throbber
Vestas Ex 1019-p. 1
`Vestas v GE
`
`Wind Engineering 29-3_final 17/8/05 5:31 pm Page 201
`
`WIND ENGINEERING VOLUME 29, NO. 3, PP 201–215
`
`201
`
`The development of grid code requirements for new
`and renewable forms of generation in Great Britain
`
`Antony Johnson and Nasser Tleis,
`Network Design, National Grid Company,
`NGT House,Warwick Technology Park,Warwick, England, CV34 6DA
`Tel:- +44 (0) 1926 655466, Fax:- +44 (0) 1926 656521
`http://www.nationalgrid.com
`Antony.Johnson@ngtuk.com
`Nasser.Tleis@ngtuk.com
`
`ABSTRACT
`This paper presents the development of Grid Code requirements for new and renewable
`forms of generation in Great Britain (GB). After briefly describing the background to the GB
`Transmission System and the volume of renewable generation which is anticipated to
`connect in the future, the paper discusses the Grid Code and Grid Code change process. In
`particular, the paper discusses the interfaces with key stakeholders, the technical issues
`considered in connecting other generation technologies to the Transmission network and
`the rationale for the final Grid Code requirements. The technical issues discussed include
`fault ride through, frequency range, frequency response, power/frequency characteristic,
`reactive range, voltage control and power quality. The paper concludes with the
`experiences gained in the connection of wind generation projects to the GB Transmission
`System both before and after the approval of new proposals to the GB Grid Code.
`
`Keywords: Grid Code, Technical Performance Requirements, Renewable Embedded
`Generation.
`
`I INTRODUCTION
`The National Grid Company (NGC) is a privately owned utility which owns and operates the
`high voltage Transmission Network in England and Wales. NGC is a wholly owned subsidiary
`of National Grid Transco (NGT) and is the holder of the GB (Great Britain) Transmission
`Licence. NGT also own and operate the high pressure gas transmission network in Great
`Britain. The company has a number of operations in both gas and electricity throughout the
`world in particular the North Eastern United States. Following the introduction of the British
`Electricity Trading and Transmission Arrangements (BETTA), introduced on 1 April 2005,
`NGC became responsible for operation of the entire Transmission System in Great Britain
`(England and Wales, and Scotland). The transmission networks in Scotland remain under the
`ownership of the Scottish Transmission companies (Scottish Power Transmission (SPT) and
`Scottish Hydro-Electric Transmission Limited (SHETL)).
`Figure 1 shows the layout of the GB Transmission System. Full details of the GB
`Transmission System including network structure, demand and generation backgrounds are
`detailed in [1]. Under its Transmission Licence, NGC has an obligation to ensure a safe, secure
`and economical transmission system and ensure non discrimination amongst System Users.
`
`

