throbber
Computers in Industry 46 (2001) 189±207
`
`A dynamic reactive scheduling mechanism for responding to
`changes of production orders and manufacturing resources
`
`J. Sun, D. Xue*
`Department of Mechanical and Manufacturing Engineering, University of Calgary, Calgary, Alberta, Canada T2N 1N4
`
`Received 24 July 2000; accepted 13 March 2001
`
`Abstract
`
`This research introduces a dynamic reactive production scheduling mechanism for modifying the originally created
`schedules when these schedules cannot be completed due to changes of production orders and manufacturing resources.
`Production order changes include removal of an order that is canceled by a customer and insertion of an order that has to be
`completed within a short period of time. Manufacturing resource changes include breakdowns of machines and sudden
`sickness of workers. Match-up and agent-based collaboration approaches are employed to modify only part of the originally
`created schedules for improving the reactive scheduling ef®ciency, while maintaining the scheduling quality. The dynamic
`reactive production scheduling system was implemented using Smalltalk, an object oriented programming language.
`# 2001 Elsevier Science B.V. All rights reserved.
`
`Keywords: Reactive scheduling; Predictive scheduling; Match-up approach; Multi-agents; Arti®cial intelligence
`
`1. Introduction
`
`Production scheduling aims at allocating available
`manufacturing resources for the required manufactur-
`ing tasks and identifying the sequence and timing
`parameter values to accomplish these tasks. Typical
`manufacturing resources include facilities, persons,
`materials, and so on. Competitiveness of products
`can be improved by identifying the optimal production
`schedule that needs the minimum production efforts.
`The research on production scheduling was started
`by developing algorithms for generating the optimal
`sequence to complete the required tasks considering
`either only one processor (machine) or multiple pro-
`cessors (machines) [1]. In each of these scheduling
`
`* Corresponding author. Tel.: ‡1-403-220-4168;
`fax: ‡1-403-282-8406.
`E-mail address: xue@enme.ucalgary.ca (D. Xue).
`
`methods, an objective function, such as the minimum
`total make-span to complete all the selected tasks, or
`the minimum mean ¯ow of these selected tasks, is
`selected for identifying the optimal schedule.
`Most of the earlier developed scheduling methods
`have dif®culty for solving actual industrial problems,
`due to the complexity of real-life manufacturing con-
`straints. First, the industrial scheduling problems are
`dynamic in nature, i.e. new orders are received con-
`tinuously during the production process. Second, the
`created schedule may be changed to re¯ect
`the
`changes of production orders and manufacturing con-
`ditions during production process. Production order
`changes include removal of an order that is canceled
`by a customer and insertion of an order that has to be
`completed within a short period of time. Manufactur-
`ing condition changes include disturbance events of
`resources such as breakdowns of machines and sick-
`ness of workers.
`
`0166-3615/01/$ ± see front matter # 2001 Elsevier Science B.V. All rights reserved.
`PII: S 0 1 6 6 - 3 6 1 5 ( 0 1 ) 0 0 1 1 9 - 1
`
`Petitioner STMICROELECTRONICS, INC.,
`Ex. 1016, IPR2022-00681, Pg. 1
`
`

