throbber
United States Patent [191
`Yegge
`
`[54] STRUCTURE AND METHOD OF
`CONSTRUCTING AND TEST-LOADING
`PILE ANCHORED FOUNDATIONS
`
`[76]
`
`Inventor: Lawrence R. Yegge, 139 Via de
`Tesoros, Los Gatos, Calif. 95030
`
`[21] Appl. No.: 707,184
`
`[22] Filed:
`
`July 21, 1976
`
`Int. CI.2 ................................................ E02D 5/74
`[51]
`(52] U.S. CI . ........................................... 61/50; 61/39;
`61/56.5; 52/166; 52/169.1
`(58] Field of Search .................... 61/39, 35, 50, 53.52,
`61/53.5, 56, 56.5, 63, 31; 52/742, 230, 169, 166,
`155
`
`[56]
`
`2,763,464
`3,087,308
`3,256,694
`3,299,644
`
`References Cited
`U.S. PATENT DOCUMENTS
`9/1956 Leonhardt ......................... 52/230 X
`4/1963 Hart et al ............................ 61/50 X
`6/1966 Siedenhans .............................. 61/50
`1/1967 White ................................... 61/39 X
`
`[11]
`
`[45]
`
`4,043,133
`Aug.23, 1977
`
`FOREIGN PATENT DOCUMENTS
`683,898
`4/1964 Canada ..................................... 61/39
`Primary Examiner-Jacob Shapiro
`Attorney, Agent, or Firm-Naylor, Neal & Uilkema
`[57]
`ABSTRACT
`A method of constructing pre-tested concrete pilings
`and pile caps particularly for use in supporting struc(cid:173)
`tures, such as transmission line towers that are subjected
`to large overturning moments. One or more pile holes
`are bored, a small diameter sheathing containing one or
`more steel tendons is inserted and a concrete mixture is
`poured in the pile hole exterior of the tendon sheathing
`with the tendons anchored in the bottom of the pile.
`When the concrete has obtained sufficient strength, the
`tendon is stressed, thereby testing the tension-carrying
`capacity of the pile and its surrounding foundation soil.
`A concrete pile cap is thereafter joined to the pile, the
`tendons are again stressed and anchored to the pile cap
`and the tendon sheathing is filled with concrete grout to
`form a solid post-tensioned foundation that has been
`pre-tested at a force in excess of its design load.
`
`7 Claims, 8 Drawing Figures
`
`12
`
`24 0
`
`Exhibit - 1008
`NV5, Inc. v. Terracon Consultants, Inc.
`Page 1
`
`

`

`Exhibit - 1008
`NV5, Inc. v. Terracon Consultants, Inc.
`Page 2
`
`

`

`U.S. Patent Aug 23, 1977
`
`Sheet 2 of 2
`
`4,043,133
`
`! ! !
`'' '
`11 I
`
`58
`
`50
`
`38
`
`FIG- _ ?_
`
`FIG(cid:173)
`_B_
`
`Exhibit - 1008
`NV5, Inc. v. Terracon Consultants, Inc.
`Page 3
`
`

