, nor to unreasonably delay Dr. Figlar’s
`
`deposition. When PMP added its new VEEV contentions, Reynolds proposed an orderly plan
`
`whereby VEEV-related discovery, including updated counter-contentions from Reynolds, could
`
`be completed and then the witnesses for both sides could be completed by mid-August, months
`
`before the scheduled April 2022 trial date. (Dkt. 709 at 7-8.) Reynolds’s plan would prevent any
`
`of the witnesses from being deposed twice. PMP refused, however, insisting that all depositions
`
`go forward on the dates in the stipulation, and it now claims that it will be prejudiced if Dr. Figlar
`
`is not forced to testify before VEEV-related discovery is complete. (Dkt. 724 at 14-15.) PMP
`
`identifies no such prejudice, however, and there is none.
`
`The Court set trial in this matter for April 2022. Without citation, PMP asserts that Dr.
`
`Figlar must testify before discovery on VEEV is complete or else “frustrate the Court’s plan.”
`
`(Dkt. 724 at 15.) In PMP’s view, when the Court ruled on Reynolds’s motion to stay and instructed
`
`that fact discovery on the injunction issues should “proceed through its conclusion” (Dkt. 702),
`
`that meant that everything was to be completed by “June 25.” (Dkt. 724 at 14.) Of course, the
`
`Court never actually said that. And even if the Court had understood when it entered that Order
`
`on June 7 that injunction discovery could be completed in a matter of a few weeks—which would
`
`have been a fair assumption, since that is exactly what PMP said in opposing the motion to stay—
`
`that understanding was upended the very next day, when PMP served its new contentions around
`
`VEEV. PMP not only waited to do this until the day after the Court ruled on the stay motion, it
`
`also happened to be the day after the parties had agreed to complete all document production in
`
`
`
`9
`
`

`

`Case 1:20-cv-00393-LO-TCB Document 740 Filed 06/17/21 Page 12 of 15 PageID# 20294
`
`
`response to injunction-specific requests. PMP appears to think that the Court’s June 7 ruling on
`
`the stay motion and the parties’ agreed June 7 production deadline provide some sort of safe harbor
`
`that allows PMP to change its injunction contentions the very next day to add a new product, yet
`
`remain immune from further discovery. That is certainly not something to which Reynolds ever
`
`agreed.
`
`Despite injecting a new theory the day after production of injunction-related documents
`
`was to have concluded, PMP’s position appears to be that it would be “orderly” for Figlar to be
`
`deposed twice. (Dkt 724 at 14.) Not so. Trial will not take place until April 2022. There is much
`
`for the parties to do before Dr. Figlar can be deposed on all of the topics for which he is designated.
`
`PMP must respond to Reynolds’s injunction-related discovery requests, including those related to
`
`VEEV, which responses are not even due until June 25—after Dr. Figlar is currently scheduled to
`
`testify. And PMP has now telegraphed its intention to refuse to comply with Reynolds’s discovery
`
`requests (Dkt. 724 at 13, n.7), which will only cause further delay if Reynolds is forced to move
`
`to compel. Again, this is in PMP’s hands. However long PMP chooses to drag this out, Reynolds
`
`is entitled to discovery on VEEV, is entitled to amend its own contentions in consideration of that
`
`discovery, and is entitled to prepare Dr. Figlar as its corporate designee to testify on “[t]he factual
`
`bases underlying [Reynolds’s] contention, including [Reynolds’s] response to Interrogatory No.
`
`30 . . . that PMP has not suffered irreparable injury,” based on the full scope of PMP’s contentions,
`
`including the new contentions around VEEV.
`
`III. CONCLUSION
`Reynolds’s Motion for Relief From Stipulation on Deposition Dates in Light of New
`
`Injunction-Related Contentions from Philip Morris Products S.A. should be granted. Reynolds
`
`respectfully requests that the Court enter an Order directing that, notwithstanding Dkt. 668, the
`
`deposition of Dr. Figlar will not go forward on June 24. Instead, Dr. Figlar will be produced for
`
`
`
`10
`
`

`

`Case 1:20-cv-00393-LO-TCB Document 740 Filed 06/17/21 Page 13 of 15 PageID# 20295
`
`
`deposition on a mutually-agreed date after Reynolds and PMP have completed discovery relating
`
`to PMP’s new contentions about the VEEV product.
`
`
`
`
`
`11
`
`