`

`190
`
`J. Sun, D. Xue / Computers in Industry 46 (2001) 189±207
`
`With the advances in computer technologies, many
`new methods and systems considering industrial con-
`straints were developed for two different types of
`production scheduling: predictive scheduling and
`reactive scheduling [2,3]. Predictive scheduling cre-
`ates the optimal schedule based on given requirements
`and constraints prior to the production process. Most
`of the scheduling algorithms and systems were devel-
`oped for predictive scheduling. Reactive scheduling,
`on the other hand, is a process to modify the created
`schedule during the manufacturing process to adapt
`changes in production environment. Reactive schedul-
`ing is also called rescheduling.
`The intelligent system approaches have been proved
`effective for conducting both predictive scheduling and
`reactive scheduling [2,4,5]. For predictive scheduling,
`generally intelligent approaches aim at identifying the
`optimal schedule through iterative search process. For
`reactive scheduling, most approaches attempt to revise
`only part of the originally created schedule for respond-
`ing to the production environment changes without
`rescheduling all the required tasks [6±9]. Because a
`large number of tasks are usually considered in pre-
`dictive scheduling and reactive scheduling, the optimal
`schedules created using these developed methods are
`not the true global optimal schedules. Quality of sche-
`duling result can be improved by employing stochastic
`computing methods, such as genetic algorithm and
`simulated annealing, to prevent the result from falling
`into the local optimal points [2].
`Despite the progress, many problems have to be
`solved for predictive scheduling and reactive schedul-
`ing. These problems are summarized as follows.
`
`1. In the presently developed scheduling systems,
`manufacturing requirements are usually modeled
`directly based upon customer requirements. The
`manufacturing requirements, together with manu-
`facturing resource descriptions, are used as
`constraints for production scheduling. Product
`design descriptions and constraints, however, are
`not considered in these systems. Because many
`new designs are created using existing modules as
`their components, modeling of the manufacturing
`requirements of these component modules and
`identi®cation of the manufacturing tasks of these
`designs by considering constraints among these
`components are required.
`
`2. The production scheduling mechanisms in these
`systems were primarily developed based on
`centralized computing architecture, in which all
`the knowledge bases and databases were modeled
`at the same location. This control architecture has
`dif®culty in handling complex manufacturing
`systems that require knowledge and data to be
`distributed at different locations. Therefore, devel-
`opment of distributed production scheduling
`systems is required.
`
`In our previous research, an intelligent predictive
`scheduling system has been developed to solve these
`two problems [10,11]. In this system, product descrip-
`tions and design constraints are represented using a
`feature-based modeling approach. Manufacturing
`requirements for producing the products, including
`tasks and sequential constraints for accomplishing
`these tasks, are represented as part of the product
`feature descriptions. Manufacturing resources, includ-
`ing facilities and persons, are modeled as distributed
`agents that are coordinated by two mediators. The
`optimal production schedule and its timing parameter
`values are identi®ed using constraint-based search and
`agent-based collaboration approaches. This project
`was initiated from the requirements of a building
`product manufacturing company Ð Gienow Building
`Products Ltd., where production tasks are created from
`customer orders.
`The research presented in this paper is a further
`development of this intelligent production scheduling
`system by introducing a reactive scheduling mechan-
`ism for responding to changes of production orders
`and manufacturing resources. Changes of production
`orders include cancellation of previously scheduled
`orders and insertion of urgent orders. Changes of
`manufacturing resource conditions include break-
`downs of machines and sickness of persons. Match-
`up and agent-based collaboration approaches are
`employed for rescheduling the tasks and identifying
`the optimal timing parameter values of these tasks, for
`improving the scheduling ef®ciency while maintain-
`ing the scheduling quality.
`The remaining of this paper is organized as follows.
`Section 2 introduces the previously developed pre-
`dictive scheduling mechanism. Section 3 proposes the
`architecture of the intelligent production scheduling
`system that supports both the predictive scheduling
`
`Petitioner STMICROELECTRONICS, INC.,
`Ex. 1016, IPR2022-00681, Pg. 2
`
`