`

`1
`
`4,043,133
`
`STRUCTURE AND METHOD OF CONSTRUCTING
`AND TEST-LOADING PILE ANCHORED
`FOUNDATIONS
`
`2
`FIG. 7 is a detailed elevation view of the lower end of
`the tendon sheath with the extending tendons anchored
`to an anchor plate; and,
`FIG. 8 is a detailed elevation view of the pile top and
`5 illustrates the placement and structure of the tensioning
`jack.
`DESCRIPTION OF THE ILLUSTRATED
`EMBODIMENT
`Turning now to a detailed description of the inven(cid:173)
`tion, FIG. 1 is a sectional elevation view illustrating the
`boring of two diverging pile holes 10 and 12. Prior to
`this boring operation, the ground surface has been exca(cid:173)
`vated to a footing or beam line and a boring template 14
`has been installed. Pile holes 10 and 12 may, in most
`cases, have a diameter of only twelve to fourteen inches
`and their depth will, of course, be dependent upon the
`consistency and nature of the subsoil and the various
`design loading on the structure.
`In FIG. 2, piling holes 10 and 12 have been com(cid:173)
`pletely bored to the design depth. Inserted throughout
`SUMMARY OF THE INVENTION
`the length of hole 10 and extending above the ground
`surface are one or more steel tendons 16. Tendons 16
`Briefly described, the invention includes the steps of
`are loosely encased in a tendon sheathing 18, which
`boring a pile hole to the appropriate design depth, in-
`serting one or more steel cable tendons loosely con- 25 preferably is a galvanized steel conduit that may be
`tained in and extending from, the ends of a tubular metal
`spirally wound to reduce wobble within the piling
`tendon sheath running coaxially through the length of
`holes. The lower end of sheathing 18 is provided with a
`collar 20 from which the tendons 16 extend to be spread
`the bored hole, and then pouring a concrete mixture in
`the hold within one or two feet of the ground surface,
`and anchored to an anchor plate 22. As will be subse-
`but not within the tendon sheath, so that the lower end 30 quently explained in detail, a plastic grout tube 24 enters
`of the tendon is firmly anchored in the bottom of the
`t~~ sheathing collar 20 and e.xtends up through th~
`concrete pile but is loose within the tendon sheath.
`p1bn~ hole and through the bormg template 14 w~ere 1t
`When the concrete has attained sufficient compressive
`remams ~bove ground surface for a future step m the
`strength, the tendon is stressed to approximately 125%
`construc!1on pro.cess.
`of the design load of the pile to test the tension capacity 35 Upo~ mstallat1on of.the tend~ns 16 and t~e tendon
`of the pile and its surrounding soil. The upward force
`s~:athmg 18, c~ncrete 1s poured.mto that portion of the
`applied to the pile by means of the stressing tendon has
`p1hng hol~ outside of the sheathing 18 and up to a level
`r
`· t th t
`·t
`· kin
`d whi h
`26 approximately one foot below the bottom surface of
`1 s r~ac ton agams
`template 14. As will be explained in connection with
`e e~p~rary Jae
`g pa '
`c
`pad is separ?ted from the ~tie m sue~ a way that no part 40 FIG. 7, a mastic is packed in the lower end of collar 20
`of th~ reac!10n ~o !he applied force 1~ t~en ~t the top of
`to prevent the poured concrete from seeping around the
`the pile. Smee 1t 1.s known that a ptle s resistance to a
`tendons 16 and into the tendon sheathing 18.
`downward lo.ad ts at. least e~ual t~ (and n~~ally
`After the concrete has attained a sufficient compres-
`greater tha~) its cap?c1ty. to resist upbft, the m1rum~
