throbber
Case 2:17-cv-00513-JRG Document 257-4 Filed 01/04/19 Page 1 of 4 PageID #: 16238
`Case 2:17-cv-00513-JRG Document 257-4 Filed 01/04/19 Page 1 of 4 PageID #: 16238
`
`
`
`
`
`EXHIBIT 4
`
`
`
`
`
`EXHIBIT 4
`
`
`
`
`
`
`

`

`Case 2:17-cv-00513-JRG Document 257-4 Filed 01/04/19 Page 2 of 4 PageID #: 16239
`Case 2:17-cv-00513-JRG Document 257-4 Filed 01/04/19 Page 2 of 4 PageID #: 16239
`
`1.1.
`
`KEY ACCOMPLISHMENTS
`
`A. Task Force XXI AWE. Completed all activities at NTC, including the de-install of the
`Applique equipment from the 1-5 Btn.
`
`B. Program Planning. Provided technical, cost, and schedule estimates for various
`alternatives and excursions (for example, adding a late 1998 or early 1999 NTC
`rotation to the program plan, adding a Limited User Test [LUT] to the program plan,
`moving the FDT&E fi'om 1998 2’ system Version 2 to 1999 2’ system Version 3, etc.)
`to PM Applique upon request, for their use in refining the program plan for the next
`several years in light of the results of the TF XX] AWE, and emerging Army decisions
`regarding the future of the FBCBZ program.
`
`C. Lessons-Learned. Completed initial Cut at developing “lessons-learned” fi'om system
`version 1 and the TF XXI AWE. Eighty-five (85) specific technical improvements to
`the system were identified, and tentatively scheduled into future releases of the FBCB2
`system (although these have not yet been finalized with PM Applique, and some
`adjustments and additions may still be made to this list). More than fifty (50) of these
`are now scheduled to be incorporated into the Version 2 system to be brought to the
`FBC B2 test milestone (FDT&E or LUT) in 1998; these are over-and-above
`previously-planned capabilities for FBCB2 Version 2.
`
`D. Tactical Interth. Made substantial progress on the design of the “next-generation”
`Tactical lnterNet, including coordination with other “stake-holders” in the Tactical
`lnterNet process. Specific activities include:
`
`1. Continued video teleconferences on Tactical lntemet (T1) implementation topics
`with participation from PM Applique, PM TRCS, PM JTACS, CECOM, ITT,
`
`HAC, TRW, and others. These meetings, which are held approximately every two
`weeks, provide a forum for discussionfiresolution of technical issues related to the
`TI. Examples of topics discussed to date include mini-router concept, approach to
`network lnonjtoringhnanagement, and emerging results from data analysis.
`
`2. Reached agreement among the TI “stake-holder” group (PM Applique, PM TRCS,
`CECOM RDEC, PEO C3s, ITT, HAC, TRW, and others) on key elements of the
`design and functionality of the T1 for the 1998 FBC B2 LUT (FBCBZ system
`Version 2). Functionality and top-level design for the key Tl threads (unicast,
`broadcast, and multicast) have been agreed to, with a small number of topics for
`further discussion identified, and a process and time-frame for reaching closure
`agreed to. A concept for the schedule to reach the 1998 test milestone (a LUT in
`August 1998 at Ft. Hood) has also been agreed to, with topics requiring further
`coordination identified and a process and time-frame for reaching closure agreed
`
`SIEGEL000789
`
`

`

`Case 2:17-cv-00513-JRG Document 257-4 Filed 01/04/19 Page 3 of 4 PageID #: 16240
`Case 2:17-cv-00513-JRG Document 257-4 Filed 01/04/19 Page 3 of 4 PageID #: 16240
`
`D24518-003A
`
`13 May 1997
`
`3. Prepared original draft of the FBCB2 Performance Description Document
`(FPDD). This document will be used in place of the Applique Performance
`
`Description Document for documenting the analysis and results of performance
`related issues. This document will be released to the government in early May.
`
`4. Prepared and internally coordinated an updated outline for the FBCB2 Interface
`Control Document (C DRL BOOS).
`
`D. Communications Studies and Analyses
`
`1. Continued planning process to identify, establish, prioritize and schedule critical
`systems engineering studies needed to support hardware and software design
`activities. Studies include expanded Situational Awareness (Friendly, Enemy and
`Sensor data) dissemination and correlation, Sealeability, Reliable Delivery of C2
`
`messages and server implementation and distribution schemes and security.
`
`2.
`
`Initiated decomposition of Technical Performance Measures to support subsystem
`performance requirement definition.
`
`3. Coordinated Operational Architecture activities with Ed McCarthy (Mitre) to
`ensure the products of the our analyses can be fed into the Operational
`Architecture database.
`
`4. Coordinated Plans with the Signal Center to visit the to visit Army Schools in
`support of the Operational Architecture analyses (FIO). A project coordination
`meeting will be held in early May to make sure project (software, hardware, ILS,
`communications) information requirements are identified.
`
`Presented the evolving FBCBZ Security concepts and requirements to the project
`staff
`
`U1
`
`1.
`
`2. Developing plan to evaluated Mil—3 (OPNET) OSPF module. Plans are to
`determine feasibility of using this module to suppon dynamic routing in the
`DBCM.
`
`3. Documented and distributed for review the SE review, the results of analyses used
`to determine performance requirements in support of ADOC and SESDD. These
`
`results were incorporated into the F PDD which is scheduled to be delivered to the
`Government in Early May.
`
`SIEGEL000794
`
`