`

`J. Sun, D. Xue / Computers in Industry 46 (2001) 189±207
`
`191
`
`function and the reactive scheduling function. Section
`4 presents the reactive scheduling algorithms and
`examples for responding to changes of orders and
`resources. Section 5 gives a number of case study
`examples to show the effectiveness of the introduced
`approach. Section 6 summarizes this research.
`
`2. Review of a previously developed predictive
`scheduling mechanism
`
`The previously developed predictive scheduling
`mechanism is composed of three sub-systems: product
`modeling sub-system, resource management sub-sys-
`tem, and scheduling sub-system.
`
`2.1. Product modeling sub-system
`
`In the product modeling sub-system, a product is
`modeled by primitives called features [12,13]. Fea-
`tures are described at two different levels, class level
`and instance level, corresponding to standard product
`libraries and special product data,
`respectively.
`Instance features are generated using class features
`as their templates. A feature is composed of element
`features, attributes, qualitative relations among fea-
`
`tures, and quantitative relations among attributes. For
`instance, Fig. 1 shows a product modeled by three
`instance features. The top-level instance feature, c, is
`generated from a class feature WindowCenter
`that is composed of two element features: ?Left
`and ?Right. When the class feature, Window-
`Center, is used to generate its instance feature, c,
`the two element features are also generated as instance
`features, cl and cr, respectively.
`The manufacturing requirements for producing
`each feature are de®ned by a graph of tasks, represent-
`ing the sequential constraints to accomplish these
`tasks. For instance, the right component, cr, shown
`in Fig. 1 can be produced by six tasks, including
`cutting, C, framing, F, assemblies, A1, A2, and
`A3, and glazing, G. A task in an instance feature is
`carried out in production only when all the tasks in this
`feature's element features have been completed. Each
`task is de®ned by its type, requirements of resources
`including facilities and persons, and time period to
`carry out this process.
`
`2.2. Resource management sub-system
`
`In the resource management sub-system, the faci-
`lity resources and person resources are modeled as
`
`Fig. 1. Feature-based product and manufacturing requirement representation.
`
`Petitioner STMICROELECTRONICS, INC.,
`Ex. 1016, IPR2022-00681, Pg. 3
`
`

`

`192
`
`J. Sun, D. Xue / Computers in Industry 46 (2001) 189±207
`
`agents, which are coordinated by a facility mediator
`and a personnel mediator during the predictive sche-
`duling process. The idea to model resources using
`agents comes from the distributed modeling approach
`for improving ¯exibility of manufacturing systems
`[14±19]. A facility resource agent is de®ned by its
`type, manufacturing functions, and time constraints
`including available periods and unavailable periods. A
`person resource agent is de®ned by the facilities that
`the person is responsible for, and time constraints
`including available periods, regular schedule, and
`unavailable periods.
`
`2.3. Scheduling sub-system
`
`The scheduling sub-system aims at identifying the
`optimal schedule for the orders received from custo-
`mers. When an order is received, an order agent is then
`created to represent the customer requirements. The
`order agents negotiate with the resource agents using
`the corresponding design constraints and manufactur-
`ing requirements, which are preserved in the instance
`
`features, to identify the optimal production schedule.
`Constraint-based search and agent-based collabora-
`tion approaches are employed for identifying the
`optimal schedule, as shown in Fig. 2.
`
`2.3.1. Constraint-based search
`The optimal sequence of tasks for a customer order
`is identi®ed using best-®rst search [20], as shown in
`Fig. 2. Each node in the search tree represents a partial
`schedule developed so far. A start node describes an
`empty schedule, while a goal node describes the
`schedule in which all the tasks of the customer order
`have been allocated with required resources and tim-
`ing parameter values. In predictive scheduling, each
`time the best node is selected for generating its sub-
`nodes. When a sub-node is generated, an unscheduled
`task is then selected for resource allocation and timing
`parameter value instantiation through collaboration
`among relevant agents. Evaluation to this node is
`conducted using a heuristic function. This process
`is conducted continuously until the selected best-node
`is the goal node. The scheduling results are described
`
`Fig. 2. Predictive scheduling using constraint-based search and agent-based collaboration.
`
`Petitioner STMICROELECTRONICS, INC.,
`Ex. 1016, IPR2022-00681, Pg. 4
`
`