`

`(cid:127) (cid:127) ..
`



`
`Vestas Ex 1019-p. 2
`Vestas v GE
`
`Wind Engineering 29-3_final 17/8/05 5:31 pm Page 202
`
`202
`
`THE DEVELOPMENT OF GRID CODE REQUIREMENTS FOR NEW AND
`RENEWABLE FORMS OF GENERATION IN GREAT BRITAIN
`
`To ensure NGC continues to meet these requirements, its activities are overseen by the
`Government Regulator “Ofgem”.
`
`BOUNDARY OF INFLUENCE
`AS AT OCTOBER 2004
`
`TRANSMISSION SYSTEM
`AS AT 1st DECEMBER 2003
`
`400kV Substations
`275kV Substations
`132kV Substations
`400kV CIRCUITS
`275kV CIRCUITS
`132kV CIRCUITS
`
`Major Generating Sites
`Including Pumped Storage
`
`Dounr eay
`
`Thur so
`
`Mybste r
`
`Stornoway
`
`Cassley
`
`Dunbea th
`
`Lairg
`
`Shin
`
`Brora
`
`Mossfo rd
`
`Grudgie
`Bridge
`
`Conon
`
`Luichart
`
`Orrin
`
`D ingwall
`
`Alness
`
`Deanie
`
`Cull igran
`
`Alga s K ilmorack
`
`Inv erne ss
`
`Nairn
`
`Elgin
`
`Keith
`Keith
`
`Macduff
`
`S trichen
`
`Beauly
`
`Blackhill ock
`
`Fraser burgh
`
`Fras erbur gh
`
`S t. Ferg us
`
`P eterhead
`P eterhead
`
`Fasn akyle
`
`Great
`Glen
`
`Quo ich
`
`Fort
`William
`
`Kilchrennan
`
`Dalm ally
`
`Foye rs
`
`Fort
`August us
`
`Inv erga rry
`
`B oat of
`Garten
`
`K intore
`
`Dyce
`
`Wood
`Hill
`
`Tarla nd
`
`Craig iebuckle r
`
`Persl ey
`
`Willowdale
`
`Clay hills
`
`Redmos s
`
`Fiddes
`
`Ranno ch
`
`Err ochty
`
`Pitio chry
`
`Tum mel
`B ridge
`
`Cash ley
`
`Lochay
`
`Killin
`
`Finlarig
`
`C lunie
`
`Bridge of Du n
`
`Tealin g
`
`Luna Head
`
`Dudhope
`
`Arbroa th
`
`Lyndhurst
`
`Milton of Crai gie
`
`C harlston
`B urghmuir
`
`Glenagne s
`
`Dudhop e
`
`Nant
`
`Inver aray
`
`Clachan
`
`Sloy
`
`St. Fillans
`
`B raco
`
`Glenrot hes
`
`Westfield
`
`Port
`Ann
`
`Devol
`Moor
`Inver kip
`
`Wind yhill
`
`B onnyb ridge
`
`Kincar din e
`
`Easte rhouse
`
`Lon ganne t
`
`Gra ngem outh
`
`S ighthill
`
`Torn ess
`
`Cocke nzie
`
`Dunoo n
`
`Neil son
`
`Newa rthill
`
`Cume
`
`Smea ton
`
`Carr ada le
`
`H unterst one
`
`A yr
`
`Wis haw
`
`Strathaven
`
`Linmill
`
`E lvanf oot
`
`K ilmarnock
`S outh
`
`Coylt on
`
`Ecc les
`
`A uchencr osh
`
`Harke r
`
`Fours tone s
`
`S tella
`W est
`
`Blyth
`
`Tynemouth
`South Shields
`
`West Boldon
`
`Off erton
`
`Spennymoo r
`
`Hawt horn e Pit
`
`Hart M oor
`
`Hartl epool
`
`Salth olme
`
`Tod Point
`Grangetown
`
`N orton
`
`Gre ystones
`
`Lacke nby
`
`Hutton
`
`H eysham
`
`Que rnmore
`
`Stanah
`
`Padih am
`
`Popple ton
`
`Os baldwic k
`
`Tho rnton
`
`Bradfo rd
`West
`
`Kirkstall
`
`Skelt on
`Gran ge
`
`Monk
`Frys ton
`
`Connected at 400kV
`Connected at 275kV
`Hydro Generation
`
`Creyke Beck
`
`Salt end Nor th
`
`Salt end Sou th
`
`Penworth am
`
`E lland
`
`Roch dale
`
`Ferryb ridge
`
`K earsley
`
`Whit egate
`
`Templeboro ugh
`
`Drax
`
`E ggb orough
`
`Killingholme
`H umber Ref ine ry
`
`Keadby
`
`Wyl fa
`
`P entir
`
`Dinorwig
`
`Ffes tiniog
`
`Trawsfyn ydd
`
