Case 6:15-cv-00907-RWS-KNM Document 102-2 Filed 07/08/16 Page 1 of 4 PageID #: 2796
`
`Exhibit A
`
`

`

`Case 6:15-cv-00907-RWS-KNM Document 102-2 Filed 07/08/16 Page 2 of 4 PageID #: 2797
`
`Case 1:15-cv-00319-AT Document 25 Filed 08/28/15 Page 1 of 3
`
`IN THE UNITED STATES DISTRICT COURT
`FOR THE NORTHERN DISTRICT OF GEORGIA
`ATLANTA DIVISION
`
`EMERSON ELECTRIC CO., et al.,
`
`Plaintiffs,
`
`v.
`
`SIPCO LLC, et al.,
`
`Defendants.
`
`CIVIL ACTION NO.
`1:15-CV-0319-AT
`
`SCHEDULING ORDER
`
`Upon review of the information contained in the Joint Preliminary
`
`Planning Report and Discovery Plan form completed by the parties, ("JPR", Doc.
`
`22), the Court ORDERS that the time limits for adding parties amending the
`
`pleadings, filing motions, completing discovery, and discussing settlement are as
`
`stated in JPR, except as modified on Exhibit A attached hereto.
`
`IT IS SO ORDERED this 28th day of August, 2015.
`
`Amy To 'rfberfig"gi
`UnitedStates istrict Judge
`
`

`

`Case 6:15-cv-00907-RWS-KNM Document 102-2 Filed 07/08/16 Page 3 of 4 PageID #: 2798
`
`Case 1:15-cv-00319-AT Document 25 Filed 08/28/15 Page 2 of 3
`
`EXH B T A
`
`EventiDescription
`
`Rule 26(a)(1) Initial Disclosures due (LR 26.1)
`
`Begin discovery (LR 26.2(A))
`
`Date
`
`August 26, 2015
`
`August 26, 2015
`
`Parties to file Joint Preliminary Report and Discovery Plan
`
`August 26, 2015
`
`Parties to file Stipulated Protective Order of Confidentiality
`(see LPR 2.2)
`
`September 9, 2015
`
`Plaintiff must serve Disclosure of Invalidity Contentions
`for patent claims it asserted in the complaint (including
`copies of all prior art identified but not in file histories)
`(LPR 4.3 & 4.4a)
`
`Defendant must serve Disclosure of Infringement
`Contentions (LPR 4.1 & 4.4b)
`
`October 26, 2015
`
`November 25, 20.16
`
`Plaintiff must serve Response to Infringement Contentions
`(LPR 4.2 & 4.4c)
`
`December 15, 2015
`
`Plaintiff must serve Disclosure of Invalidity Contentions
`for patent claims asserted by Defendants in the Disclosure
`of Infringement Contentions not addressed by Plaintiffs'
`first Disclosure of Invalidity Contentions
`
`Each party to simultaneously exchange a list of claim
`terms, phrases or clauses that should be construed by Court,
`and identify any IPF claim elements (Proposed Tains,
`for Construction") (LPR 6.1)
`
`December 23, 2015
`
`December 23, 2015
`
`

`

`Case 6:15-cv-00907-RWS-KNM Document 102-2 Filed 07/08/16 Page 4 of 4 PageID #: 2799
`
`Case 1:15-cv-00319-AT Document 25 Filed 08/28/15 Page 3 of 3
`
`Even /Description
`
`Parties to meet and confer on Proposed Terms for
`Construction (LPR 6.1b)
`
`Parties shall simultaneously exchange a preliminary
`proposed construction for each claim term, phrase, or
`clause and exchange preliminary identification of extrinsic
`evidence supporting construction (dictionary definitions,
`treatise cites, prior art, proposed testimony) (LPR 6.2)
`
`Parties to meet and confer to narrow claim construction
`issues and finalize Joint Claim Construction Statement
`(LPR 6.2c)
`
`Parties shall file a Joint Claim Construction Statement
`(LPR 6.3)
`
`Date
`
`After
`December 23, 2015
`
`January 12, 2016
`
`After
`January 12, 2016
`
`February 2, 2016
`
`Complete claim construction discovery (LPR 6.4)
`
`February 17, 2016
`
`Opening claim construction brief (LPR 6.5)
`
`Responsive claim construction brief (LPR 6.5)
`
`Plaintiff must serve advice of counsel and related
`information rebutting a willfulness charge (LPR 5.2)
`
`Fact Discovery Closes
`
`Initial Rule 26 Expert Witness disclosures due on issues
`that a party bears the burden of proof (for non-claim
`construction issues) (LPR 7.1)
`
`Second Rule 26 Expert Witness disclosures due on issues
`that opposing party bears the burden of proof (for non-
`claim constriction issues) (LPR 7.1)
`
`March 3, 2016
`
`March 23, 2016
`
`May 27, 2016
`
`June 27, 2016
`
`July 27, 2016
`
`August 26, 2016
`
`Rebuttal expert disclosures (when permitted by Rule 26)
`(LPR 7.1)
`
`September 6, 2016
`
`Expert depositions (LPR 7.2)
`
`Summary Judgment Motions due (LR 56.1D)
`
`September 13-
`October 13, 2016
`
`November 14, 2016
`
`Briefs Opposing Summary Judgment due (LR 7.1B)
`
`December 7, 2016
`
`Reply Briefs for Summary Judgment (LR 7.1C)
`
`December 21, 2016
`
`

This document is available on Docket Alarm but you must sign up to view it.


Or .

Accessing this document will incur an additional charge of $.

After purchase, you can access this document again without charge.

Accept $ Charge
throbber

Still Working On It

This document is taking longer than usual to download. This can happen if we need to contact the court directly to obtain the document and their servers are running slowly.

Give it another minute or two to complete, and then try the refresh button.

throbber

A few More Minutes ... Still Working

It can take up to 5 minutes for us to download a document if the court servers are running slowly.

Thank you for your continued patience.

This document could not be displayed.

We could not find this document within its docket. Please go back to the docket page and check the link. If that does not work, go back to the docket and refresh it to pull the newest information.

Your account does not support viewing this document.

You need a Paid Account to view this document. Click here to change your account type.

Your account does not support viewing this document.

Set your membership status to view this document.

With a Docket Alarm membership, you'll get a whole lot more, including:

  • Up-to-date information for this case.
  • Email alerts whenever there is an update.
  • Full text search for other cases.
  • Get email alerts whenever a new case matches your search.

Become a Member

One Moment Please

The filing “” is large (MB) and is being downloaded.

Please refresh this page in a few minutes to see if the filing has been downloaded. The filing will also be emailed to you when the download completes.

Your document is on its way!

If you do not receive the document in five minutes, contact support at support@docketalarm.com.

Sealed Document

We are unable to display this document, it may be under a court ordered seal.

If you have proper credentials to access the file, you may proceed directly to the court's system using your government issued username and password.


Access Government Site

We are redirecting you
to a mobile optimized page.





Document Unreadable or Corrupt

Refresh this Document
Go to the Docket

We are unable to display this document.

Refresh this Document
Go to the Docket