`

`J. Sun, D. Xue / Computers in Industry 46 (2001) 189±207
`
`193
`
`by sequences of tasks that are preserved in order
`agents and resource agents, as shown in Fig. 2. In
`predictive scheduling, the created schedule should
`satisfy the following temporal constraints: (1) a task
`in an instance feature can be carried out in production
`only when all
`the tasks in this feature's element
`features have been completed. (2) A task can be
`carried out only when all its ancestor tasks have been
`completed.
`Two heuristic functions have been developed in this
`research: (1) Fmax Ð the latest task ®nish time con-
`sidering all the scheduled tasks of an order and (2) Smin
`Ð the earliest task start time considering all the
`scheduled tasks of an order. Two search strategies
`for predictive scheduling have also been developed
`based upon the two heuristic functions: (1) earliest-
`delivery-time-based scheduling strategy Ð to provide
`the product to the customer as early as possible by
`selecting the node with the minimum value of the Fmax
`as the best node, and (2) due-time-based scheduling
`strategy Ð to start the product manufacturing as late
`as possible to reduce the space for storing the pro-
`duced product by selecting the node with the max-
`imum value of the Smin as the best node.
`
`2.3.2. Agent-based collaboration
`Allocation of
`resources and instantiation of
`timing parameter values for the required tasks are
`
`conducted based upon agent-based collaboration
`using the contract net protocol [21]. Two timing
`parameters of tasks, start time and ®nish time, are
`considered in scheduling. The agent-based collabora-
`tion in predictive scheduling is conducted at two
`different
`levels: order-facility collaboration level
`and facility-person collaboration level, as shown in
`Fig. 2. When the facility mediator receives a to-
`be-scheduled task from the order agent, this mediator
`sends messages to all the relevant facility agents it
`knows. Each facility agent then starts negotiation with
`the relevant person agents through the personnel
`mediator and sends a bid (with the proposed start
`time, ®nish time, and person) to the facility mediator.
`The facility mediator selects the facility that provides
`the best bid, such as the one with the earliest product
`manufacturing completion time for
`the earliest-
`delivery-time-based scheduling, or the one with the
`latest product manufacturing releasing time for the
`due-time-based scheduling.
`
`3. Architecture of an intelligent production
`scheduling system
`
`The dynamic reactive scheduling mechanism
`introduced in this research was developed as a
`
`Fig. 3. Architecture of the intelligent production scheduling system.
`
`Petitioner STMICROELECTRONICS, INC.,
`Ex. 1016, IPR2022-00681, Pg. 5
`
`

`

`194
`
`J. Sun, D. Xue / Computers in Industry 46 (2001) 189±207
`
`function block added to the scheduling module
`of the previously developed intelligent production
`scheduling system. Architecture of the whole intelli-
`gent production scheduling system with both predic-
`tive scheduling function and reactive scheduling
`function is shown in Fig. 3. The system is composed
`of three sub-systems: product modeling sub-system,
`resource management sub-system, and scheduling
`sub-system.
`Predictive scheduling is conducted to allocate
`resources and their timing parameter values for pro-
`ducing the products ordered by customers prior to the
`production process. Reactive scheduling, on the other
`hand, is conducted to modify the created schedule for
`responding to the changes of customer orders (such as
`cancellation of orders or insertion of urgent orders)
`and manufacturing conditions (such as machine break-