`Was hway
`Farm
`
`Kirkby
`
`Liste r
`Drive
`
`Rain hill
`
`S outh
`Manchest er
`
`Birkenhead
`
`Capenh urst
`
`Deesid e
`
`Carring ton
`
`Fiddle rs
`Ferry
`Frodsh am
`
`Staly brid ge
`
`Bredbur y
`
`S tocksbri dge
`Win co Bank
`Neepse nd
`Sheff ield C ity
`
`Daine s
`
`Maccle sfield
`
`Jordant horpe
`
`Cheste rfield
`
`West
`Melton
`
`Pits moor
`
`Tho rpe
`Marsh
`
`Aldwarke
`
`Thurcr oft
`
`Brins worth
`
`Norto n Lees
`
`H igh
`Marnham
`
`Stayth orpe
`
`S outh
`Humber
`Bank
`
`Grimsb y
`West
`
`West
`Burto n
`
`Cottam
`
`Legacy
`
`Cell arhead
`
`Willington
`
`Ratcl iffe
`
`Rugel ey
`
`D rakelow
`
`Ironbrid ge
`
`Shrewsbur y
`
`P enn
`
`Bush bury
`Willenhall
`
`Bustl eholm
`
`Nechells
`
`Hams
`H all
`
`Enderby
`
`Ocker
`H ill
`
`Oldbury
`
`K itwell
`
`Berks well
`
`Covent ry
`
`Walp ole
`
`Spald ing
`North
`
`N orwich
`Main
`
`Bishop s
`Wood
`
`Feckenham
`
`Grendon
`
`Eaton
`Soco n
`
`Burwe ll
`Main
`
`Rass au
`
`Walh am
`
`Imperial
`Park
`
`P atford
`B ridge
`
`East
`Clay don
`
`Leighto n
`Buzz ard
`
`Cowley
`
`Sundon
`
`Pelha m
`
`Wymo ndley
`
`B raintree
`
`Rye House
`
`Brim sdown
`
`Wal tham
`Cross
`
`S izew ell
`
`Bramf ord
`
`Pembro ke
`
`Swa nsea
`North
`Bagla n
`
`Bay
`
`Margam
`
`Pyle
`
`Cilfyn ydd
`
`U skmo uth
`
`Whitson
`
`Upper Boat
`
`A lpha Stee l
`
`S eab ank
`
`Iron Act on
`
`Minety
`
`Cowb ridge
`
`Aberthaw
`
`Trem orfa
`
`C ardiff
`East
`
`Melksham
`
`Braml ey
`
`A mersham Main
`
`Watford
`
`Elst ree
`
`Hackn ey
`
`Culham
`D idcot
`
`Iver
`
`N.Hy de
`
`Mill Hill
`Willesden
`
`Ealin g
`
`Tottenham
`
`Redbrid ge
`
`Barki ng
`
`Laleham
`
`St Jo hns
`Wood
`
`City Rd
`
`W.Ham
`
`Hurst
`
`New
`Cross
`
`West
`Weyb ridge
`
`C hessingto n
`
`Rowd own
`Beddin gton
`
`Fleet
`
`Wimb led on
`
`Alverdi scott
`
`H inkley Poin t
`
`Bridgwater
`
`Taunton
`
`Axmi nst er
`
`Exeter
`
`C hickere ll
`
`Indian
`Que ens
`
`Land ulph
`
`Abham
`
`Nursl ing
`
`B oln ey
`
`Mannington
`
`Fawle y
`
`Botle y Wo od
`
`Lovedean
`
`N infield
`
`Peak Demand = 58.8 GW
`Minimum Demand = 22GW
`
`Figure 1.
`
`Overview of the GB Transmission System.
`
`Warle y
`West Thurr ock
`North fleet East
`
`Rayl eig h Ma in
`
`Coryt on
`
`Tilbury
`
`Grain
`
`S ingle well
`
`N orthfleet
`West
`
`Littlebrook
`
`K ingsnorth
`
`K emsley
`
`Canterbu ry
`North
`
`Sellindge
`
`E de F
`
`Dungen ess
`
`2. PRESENT AND FUTURE TRENDS FOR WIND GENERATION IN GREAT BRITAIN
`Following the Kyoto protocol, the UK Government set a target of 10% of electricity
`requirements in England and Wales to be sourced from renewable generation technologies by
`2010, which has subsequently increased to 15% by the year 2015. In Scotland, the Scottish
`Parliament have a commitment to achieving 18% renewable generation by the year 2010,
`increasing to 40% by the year 2020. Whilst this target includes all forms of renewable
`
`