`sive strength, the drilling template 14 is removed and is
`value .at which the ptle wtll support down:ward loads 1s 45 replaced with a temporary jacking pad 28, as illustrated
`in FIG. 3. Jacking pad 28 is a large surfaced steel or
`est~bbshed by t~e performance of the pile ~nder the
`~pbft load. appb~d. Thereafter, the te~don 1s ?e-ten-
`concrete structure suitably bored to receive the tendons
`stoned, a pil.e cap .1s poured to connect .with the pile top,
`16, an anchorage trumpet 30 and a bearing plate 32.
`the ~endon 1s agam stre~sed to the design load, t~e ten-
`Jacking pad 28 is provided with two upper surfaces that
`don 1s anchored to the pile cap, ~d cement grout !s the~ 50 are pitched at an angle normal to the longitudinal axes
`pumped into the tendon sheathtng to form a sobd uru-
`of piling holes 10 and 12 to receive a tensioning jack 34.
`The illustrated jack 34 is of the type disclosed in my
`tary pre-tested pile and cap.
`U.S. Pat. No. 3,597,830.
`As will be discussed in detail in connection with FIG.
`8, the tensioning jack 34 is connected to the end of each
`tendon 16 and the tendons are stressed to 125% of the
`design load of the pile. By stressing the tendons in this
`manner, the tension capacity of the pile and its sur(cid:173)
`rounding soil is tested to assure that uplift forces will
`not dislodge the pile. Likewise, the compressive load(cid:173)
`carrying capacity of the pile is also tested as this capac(cid:173)
`ity is at least as great as the tension capacity. Further(cid:173)
`more, the force exerted by the bottom of the jacking
`pad 28 can be used when desired to effectively test the
`vertical downward load-carrying capacity of the sub(cid:173)
`surface soil. Since there is a space of approximately one
`foot between the top level 26 of the poured pile and the
`bottom surface of the jacking pad 28, sub-surface soil
`consolidation may be achieved by continuing the test
`
`BRIEF DESCRIPTION OF THE ORA WINGS
`In the drawings that illustrate the preferred embodi- 55
`ment of the invention:
`FIG. 1 is a proftle view illustrating the boring,
`through a template, of two diverging pile holes;
`FIG. 2 is a proftle view illustrating the placement of 60
`the tendons and the tendon sheath;
`FIG. 3 is a proftle view illustrating the placement of a
`jacking pad and tendon jack;
`FIG. 4 is a proftle view illustrating the pouring and
`connection of a permanent pile cap;
`FIG. 5 is a proftle view illustrating the post-tension(cid:173)
`ing of a completed pile to .. the pile cap;
`FIG. 6 is a profile illustrating the completed pile cap
`with installed stub angle;
`
`BACKGROUND OF THE INVENTION
`This invention relates to the construction of concrete
`piling and more particularly to a method of construct(cid:173)
`ing, on the site, a structure foundation which includes
`one or more concrete piles post-stressed to the pile cap 10
`to form a rigid unitary foundation for a structure, such
`as an electrical transmission line tower, that may be
`subjected to severe overturning moments or uplifting
`forces as well as the downward gravity loads. The in-
`vention is particularly valuable for use in the construc(cid:173)
`tion of transmission line towers in remote areas where
`all construction material may be transported to the site
`by helicopters, thereby obviating the need for costly
`access roads.
`
`15
`
`20
`
`65
`
`Exhibit - 1008
`NV5, Inc. v. Terracon Consultants, Inc.
`Page 4
`
`