`downs and persons' sudden sickness) during the pro-
`duction process.
`The intelligent predictive/reactive production sche-
`duling system was implemented using Smalltalk, an
`object oriented programming language [22]. Smalltalk
`was used due to its good user interface environment
`and large class library. Details of the developed
`dynamic reactive scheduling mechanism will be
`described in the next section.
`
`4. A dynamic reactive scheduling mechanism
`
`In this research, two reactive scheduling algorithms
`have been developed for responding to the changes of
`customer orders and manufacturing resource condi-
`tions, respectively, by partially modifying the origin-
`ally created schedule. Changes of customer orders
`include cancellation of scheduled orders and insertion
`of urgent orders. Changes of manufacturing resource
`conditions include breakdowns of machines and sud-
`den sickness of persons.
`In both algorithms, the previously scheduled tasks
`are modi®ed. The objective of this research is to
`develop a reactive scheduling method to minimize
`the schedule changes for improving the ef®ciency of
`reactive scheduling, while maintaining the quality of
`reactive scheduling. Since the revised schedule can
`maximally match up with the original schedule, this
`reactive scheduling approach is also called a match-up
`reactive scheduling approach.
`
`4.1. Reactive scheduling for customer
`order changes
`
`Changes of customer orders are of two cases: (1)
`cancellation of scheduled orders and (2) insertion of
`urgent orders. When a previously scheduled order is
`canceled by its customer, all the resource time slots
`assigned to the tasks of this order should be released.
`To improve the quality of the overall schedule con-
`sidering all
`the other ordered products,
`the tasks
`scheduled using the due-time-based scheduling strat-
`egy could be moved forward towards their due-time
`measures, while the tasks scheduled using the earliest-
`delivery-time-based scheduling strategy could be
`moved backward towards their ordering time mea-
`sures. When a feasible schedule cannot be identi®ed
`for an order using the predictive scheduling strategy
`due to its urgent due-time requirement, some of the
`previously scheduled tasks can be temporarily released
`for inserting the tasks in the urgent order to the
`schedule. The released tasks should be rescheduled
`to satisfy the product and manufacturing constraints.
`Since one of the objectives in this research is to
`integrate production scheduling with product design,
`when design parameters are changed, the manufactur-
`ing requirements are then updated automatically.
`When these manufacturing requirements cannot be
`satis®ed by the currently created schedule, change of
`the production schedule can be conducted simply by
`canceling the original order and inserting the modi®ed
`order.
`To minimize the schedule change, while maintain-
`ing the quality of the overall schedule, the following
`rules have been employed in reactive scheduling for
`customer order changes.
`
`1. The customer orders previously scheduled using
`the due-time-based scheduling strategy are re-
`scheduled prior to the revision of the customer
`orders previously scheduled using the earliest-
`delivery-time-based scheduling strategy.
`2. In the revised schedule, the sequence of tasks for
`each to-be-rescheduled order remains the same as
`the sequence in the original schedule to satisfy the
`task precedence constraints and improve the
`rescheduling ef®ciency.
`3. In the revised schedule, each rescheduled task
`is still allocated with the facility resource and
`
`Petitioner STMICROELECTRONICS, INC.,
`Ex. 1016, IPR2022-00681, Pg. 6
`
`