`

`Case 1:20-cv-00393-LO-TCB Document 740 Filed 06/17/21 Page 14 of 15 PageID# 20296
`
`
`Dated: June 17, 2021
`
`
`
`Stephanie E. Parker
`JONES DAY
`1221 Peachtree Street, N.E.
`Suite 400
`Atlanta, GA 30361
`Telephone: (404) 521-3939
`Facsimile: (404) 581-8330
`Email: separker@jonesday.com
`
`
`Anthony M. Insogna
`JONES DAY
`4655 Executive Drive
`Suite 1500
`San Diego, CA 92121
`Telephone: (858) 314-1200
`Facsimile: (844) 345-3178
`Email: aminsogna@jonesday.com
`
`William E. Devitt
`JONES DAY
`77 West Wacker
`Suite 3500
`Chicago, IL 60601
`Telephone: (312) 269-4240
`Facsimile: (312) 782-8585
`Email: wdevitt@jonesday.com
`
`Sanjiv P. Laud
`JONES DAY
`90 South Seventh Street
`Suite 4950
`Minneapolis, MN 55402
`Telephone: (612) 217-8800
`Facsimile: (844) 345-3178
`Email: slaud@jonesday.com
`
`
`Respectfully submitted,
`
`
`
`
`
` /s/ David M. Maiorana
`David M. Maiorana (VA Bar No. 42334)
`Ryan B. McCrum
`JONES DAY
`901 Lakeside Ave.
`Cleveland, OH 44114
`Telephone: (216) 586-3939
`Facsimile: (216) 579-0212
`Email: dmaiorana@jonesday.com
`Email: rbmccrum@jonesday.com
`
`John J. Normile
`JONES DAY
`250 Vesey Street
`New York, NY 10281
`Telephone: (212) 326-3939
`Facsimile: (212) 755-7306
`Email: jjnormile@jonesday.com
`
`
`Alexis A. Smith
`JONES DAY
`555 South Flower Street
`Fiftieth Floor
`Los Angeles, CA 90071
`Telephone: (213) 243-2653
`Facsimile: (213) 243-2539
`Email: asmith@jonesday.com
`
`Charles B. Molster, III Va. Bar No. 23613
`THE LAW OFFICES OF
`CHARLES B. MOLSTER, III PLLC
`2141 Wisconsin Avenue, N.W. Suite M
`Washington, DC 20007
`Telephone: (703) 346-1505
`Email: cmolster@molsterlaw.com
`
`Counsel for Plaintiffs RAI Strategic Holdings,
`Inc. and R.J. Reynolds Vapor Company
`
`
`
`1
`
`

`

`
`Case 1:20-cv-00393-LO-TCB Document 740 Filed 06/17/21 Page 15 of 15 PageID# 20297
`
`CERTIFICATE OF SERVICE
`
`
`
`I hereby certify that on 17th day of June, 2021, a true and correct copy of the foregoing was
`
`served using the Court’s CM/ECF system, with electronic notification of such filing to all counsel
`
`
`
`
`
`/s/ David M. Maiorana
`David M. Maiorana (VA Bar No. 42334)
`JONES DAY
`901 Lakeside Ave.
`Cleveland, OH 44114
`Telephone: (216) 586-3939
`Facsimile: (216) 579-0212
`Email: dmaiorana@jonesday.com
`
`Counsel for Plaintiffs RAI Strategic Holdings,
`Inc. and R.J. Reynolds Vapor Company
`
`of record.
`
`
`
`
`
`
`
`
`
`
`
`

This document is available on Docket Alarm but you must sign up to view it.


Or .

Accessing this document will incur an additional charge of $.

After purchase, you can access this document again without charge.

Accept $ Charge
throbber

Still Working On It

This document is taking longer than usual to download. This can happen if we need to contact the court directly to obtain the document and their servers are running slowly.

Give it another minute or two to complete, and then try the refresh button.

throbber

A few More Minutes ... Still Working

It can take up to 5 minutes for us to download a document if the court servers are running slowly.

Thank you for your continued patience.

This document could not be displayed.

We could not find this document within its docket. Please go back to the docket page and check the link. If that does not work, go back to the docket and refresh it to pull the newest information.

Your account does not support viewing this document.

You need a Paid Account to view this document. Click here to change your account type.

Your account does not support viewing this document.

Set your membership status to view this document.

With a Docket Alarm membership, you'll get a whole lot more, including:

  • Up-to-date information for this case.
  • Email alerts whenever there is an update.
  • Full text search for other cases.
  • Get email alerts whenever a new case matches your search.

Become a Member

One Moment Please

The filing “” is large (MB) and is being downloaded.

Please refresh this page in a few minutes to see if the filing has been downloaded. The filing will also be emailed to you when the download completes.

Your document is on its way!

If you do not receive the document in five minutes, contact support at support@docketalarm.com.

Sealed Document

We are unable to display this document, it may be under a court ordered seal.

If you have proper credentials to access the file, you may proceed directly to the court's system using your government issued username and password.


Access Government Site

We are redirecting you
to a mobile optimized page.





Document Unreadable or Corrupt

Refresh this Document
Go to the Docket

We are unable to display this document.

Refresh this Document
Go to the Docket