`

`4,043,133
`
`4
`through the trumpet 30 and the bearing plate 32, which
`overlies both the trumpet 30 and the top surface of the
`pile cap 38. Atop the upper surface of bearing plate 32
`is anchor head 40, which is a thick steel disc drilled to
`5 receive tendons 16. The tendon holes on the top surface
`of anchor head 40 are conically counterbored to receive
`gripper jaws 42.
`Tensioning jack 34 is installed on the bearing plate 32
`and is aligned with the anchor head 40 so that tendons
`16 extend through the center open portion of jack 34
`where they are anchored by a second set of gripper
`jaws 44 connected to a hydraulic piston assembly in the
`tensioning jack 34. This piston assembly includes an
`annular piston 46 adapted to slide within an annular
`cylinder 48 coaxially located in the housing of the jack
`34. An intake port 50 admits an hydraulic fluid under
`force into the cylinder area, forcing the annular piston
`46 to apply tension to the tendons 16. Installed within
`tensioning jack 34 and adjacent the anchor head 40 is a
`second piston 52 which, when activated by the applica(cid:173)
`tion of pressure through intake port 54, will apply a
`downward locking force against gripper jaws 42 to
`insure that the jaws lock tendons 16. When presure is
`applied to the intake port 56 of the piston 52, the piston
`releases its force against the gripper jaws 42. This re(cid:173)
`leasing function is necessary when it is desired to de(cid:173)
`tension tendons 16 as described in connection with FIG.
`3. When it is desired to remove tensioning jack 34 after
`tendons 16 have been tensioned, pressure is admitted to
`intake port 54, forcing piston 52 to lock the gripper jaws
`42. Pressure is then admitted to the intake port 58 to
`force the main tensioning piston 46 back down to its
`non-tensioning position. At this point, the gripper jaws
`44 are loose and may be removed so that the entire
`tensioning jack 34 may be lifted from the bearing plate
`32, thereby leaving the tendons 16 firmly anchored in
`the gripper jaws 42 of the a1:.chor head 40.
`
`30
`
`3
`load until the desired consolidation is obtained. When
`the test has been completed and any desired soil com(cid:173)
`paction has been obtained, tendons 16 are de-tensioned
`and the tensioning jack 34 and the temporary jacking
`pad 28 are removed.
`FIG. 4 is a sectional elevation view illustrating that
`after removal of the temporary jack pad 28, a concrete
`form is placed, a bearing plate 32 and trumpet 30 assem(cid:173)
`bly is attached to the top of the tendon sheathing 18, the
`desired stub angle 36 is installed and the lower portion 10
`of the bearing cap 38 is poured from the top of the
`existing concrete piles and the ground surface to the
`lower surface of the bearing plate 32.
`After the lower portion of the piling cap has attained
`sufficient strength, the tendons 16 are threaded through 15
`a suitable anchor head 40, as illustrated in FIG. S. The
`tensioning jack 34 is reinstalled and the tendons 16 are
`stressed to their design load and permanently anchored
`to anchor head 40. This post-stressing step renders the
`pile cap 38 and each of the pilings into a solid unitary 20
`structure so that compressive loads applied downward
`upon the piling cap 38 will be carried by the pilings 10
`and 12, as well as by the cap 38.
`After tendons 16 have been stressed and anchored to
`the anchor head 40, a cement grout is pumped through 25
`the plastic grouting tube 24 and the interior of the ten(cid:173)
`don sheathing 18 and anchor head 40 is filled with
`grout. This grouting prevents corrosion of the steel
`tendons 16 and further adds to the solidarity of the
`pilings.
`FIG. 6 illustrates that, upon completion of the posts(cid:173)
`tressing and anchoring step described above, the piling
`cap form is again installed and the concrete piling cap is
`completed by pouring an upper portion 42 that covers
`the anchor head 40 and the exposed ends of the ten- 35
`sioned tendons 16 which now become thoroughly and
`permanently anchored. Thereafter, the desired struc(cid:173)
`ture 44 may be installed.
`FIG. 7 illustrates in detail the lower end of the tendon
`sheathing 18 with the attached collar 20 from which the 40
`tendons 16 extend. In most instances it is necessary to
`anchor the lower ends of the tendons 16 to an anchor
`plate 22 which effectively separates the ends of the
`tendons and prevents them from being pulled through
`the sheathing during the tensioning step described in 45
`connection with FIG. 3. It has been found that, if the
`pile hole is sufficiently deep so that the length of the
`exposed tendons 16 extending from the collar 20 is five
`feet or greater, there is adequate anchorage by the ten(cid:173)
`dons themselves and a bottom anchorage plate 22 may 50
`be omitted. FIG. 7 also illustrates that tendons 16 are
`sealed in the lower end of the collar 20 by a mastic seal
`44, which is installed prior to inserting the sheathing 18
`into the piling hole 20 to prevent the poured concrete of
`the pile from entering the sheathing 18. After the post- 55
`tensioning of the tendons 16, as described in connection
`with FIG. 5, cement grout is forced through the plastic
`grouting tube 24 that is connected to the collar 20 and
`the interior portion of the sheathing 18 is then filled
`with the cement grout to prevent corrosion of the cable 60
`and to add additional strength and rigidity to the sheath(cid:173)
`ing section of the piling.
`FIG. 8 is a detailed elevation view of the top end of
`the tendon sheathing 18 connected in a trumpet 30 that
`is embedded in the lower portion of the pile cap 38. The 65
`tensioning jack 34 is installed in its position for the
`post-tensioning operation described in connection with
`FIG. 5. As shown in FIG. 8, the tendons 16 extend
`
`CONCLUSION
`Although a preferred embodiment has been illus(cid:173)
`trated and described, it should be understood that the
`invention is not limited to the specifics of this embodi(cid:173)
`ment, but rather is defined by the following claims. For
`example, it is possible that the separate jacking pads
`illustrated in FIG. 3 might be omitted and that a pile cap
`with voids between the cap and the piles might be em(cid:173)
`ployed for use in the load-testing step. In such an ar(cid:173)
`rangement, the voids between the cap and piles would
`be filled after load testing and prior to the final stressing
`step.
`What is claimed is:
`1. A method of making a pre-tested anchored founda(cid:173)
`tion structure in which the anchor members carry com(cid:173)
`pressive loads and resist upward loads including the
`steps of:
`boring at least one pile hole into the sub-surface soil;
`inserting into each pile hole a sheath containing one
`or more tendons, said tendons extending from the
`lower end of said sheath into the bottom end of said
`pile hole, and extending from the top end of said
`sheath above the surface of the soil;
`forming a pile by pouring a concrete mixture into said
`hole to the exterior of said sheath, whereby the
`tendons extending from the lower end of said
`sheath become anchored to the bottom end of said
`pile but remain free for movement within said
`sheath;
`
`Exhibit - 1008
`NV5, Inc. v. Terracon Consultants, Inc.
`Page 5
`
`