`

`J. Sun, D. Xue / Computers in Industry 46 (2001) 189±207
`
`195
`
`person resource that were originally allocated to
`this task.
`
`Reactive scheduling algorithm responding to cus-
`tomer order changes is formulated as the following
`three steps.
`
`1. Step 1: Initialize for rescheduling.
`Generate a copy of the original schedules that
`are preserved in the resource agents. Consider all
`the orders that have not been manufactured so far
`as the to-be-rescheduled orders and remove their
`original schedules from the resource agents. In
`case of canceling an order, the canceled order
`should not considered in further
`rescheduling
`process. In case of inserting an order, this order
`is scheduled ®rst using the due-time-based pre-
`dictive scheduling approach.
`2. Step 2: Reschedule the to-be-rescheduled orders
`that were previously scheduled using the due-
`time-based scheduling strategy.
`2.1. For these to-be-rescheduled orders, identify
`the to-be-rescheduled tasks from the copy of
`the original schedules. In case of canceling
`an order, the tasks that precede the tasks of
`the canceled order in the original schedules
`should be considered as the to-be-resched-
`uled tasks. In case of inserting an order, the
`tasks whose original schedules are in con¯ict
`with the schedule of the inserted order should
`be considered as the to-be-rescheduled tasks.
`Sort the list of the to-be-rescheduled tasks
`according to the ®nish time values of these
`tasks. The to-be-rescheduled task with the
`largest ®nish time value is placed at
`the
`beginning of the list.
`from the to-be-
`2.2. Select
`the ®rst element
`rescheduled task list as the current to-be-
`rescheduled task. Recover schedules of the
`tasks that are in the to-be-rescheduled orders
`and will start after the ®nish time of the
`current
`to-be-rescheduled task. Reassign
`timing parameter values to the current to-
`be-rescheduled task using agent-based colla-
`boration mechanism. The current
`to-be-
`rescheduled task should be removed from
`the list of the to-be-rescheduled tasks.
`2.3. Check if the reassigned timing parameter
`values are the same as those in the copy of the
`
`original schedules. If they are not the same,
`the following tasks belonging to the to-be-
`rescheduled orders should be added to the list
`of the to-be-rescheduled tasks: (1) the tasks
`preceding the current to-be-rescheduled task
`in the copy of the original schedules pre-
`served in the relevant facility agent and per-
`son agent that were allocated for the current
`to-be-rescheduled task, (2) the task preceding
`the current to-be-rescheduled task in the task
`sequence of the corresponding customer order,
`and (3) the tasks whose original schedules are
`in con¯ict with the revised schedule for the
`current to-be-rescheduled task.
`2.4. Check if the list of the to-be-rescheduled
`tasks is empty. If the list is not empty, go to
`Step 2 (2.1).
`2.5. Recover all the tasks of the to-be-rescheduled
`orders that are preserved in the copy of the
`original schedules and have not been re-
`scheduled so far in the reactive scheduling
`process.
`3. Step 3: Reschedule the to-be-rescheduled orders
`that were previously scheduled using the earliest-
`delivery-time-based scheduling strategy.
`3.1. For these orders, identify the to-be-resched-
`uled tasks from the copy of the original
`schedules. The tasks whose original sche-
`dules are in con¯ict with the revised
`schedules are considered as the to-be-re-
`scheduled tasks. In case of canceling an
`order, the tasks that follow the tasks of the
`canceled order
`in the original schedules
`should also be considered as the to-be-
`rescheduled tasks. Sort the list of the to-be-
`rescheduled tasks according to the start time
`values of these tasks. The to-be-rescheduled
`task with the smallest start
`time value is
`placed at the beginning of the list.
`3.2. Select the ®rst element from the to-be-resched-
`uled task list as the current to-be-rescheduled
`task. Recover schedules of the tasks that are in
`the to-be-rescheduled orders and will be
`completed before the start time of the current
`to-be-rescheduled task. Reassign timing para-
`meter values to the current to-be-rescheduled
`task using the agent-based collaboration
`mechanism. The current
`to-be-rescheduled
`
`Petitioner STMICROELECTRONICS, INC.,
`Ex. 1016, IPR2022-00681, Pg. 7
`
`

