`
`BEFORE THE PATENT TRIAL AND APPEAL BOARD
`
`APPLIED MATERIALS, INC.,
`Petitioner
`
`v.
`
`OCEAN SEMICONDUCTOR LLC,
`Patent Owner
`
`IPR2021-01342
`U.S. Patent No. 6,968,248
`
`
`
`
`
`PATENT OWNER’S AUTHORIZED SUR-REPLY
`IN SUPPORT OF PATENT OWNER’S PRELIMINARY RESPONSE
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`Mail Stop PATENT BOARD
`Patent Trial and Appeal Board
`U.S. Patent and Trademark Office
`P.O. Box 1450
`Alexandria, VA 22313-1450
`
`Submitted Electronically via PTAB E2E
`
`
`
`
`It is undisputed that: (1) the parallel actions are set for trial months before the
`
`FWD date with no stay sought by anyone; (2) there is a complete overlap1 of the
`
`issues and prior art and (3) an immense investment on invalidity issues in those
`
`actions; and (4) the defendants there have rejected being bound by this Petition.
`
`Extreme speculation about alternative outcomes cannot overcome these facts.
`
`I.
`
`FINTIV I FACTOR 1: THERE IS NO BASIS TO THINK THAT A
`STAY MAY BE ENTERED IN ANY, MUCH LESS ALL, OF THE
`EDTX/WDTX ACTIONS
`The granting of a temporary stay in the DMASS actions pending IPR
`
`institution decisions for the various patents asserted there does not tip the scale of
`
`this factor away from denial. As the court there noted (Exs. 2038 and 2039), whether
`
`a stay is warranted depends on the Board’s institution decision. Nothing in the
`
`court’s order impacts the WDTX or EDTX proceedings, nor is it predictive of what
`
`those courts will decide should a stay motion ever be filed. Petitioner’s reference to
`
`the DMASS actions is also a red herring because, as a non-party, it can never move
`
`for a stay in any of the WDTX, EDTX, or DMASS cases. While Petitioner cites to
`
`Juniper Networks v. WSOU Inv., that case is inapposite because the case did not
`
`involve: (1) a non-party Petitioner; and (2) a temporary stay. At best, this factor is
`
`neutral. See IPR2021-00929, Paper 13 at 9-10 (P.T.A.B. Nov. 16, 2021); IPR2021-
`
`00864, Paper 13 at 9-10 (P.T.A.B. Nov. 16, 2021).
`
`
`1 Unless otherwise indicated, all emphasis in this Sur-reply has been added.
`
`1
`
`
`
`II. FINTIV I FACTOR 2: THE TRIAL DATES ARE MONTHS BEFORE
`THE DEADLINE FOR A FINAL WRITTEN DECISION
`Petitioner’s contention that the EDTX cases have no trial date (Reply at 1) is
`
`unavailing because there will almost certainly be a trial long before an FWD. That
`
`the EDTX schedule does not contain an exact trial date does not alter the fact that
`
`the Final Pretrial Conference is set six months before any FWD here and the court’s
`
`established practice is to hold trial within three weeks thereafter. (Paper 9 at 1-2,
`
`12-14.) Even if trial slips several weeks, it will still occur over five months before
`
`a FWD. (Petitioner also misleadingly states that the WDTX trial dates are
`
`“tentative” (Reply at 1) when they have been set. (See Ex. 2001-2007 at 4.)
`
`Petitioner’s assertion that “overlapping trial dates [with unrelated actions] will
`
`necessarily result in rescheduling at least some of those trials” (Reply at 1) is
`
`unavailing as the Court has not even hinted at the possibility that the December 7,
`
`2022, trial date will be altered. The Board also need not entertain this line of
`
`arguments by Petitioner because the Board generally takes courts’ trial schedules at
`
`“face value.” IPR 2020-00019, Paper 15 at 13 (informative). In two pending IPRs
`
`involving Patent Owner and the WDTX actions, the Board took this exact position
`
`with respect to this factor and rejected the petitioner’s invitation to speculate trial
`
`delay. See IPR2021-00929, Paper 13 at 11; IPR2021-00864, Paper 13 at 11.
`
`Finally, the fact that Petitioner is not a party to the parallel actions is of no
`
`moment. Petitioner’s cited cases recognize as much. Bose Corp. v. Koss Corp.,
`
`2
`
`
`
`IPR2021-00680, Paper 15 at 15 (P.T.A.B. Oct. 13, 2021) (“Given that the trial is
`
`currently scheduled for . . . approximately five months before the final decision, the
`
`efficiency and system integrity concerns that animate the Fintiv analysis are present
`
`. . . .”); Dish Network v. Broadband iTV, IPR2020-01359, Paper 15 at 14 (Feb. 12,
`
`2021) (finding that a trial date “likely to happen prior to the Board’s final written
`
`decision . . . [is] in favor of exercising our discretion to deny the Petition.”); Western
`
`Digital v. Kuster, IPR2020-01391, Paper 10 at 9-10 (P.T.A.B. Feb. 16, 2021)
`
`(finding “uncertainty” in the trial date that is not present here).