`

`4,043,133
`
`5
`mounting a tensioning jack to a jacking pad supported
`on the soil surface out of bearing engagement with
`the pile to position the jack in spaced relationship
`above the top of said pile, and connecting said jack s
`to said tendons extending from the top end of said
`sheath; and
`actuating said tensioning jack to apply a tension to
`said tendons, whereby said pile and its surrounding 10
`soil is pre-tested to withstand a measured force thus
`applied, and whereby the soil beneath the bottom
`surface of said jacking pad is loaded.
`2. The method claimed in claim 1 further including 15
`the steps of;
`de-tensioning said tensioning jack and removing said
`jack and said jacking pad;
`forming and pouring a permanent concrete pile cap 20
`above and connected to the tops of said concrete
`piles;
`
`6
`re-installing a tensioning jack to the surface of said
`pile cap and attaching said jack to said extending
`tendons; and
`actuating said jack to apply tension to said tendons,
`whereby said pilings and said pile cap are com(cid:173)
`pressed into a unitary member.
`3. The method claimed in claim 2 further including
`the step of permanently anchoring said stressed tendons
`to said pile cap, and removing said tensioning jack.
`4. The method claimed in claim 3 further including
`the step of pumping cement grout into said sheath ex(cid:173)
`tending throughout the center of each of said pilings.
`5, The method claimed in Claim 4 further including
`the step of forming and pouring a top concrete section
`to said pile cap for sealing said anchored tendons within
`said pile cap.
`6. The method claimed in claim 2 further including
`the step of installing a stub angle during said step of
`forming and pouring a permanent concrete pile cap.
`7. The method claimed in claim 1 wherein at least two
`diverging holes are bored into the sub-surface soil.
`• • • • •
`
`25
`
`30
`
`35
`
`40
`
`4S
`
`so
`
`55
`
`60
`
`65
`
`Exhibit - 1008
`NV5, Inc. v. Terracon Consultants, Inc.
`Page 6
`
`

This document is available on Docket Alarm but you must sign up to view it.


Or .

Accessing this document will incur an additional charge of $.

After purchase, you can access this document again without charge.

Accept $ Charge
throbber

Still Working On It

This document is taking longer than usual to download. This can happen if we need to contact the court directly to obtain the document and their servers are running slowly.

Give it another minute or two to complete, and then try the refresh button.

throbber

A few More Minutes ... Still Working

It can take up to 5 minutes for us to download a document if the court servers are running slowly.

Thank you for your continued patience.

This document could not be displayed.

We could not find this document within its docket. Please go back to the docket page and check the link. If that does not work, go back to the docket and refresh it to pull the newest information.

Your account does not support viewing this document.

You need a Paid Account to view this document. Click here to change your account type.

Your account does not support viewing this document.

Set your membership status to view this document.

With a Docket Alarm membership, you'll get a whole lot more, including:

  • Up-to-date information for this case.
  • Email alerts whenever there is an update.
  • Full text search for other cases.
  • Get email alerts whenever a new case matches your search.

Become a Member

One Moment Please

The filing “” is large (MB) and is being downloaded.

Please refresh this page in a few minutes to see if the filing has been downloaded. The filing will also be emailed to you when the download completes.

Your document is on its way!

If you do not receive the document in five minutes, contact support at support@docketalarm.com.

Sealed Document

We are unable to display this document, it may be under a court ordered seal.

If you have proper credentials to access the file, you may proceed directly to the court's system using your government issued username and password.


Access Government Site

We are redirecting you
to a mobile optimized page.





Document Unreadable or Corrupt

Refresh this Document
Go to the Docket

We are unable to display this document.

Refresh this Document
Go to the Docket