`

`196
`
`J. Sun, D. Xue / Computers in Industry 46 (2001) 189±207
`
`task should be removed from the list of the
`to-be-rescheduled tasks.
`3.3. Check if the reassigned timing parameter
`values are the same as those in the copy of
`the original schedules. If they are not the
`same, the following tasks belonging to the to-
`be-rescheduled orders should be added to the
`list of the to-be-rescheduled tasks: (1) the
`tasks following the current to-be-rescheduled
`task in the copy of the original schedules
`preserved in the relevant facility agent and
`person agent
`that were allocated for
`the
`current to-be-rescheduled task, (2) the task
`following the current to-be-rescheduled task
`in the task sequence of the corresponding
`customer order, and (3) the tasks whose
`original schedules are in con¯ict with the
`revised schedule for
`the current
`to-be-
`rescheduled task.
`3.4. Check if the list of the to-be-rescheduled
`tasks is empty. If the list is not empty, go to
`Step 3 (3.2).
`3.5. Recover all the tasks of the to-be-rescheduled
`orders that are preserved in the copy of the
`original schedules and have not been re-
`scheduled so far in the reactive scheduling
`process.
`
`An example is given in Fig. 4 to illustrate the
`reactive scheduling algorithm for responding to cus-
`tomer order change. In this example, an urgent order E
`needs to be inserted in the original schedule, which is
`shown in Fig. 4a. The orders A and B were scheduled
`using the earliest-delivery-time-based scheduling
`strategy, and the orders C and D were scheduled using
`the
`due-time-based
`scheduling
`strategy. The
`sequences of tasks for the orders A, B, C, and D in
`the original schedule are:
`Order A : A1 ! A2 ! A3
`Order B : B1 ! B2 ! B3 ! B4
`Order C : C1 ! C2 ! C3
`Order D : D1 ! D2 ! D3
`In Step 1, as shown in Fig. 4b, orders A, B, C, and D
`are identi®ed as the to-be-rescheduled orders and
`removed from the original schedule temporally. Then,
`order E is scheduled using the due-time-based sche-
`duling strategy.
`
`In Step 2, as shown in Fig. 4c, the orders C and D
`that were scheduled previously using the due-time-
`based scheduling strategy are rescheduled. The tasks
`D1 and D2 are identi®ed as the to-be-rescheduled
`tasks at the beginning, due to their con¯ict with the
`tasks E1 and E2. Based on the ®nish time values, D2
`is selected as the ®rst current to-be-rescheduled task.
`Task D3 that is to be started after the ®nish time of D2
`is recovered in the revised schedule. Then D2 is
`assigned with new timing parameter values. Since
`the timing parameter values of D2 are changed in
`the revised schedule, two tasks are identi®ed as the
`new to-be-rescheduled tasks: C2 that precedes D2 in
`the original schedule considering facility F2 and D1
`that precedes D2 in the task sequence of the original
`schedule for order D. Only C2 is added to the to-be-
`rescheduled tasks, since D1 has been already identi-
`®ed as a to-be-rescheduled task at the beginning of this
`step. Next, D1 is selected as the current to-be-resched-
`uled task and assigned with new timing parameter
`values. Although the new timing parameter values of
`D1 are different from the original ones, no to-be-
`rescheduled tasks are further identi®ed. Then task C2
`is selected as the current to-be-rescheduled task. Task
`C3 that is to be started after the ®nish time of C2 is
`recovered in the revised schedule. The task C2 is
`rescheduled with the same timing parameter values.
`After task C2 is rescheduled, the to-be-rescheduled
`task list becomes an empty one. Task C1 is recovered
`with its original schedule.
`In Step 3, as shown in Fig. 4d, the orders A and B
`that were scheduled previously using the earliest-
`delivery-time-based scheduling strategy are resched-
`uled. The original schedule of B4 is in con¯ict with
`the revised schedule of D2, thus, B4 is identi®ed as
`the to-be-rescheduled task at the beginning. Next, B4
`is selected as the current to-be-rescheduled task and
`the tasks A1, A2, A3, B1, B2, and B3, whose ®nish
`time values precede the start time of B4 in the original
`schedule, are recovered in the revised schedule. Then,
`B4 is assigned with new timing parameter values.
`Since no additional tasks can be identi®ed as the to-be-
`rescheduled tasks, the reactive scheduling process is
`terminated.
`In this example, among the 13 tasks in the four
`orders, only 3 tasks are revised during the reschedul-
`ing process for responding to the change of customer
`order.
`
`Petitioner STMICROELECTRONICS, INC.,
`Ex. 1016, IPR2022-00681, Pg. 8
`
`

`

`J. Sun, D. Xue / Computers in Industry 46 (2001) 189±207
`
`197
`
`Fig. 4. Reactive scheduling for customer order change.
`
`In the rescheduling process, reassignment of timing
`parameter values to the to-be-rescheduled tasks is
`conducted based upon agent-based collaboration
`among resource agents through coordination of the
`two mediators in the resource management sub-sys-
`tem. Two task timing parameters, start time and ®nish
`time, are considered in this research.
`An example is shown in Fig. 5 to illustrate the
`process of reassigning timing parameter values to a
`to-be-rescheduled task of an order, which was ori-
`ginally scheduled using the earliest-delivery-time-
`based scheduling strategy. During the rescheduling
`process, the current to-be-rescheduled task A needs
`to be reassigned with new timing parameter values.
`
`The resources, facility agent F1 and person agent
`P1, were originally allocated for this task. The ear-
`liest possible start time is Tes that was determined
`based on task precedence constraints and feature
`relations using the previously developed predictive
`scheduling method. First, the facility mediator reas-
`signs this task to the facility agent F1. Upon receiving
`the facility agent F1 identi®es the
`this message,
`related person agent P1 through the personnel med-
`iator. Then the facility agent F1 negotiates with the
`person agent P1 to determine the proper time slot for
`the task A. The time slot should provide the mini-
`mum value of the task start time in the earliest-
`delivery-time-based scheduling, while
`satisfying
`
`Petitioner STMICROELECTRONICS, INC.,
`Ex. 1016, IPR2022-00681, Pg. 9
`
`