`

`(cid:141)
`
`SHETL
`
`•
`• •
`•• •
`
`•
`
`11GW
`
`6GW
`
`•
`
`NGC
`
`8GW
`
`• ROUND 1 SITES OFFSHORE
`ROUND 2 AREAS OFFSHORE
`
`Vestas Ex 1019-p. 3
`Vestas v GE
`
`Wind Engineering 29-3_final 17/8/05 5:31 pm Page 203
`
`WIND ENGINEERING VOLUME 29, NO. 3, 2005
`
`203
`
`generation, a large proportion of this is expected to come from wind, especially since, to
`encourage renewable generation, the UK Government introduced a number of incentives.
`These include additional payments to generators who supply “Green Energy” through the
`issue of “Renewable Obligation Certificates” (ROC’s), the requirement for Suppliers to source
`a proportion of their energy from renewable sources and the issue of grants for the
`development of renewable generation projects.
`In Scotland, the naturally good wind resource and its geographic characteristics have
`resulted in interest amongst a number of developers for onshore sites. By the end of December
`2004, the Scottish Transmission Licensees had received a total of nearly 17 GW of wind farm
`applications. It should however be noted that a number of these projects would be considered
`as speculative and may not proceed to the construction phase.
`In England and Wales, interest has also been shown in onshore wind farms although to
`date, these have tended to be less than 50 MW in size. The majority of growth is expected to be
`in offshore wind farms around the England and Wales coast. These have been promoted
`through the Round 1 and Round 2 Government offshore wind farm programmes. Under
`Round 1, developers have leased offshore seabed sites (less than 12 nautical miles from the
`coast) for the purposes of developing wind farms up to a maximum of 30 turbines. Under the
`Round 1 programme some 1.3 GW of offshore wind generation are expected to connect over
`the next few years. Round 2 is a much larger programme with tendering resulting in the
`connection of some 7.1 GW of additional offshore wind farm generation. A graphical
`representation of these figures is shown in Figure 21, which portrays both onshore and
`offshore wind farm projects.
`
`Figure 2.
`
`Potential future Wind Farm Connection Activity in Great Britain as of 31 December 2004
`
`1Figure 2 details the Round 1 and Round 2 development sites for offshore wind farms. Further details are
`available from:- http://www.thecrownestate.co.uk/34_r1_r2_windfarm_location_maps_04_08_13.pdf
`
`

`

`Vestas Ex 1019-p. 4
`Vestas v GE
`
`Wind Engineering 29-3_final 17/8/05 5:31 pm Page 204
`
`204
`
`THE DEVELOPMENT OF GRID CODE REQUIREMENTS FOR NEW AND
`RENEWABLE FORMS OF GENERATION IN GREAT BRITAIN
`
`In respect of these programmes and other projects, NGC has witnessed increasing activity
`from interested developers in connecting wind farms to the GB Transmission System.
`
`3. THE GRID CODE AND THE NEED FOR CHANGE
`Under the terms of its Transmission Licence, NGC is required to maintain a Grid Code. The Grid
`Code was originally developed in 1989 to facilitate privatisation of the UK Electricity Supply
`Industry in 1990. The Grid Code defines the technical and operational requirements on all
`Users of the GB Transmission System and was based on previous decades of network design
`and operational experience. Originally, the technical requirements for generating plant were
`specified in terms of large synchronous machines.
`Wind turbines rely on generator technologies [2] which exhibit very different operational
`characteristics to their synchronous counterparts. Since the operational characteristics of a
`transmission system are largely dictated by the generation and demand, it was important to
`ensure that NGC could continue to meet its statutory obligations (including the Security and
`Quality of Supply Standards, specified under its Licence) whilst facilitating the connection of
`the forecast large volumes of wind generation. Consequently it was recognised that the Grid
`Code was vague in its treatment of renewable generation technologies and changes would be
`required to provide a transparent set of technical requirements to all users. NGC had also
`observed the growth of wind generation in Germany and Denmark and the corresponding
`technical requirements that had been introduced in these and other countries [5], [6], [8].
`
`4. THE GRID CODE CHANGE PROCESS
`The Grid Code applies to all users of the GB Transmission System and is an industry wide
`document whose governance is managed by the Grid Code Review Panel (GCRP). This panel
`represents a cross section of the industry and includes representatives from generating
`companies, distribution companies, inter-connector operators, transmission companies and
`large customers. The Regulator attends meetings as an observer. Any member of the Grid
`Code Review Panel including NGC, can propose a change to the Grid Code although changes
`must be subject to a consultation process and approved by the Regulator before
`implementation.
`
`4.1. The grid code change process for renewable generation
`In September 2002, NGC submitted a paper to the Grid Code Review Panel proposing a change
`to the Grid Code in respect of renewable generation. To minimise future work, the terms of
`reference included all forms of renewable generation, in addition to wind farms. A working
`group (the Generic Provisions Working Group (GPWG)) was established which included
`representatives from generating companies, distribution companies, inter-connector
`operators, trade associations (such as the British Wind Energy Association) and NGC with the
`Regulator attending as an observer. The aim of the working group was to develop a set of Grid
`Code proposals for new and renewable forms of generation suitable for industry wide
`consultation.
`Key parts of the process involved in developing the Grid Code proposals both in England
`and Wales and Scotland are shown in Figure 3. A comprehensive account of this process is
`detailed in [3] [4].
`
`