`
`III. FINTIV I FACTOR 3: THERE HAS BEEN CONSIDERABLE
`“INVESTMENT IN THE PARALLEL PROCEEDINGS”
`Petitioner’s assertion of “no apparent relation” (Reply at 2-3) seems to
`
`improperly interpret this factor as the degree of investment only in the context of
`
`invalidity issues. But even so, Petitioner has ignored, in wholesale, the court’s and
`
`the parties’ immense resources expended in connection with patent (in-)eligibility
`
`(e.g., a 101 motion pending in Ocean Semiconductor LLC v. Renesas Electronics
`
`Corp., et al., No. 6:20-cv-01213-ADA, Dkt. 15 (W.D. Tex. Apr. 26, 2021)) as well
`
`as anticipation/obviousness contentions set forth in the defendants’ preliminary/
`
`final invalidity contentions served in the EDTX and WDTX proceedings. Also, as
`
`the WDTX Court has already issued a claim construction order for the present
`
`patent (Ex. 2040)—a major milestone—this factor favors discretionary denial.
`
`Fintiv II at 13-14 (holding, inter alia, that the issuance of a claim construction
`
`3
`
`
`
`order “weighs somewhat in favor of discretionary denial . . . .”).
`
`IV. FINTIV I FACTOR 4: THERE IS COMPLETE “OVERLAP
`BETWEEN ISSUES RAISED”
`Petitioner’s contention that the court actions involve additional prior art is a
`
`red herring—this fact has no impact on the complete overlap between references
`
`raised in the IPR and the co-pending litigations. Also, while, as in Bose (Reply at
`
`3), there are additional challenged claims here—most of which are dependent—the
`
`Board has nonetheless repeatedly found a “substantial overlap” between the issues
`
`in an IPR and co-pending litigation that weighed in favor of discretionary denial in
`
`very similar circumstances. See, e.g., Apcon, Inc. v. Gigamon Inc., IPR2020-01579,
`
`Paper 9 at 19, 26 (P.T.A.B. Mar. 16, 2021) (“Although Petitioner has challenged. . .
`
`additional dependent claims. . . , we do not determine including these additional
`
`claims to weigh in favor of or against institution. . . . [T]he art appears substantially
`
`the same, and no stipulation has been filed by Petitioner agreeing not to assert the
`
`same art”); Satco Productions, Inc. v. The Regents of the Univ. of Cal., IPR2021-
`
`00661, Paper 14 at 24 (P.T.A.B. Nov. 8, 2021) (same).
`
`V. FINTIV I FACTOR 5: WHETHER PETITIONER IS A DEFENDANT
`Petitioner’s purported distinction over Apple and Mylan is unavailing
`
`because the petitioners in those two cases, like Petitioner here, also are not
`
`defendants in the underlying litigation. Also, nothing prevents Petitioner from
`
`filing a declaratory judgment action “to litigate the [’248] patent claims’ validity in
`
`4
`
`
`
`its own district court case,” which would afford Petitioner a forum to present its
`
`challenge. Dolby cited by Petitioner is inapposite, as it cannot overcome the
`
`PTAB’s precedential decision noting that Factor 5 weighs in favor of denial of
`
`institution—as it does here—even where a petitioner that is not a defendant in a
`
`co-pending action. (Paper 9 at 25, citing Fintiv I at 14).
`
`VI. FINTIV I FACTOR 6: OTHER CIRCUMSTANCES FAVOR NON-
`INSTITUTION
`The merits, even at this early stage, are in Patent Owner’s favor. Gupta’s
`
`local optimization cannot be simultaneously applied to “every tool in the fab.”
`
`Rather, and as repeatedly emphasized throughout the patent’s written description,
`
`it can only be applied piecemeal, lest the “prohibitive computational resources”
`
`demanded by scheduling for the entire fab prove too much for the system to bear.
`
`(Ex. 1006 at 14:1-4.) Further, Petitioner’s assertion that scheduling “would be
`
`desirable” in Gupta is incorrect because the local optimization’s reliance on
`
`calculation of simulated process steps is not reactive. (See discussion at Paper 10
`
`at 38-39.) Finally, Petitioner also fails to provide any meaningful rebuttal to the
`
`fact that Gupta’s six-minute time steps, involving changes responsive to a
`
`predictive step, are inconsistent with “reactive scheduling,” instead misleadingly
`
`characterizing Patent Owner’s position as arguing that “reactive scheduling”
`
`requires “zero delay” between process steps, when Patent Owner never so argued.
`
`(See id. at 43-47.)
`
`5
`
`
`
`Dated: December 20, 2021
`
`
`
`
`
`DEVLIN LAW FIRM LLC
`
`/s/ Timothy Devlin
`Timothy Devlin
`Registration No. 41,706
`tdevlin@devlinlawfirm.com
`Alex Chan
`Registration No. 52,713
`achan@devlinlawfirm.com
`1526 Gilpin Avenue
`Wilmington, DE 19806
`(302) 449-9010
`
`Attorneys for Patent Owner
`
`
`
`
`
`6
`
`
`
`CERTIFICATE OF SERVICE
`The undersigned certifies that the foregoing document was served
`
`electronically via electronic mail on December 20, 2021, on the following counsel
`
`of record for Petitioners:
`
`LEAD COUNSEL
`
`Eric A. Krause (Reg. No. 62,329)
`Axinn, Veltrop & Harkrider LLP
`560 Mission Street
`San Francisco, California 94105
`Phone: 415-490-1491
`Fax: 415-490-2001
`ekrause@axinn.com
`
`
`Counsel for Applied Materials, Inc.
`BACKUP COUNSEL
`
`Christopher M. Gallo (Reg. No. 70,291)
`Axinn, Veltrop & Harkrider LLP
`1901 L Street NW
`Washington, DC 20036
`Phone: 202-721-5413
`Fax: 202-912-4700
`cgallo@axinn.com
`
`
`
`/s/ Timothy Devlin
` Timothy Devlin
`
`
`7
`
`