`

`198
`
`J. Sun, D. Xue / Computers in Industry 46 (2001) 189±207
`
`Fig. 5. An example of rescheduling timing parameter values through agent-based collaboration.
`
`all the manufacturing requirement and resource con-
`straints.
`
`4.2. Reactive scheduling for manufacturing resource
`changes
`
`Manufacturing resources changes are of two cases:
`(1) facility breakdowns and (2) persons' sudden sick-
`ness. When such a disturbance occurs, the schedules of
`the affected tasks have to be revised. Match-up resche-
`duling approach is also employed to minimize the
`changes to the originally created schedules, while
`satisfying the product and manufacturing constraints.
`The following rules have been used for reactive sche-
`duling to respond to the changes of manufacturing
`resources.
`
`1. The reactive scheduling mechanism ®rst tries to
`move the tasks that are affected directly by the
`resource changes to other
`resources without
`changing the timing parameter values of these
`tasks.
`2. If the alternative resources can not be identi®ed
`for the affected tasks, match-up-based reschedul-
`ing is then conducted. The customer orders
`previously scheduled using the due-time-based
`
`scheduling strategy are rescheduled prior to the
`revision to the customer orders previously sched-
`uled using the earliest-delivery-time-based sche-
`duling strategy.
`3. If some orders, which were previously scheduled
`using the due-time-based scheduling strategy,
`cannot be rescheduled to satisfy the due-time
`constraints due to the changes of
`resource
`conditions,
`the directly affected orders will be
`rescheduled with modi®ed due-time values, after
`all other orders with due-time requirements have
`been rescheduled.
`4. In the revised schedule, the sequence of tasks for
`each to-be-rescheduled order remains the same as
`the sequence in the original schedule to satisfy the
`task precedence constraints while improving the
`rescheduling ef®ciency.
`5. In the revised schedule, if alternative resources
`cannot be identi®ed for the affected tasks, each
`rescheduled task is still allocated with the
`resources that were originally assigned to this
`task for improving the rescheduling ef®ciency.
`
`Reactive scheduling algorithm responding to man-
`ufacturing resource changes is formulated as the
`following ®ve steps.
`
`Petitioner STMICROELECTRONICS, INC.,
`Ex. 1016, IPR2022-00681, Pg. 10
`
`

`

`J. Sun, D. Xue / Computers in Industry 4

This document is available on Docket Alarm but you must sign up to view it.


Or .

Accessing this document will incur an additional charge of $.

After purchase, you can access this document again without charge.

Accept $ Charge
throbber

Still Working On It

This document is taking longer than usual to download. This can happen if we need to contact the court directly to obtain the document and their servers are running slowly.

Give it another minute or two to complete, and then try the refresh button.

throbber

A few More Minutes ... Still Working

It can take up to 5 minutes for us to download a document if the court servers are running slowly.

Thank you for your continued patience.

This document could not be displayed.

We could not find this document within its docket. Please go back to the docket page and check the link. If that does not work, go back to the docket and refresh it to pull the newest information.

Your account does not support viewing this document.

You need a Paid Account to view this document. Click here to change your account type.

Your account does not support viewing this document.

Set your membership status to view this document.

With a Docket Alarm membership, you'll get a whole lot more, including:

  • Up-to-date information for this case.
  • Email alerts whenever there is an update.
  • Full text search for other cases.
  • Get email alerts whenever a new case matches your search.

Become a Member

One Moment Please

The filing “” is large (MB) and is being downloaded.

Please refresh this page in a few minutes to see if the filing has been downloaded. The filing will also be emailed to you when the download completes.

Your document is on its way!

If you do not receive the document in five minutes, contact support at support@docketalarm.com.

Sealed Document

We are unable to display this document, it may be under a court ordered seal.

If you have proper credentials to access the file, you may proceed directly to the court's system using your government issued username and password.


Access Government Site

We are redirecting you
to a mobile optimized page.





Document Unreadable or Corrupt

Refresh this Document
Go to the Docket

We are unable to display this document.

Refresh this Document
Go to the Docket