`

`OctobeiJoilt-::·Ckfubli-jjOJ--1
`England & Wales~
`.Q.urnp followed by Industry
`Wide Consultation D/03 and
`r~_Q!:! .. ~.o_.Q_fg~_
`
`r------<11>-----, i consultations in Scotland and
`
`March - Doc ember 2002
`Two industry wide
`
`i
`
`report to Ofgem
`
`November 2003 - Marth 2004
`I Three Transmission Licensees in Great I
`! Britain align requirements and furtho- !
`! consult with wind twbine manufacturo-s !
`'
`on capabilities & costs
`'
`
`~ ,
`
`March - April 2004
`
`, L,
`l ll1/:J~1~:~~dJ;~~:~~IJ l
`
`June - August 2004
`Industry Wide Consultation
`H/04 forEnglandandWales
`Grid Code
`- Report to Of gem for approval
`
`June -~
`Industry Wide Consultation
`SA2004 for Scottish
`, -~------, Grid Code-Report to Ofgem
`for approval
`
`1
`
`N<mmb,,- 2004 - Fetrua,y 2005
`Ofgemconsult ona combined GB Grid
`Code basis with a Regulatory Irrq:iact
`Assessment
`
`Man:h- Jme 2005
`i Ofgemconsider Consultation Responses
`'
`and apirove Grid Code proposals
`(subject to minor changes) an I June
`2005
`
`Vestas Ex 1019-p. 5
`Vestas v GE
`
`Wind Engineering 29-3_final 17/8/05 5:31 pm Page 205
`
`WIND ENGINEERING VOLUME 29, NO. 3, 2005
`
`205
`
`Figure 3.
`
`Diagram of the Grid Code Change Process for Renewable Generation.
`
`The key stages to note as part of the Grid Code development process included, alignment
`of the Scottish and the England and Wales proposals in preparation for a single GB Grid Code,
`detailed discussions with turbine manufacturers, fully open dialogue with all stakeholders at
`discussion forums arranged by the Regulator, full industry wide consultations for all
`interested parties and a Regulatory Impact Assessment.
`
`5. EXPERIENCES OF ADOPTING A GRID CODE TO INCLUDE REQUIREMENTS FOR
`RENEWABLE GENERATION
`The declared aim of all stakeholders involved in the Grid Code process was to enable wind
`generation to connect to the GB Transmission System without undue restriction whilst
`ensuring the continued safety, security and economy of supply. When the Generic Provisions
`Working Group was first established in October 2002, there was a significant difference of
`opinion between the stakeholders. These could be summarised into four key interest groups:-
`
`I.
`
`II.
`
`III.
`
`IV.
`
`Wind Farm developers were reluctant to accept any requirements on the basis of
`additional cost incurred and that technology was still at the proving stage.
`Existing System Users including nuclear power stations and those having no wind
`generation projects were keen to maintain safety, security and economy of supply
`and ensure a level playing field amongst Users.
`Manufacturers were generally supportive of a clear set of technical requirements as
`a basis for increasing market share.
`Utilities required the development of technical requirements for wind generation to
`meet Transmission Licence obligations for maintaining system security and
`stability.
`
`As the process developed, these views started to converge as more information was
`gained from manufacturers’ turbine generator capabilities, experience overseas, additional
`costs and a continuous review of the technical requirements based on transmission system
`
`