`

`Case 2:17-cv-00513-JRG Document 257-4 Filed 01/04/19 Page 4 of 4 PageID #: 16241
`Case 2:17-cv-00513-JRG Document 257-4 Filed 01/04/19 Page 4 of 4 PageID #: 16241
`
`D24518-003A
`
`13 May 199?
`
`F.
`
`Interfacesllntcroperability
`
`1. BCIS European demonstration (T&M). Installed Applique Version [.02 software
`and map data onto the PND computers. Collected and shipped equipment to
`Germany in preparation for end of May activity.
`
`CBDCOM (T&M). Successfiilly completed field integration of Applique software
`Version l.0.2b with C BDCOM patch with the CP LR-BSDS during the week of 7
`
`April. Prior exchange of VMF message bit streams greatly reduced the integration
`time. A minor problem was discovered and fixed where the serial HF baud rate
`was set for 9600 bps instead of 4800 bps specified in the ICD. All 5 DSSU
`computers were configured with the final release of 1.0.2b with CBDCOM patch
`and shipped to three different locations (2 to Aberdeen, MA 2 to Orlando, FL and
`l to MICAD contractor in Glendale, CA). MICAD integration was proposed as a
`separate task option due to its schedule. Additional fiJnds were received to
`support this integration effort which is schedule for JulyfAugust [997. This effort
`will produce a new software Version 1.0.20 that incorporate fixes discovered
`during the integration process with MICAD.
`
`G. RFPI. Submitted an early (rough) release of RFPI address book assignments to
`
`Applique URNs. Supported numerous questions following release of this data.
`
`1. Completed update to Applique database to include 70 new Tactical Unit Names
`mapped against existing URNs used during TF XXI. Suecessfitlly integrated patch
`floppies with Applique software Version 1.0.2a including all patches up to patch
`#13. Modified SA server assignments to ensure proper SA dissemination.
`
`Began on—site support at Ft. Benning, GA and Huntsville, AL starting 21 April to
`begin integration of RFPI patch with LDTOC, MODS AF, and DCZ equipment.
`Patch was fully installed and tested in 2 days. Subsequent efforts focused on inter-
`site communication using DIS network, the injection of MODSAF VMF position
`reports for virtual units, and DC2 interface with ABCS. Discovered that
`MODSAF was changing the source URN of each position report to match the
`
`URN of the unit that was being reported. Previous discussions assumed that
`MODSAF would be injected the same as JANUS data (fi'om a single URN with a
`role code of 480). MODSAF was changed to act the same as JANUS.
`
`2.1.2. Major difficulties encountered, and plans to overcome those difficulties
`
`None
`
`SIEGEL000795
`
`

This document is available on Docket Alarm but you must sign up to view it.


Or .

Accessing this document will incur an additional charge of $.

After purchase, you can access this document again without charge.

Accept $ Charge
throbber

Still Working On It

This document is taking longer than usual to download. This can happen if we need to contact the court directly to obtain the document and their servers are running slowly.

Give it another minute or two to complete, and then try the refresh button.

throbber

A few More Minutes ... Still Working

It can take up to 5 minutes for us to download a document if the court servers are running slowly.

Thank you for your continued patience.

This document could not be displayed.

We could not find this document within its docket. Please go back to the docket page and check the link. If that does not work, go back to the docket and refresh it to pull the newest information.

Your account does not support viewing this document.

You need a Paid Account to view this document. Click here to change your account type.

Your account does not support viewing this document.

Set your membership status to view this document.

With a Docket Alarm membership, you'll get a whole lot more, including:

  • Up-to-date information for this case.
  • Email alerts whenever there is an update.
  • Full text search for other cases.
  • Get email alerts whenever a new case matches your search.

Become a Member

One Moment Please

The filing “” is large (MB) and is being downloaded.

Please refresh this page in a few minutes to see if the filing has been downloaded. The filing will also be emailed to you when the download completes.

Your document is on its way!

If you do not receive the document in five minutes, contact support at support@docketalarm.com.

Sealed Document

We are unable to display this document, it may be under a court ordered seal.

If you have proper credentials to access the file, you may proceed directly to the court's system using your government issued username and password.


Access Government Site

We are redirecting you
to a mobile optimized page.





Document Unreadable or Corrupt

Refresh this Document
Go to the Docket

We are unable to display this document.

Refresh this Document
Go to the Docket