`

`Vestas Ex 1019-p. 6
`Vestas v GE
`
`Wind Engineering 29-3_final 17/8/05 5:31 pm Page 206
`
`206
`
`THE DEVELOPMENT OF GRID CODE REQUIREMENTS FOR NEW AND
`RENEWABLE FORMS OF GENERATION IN GREAT BRITAIN
`
`need. When the H/04 and SA2004 proposals were submitted to the Regulator in late August
`2004, there had been significant movement by all stakeholders. At this stage however, the
`impending introduction of a single electricity market (BETTA) scheduled for 1 April 2005,
`needed a single GB Grid Code, irrespective of the changes required for renewable generation.
`In view of this, the proposals from consultation H/04 and SA2004 were redrafted within the
`framework of the combined GB Grid Code. Ofgem then held a further industry wide
`consultation in January and February 2005, releasing a Regulatory Impact Assessment at the
`same time. After due consideration of the responses from Users to the consultation, Ofgem
`approved the Grid Code proposals (subject to minor changes) to become effective from 1 June
`2005. The full determination by the Regulator is available in [13].
`
`6. SPECIFIC TECHNICAL ASPECTS OF THE GRID CODE REQUIREMENTS
`The aim of the Grid Code modifications was to develop a set of technical requirements which
`would meet the minimum security and stability needs of the transmission system, ensure non
`discrimination between technology types and enable maximum flexibility for developers. For
`this reason, all the technical requirements were based at the point of connection to the Public
`Electricity System rather than at the turbine terminals. Before any Grid Code proposals could
`be drafted, the Transmission Licensees had to understand the behaviour, operation and
`characteristics of non-synchronous generator technologies such as wind turbines. This was
`achieved through information received at seminars, conferences, literature searches of Grid
`Code work, liaison with manufacturers and detailed system modelling studies.
`A number of key issues were identified including fault ride through, frequency range,
`frequency control, power frequency characteristic, voltage / reactive control, power quality
`and data requirements. The technical issues and rationale behind these requirements are
`briefly described below.
`
`A. Fault ride through
`In the event of a significant three-phase transmission system fault, the voltage at the point of
`fault will be zero on all three phases. Due to the small impedance of the transmission lines, the
`voltage depression will be experienced across large geographical areas of the Transmission
`system as shown in Figure 4.
`Where a generating plant is directly connected to a faulted circuit, it will be disconnected,
`i.e. ‘lost’. However, generation connected to adjacent healthy circuits separated by circuit
`breakers would be expected to remain connected and running. Synchronous generating plant
`is required to continue to operate through the transient voltage depression that accompanies
`a network fault provided the fault is cleared in sufficient time to prevent pole slipping.
`However, some early designs of non synchronous generator technologies which employed
`power electronic converters were susceptible to tripping even if the terminal voltage only fell
`below 80% of nominal for periods shorter than that expected for transmission fault clearance.
`Under the Security and Quality of Supply Standards, NGC currently cater for a maximum
`instantaneous generation loss of 1320 MW. From the results shown in Figure 4, and the
`potential risk of wind farm tripping under short duration low voltage conditions, it possible
`that 1320 MW of generation could trip with the additional loss of neighbouring wind farms
`connected to healthy circuits. The corresponding fall in system frequency could result in
`excursions to limits approaching the threshold of the automatic low frequency demand
`disconnection scheme, which if operated would result in wide spread customer demand
`disconnection. Alternatively, the connection of wind generation would have to be
`
`

`

`(cid:127)
`(cid:143)
`(cid:143)
`(cid:127)
`(cid:143)
`(cid:143)
`
`(cid:127)
`(cid:143)
`(cid:127)
`(cid:143)
`
`Vestas Ex 1019-p. 7
`Vestas v GE
`
`Wind Engineering 29-3_final 17/8/05 5:31 pm Page 207
`
`WIND ENGINEERING VOLUME 29, NO. 3, 2005
`
`207
`
`significantly constrained thereby resulting in a shortfall against government energy targets
`with additional constraint issues for future conventional generation which intended to
`connect adjacent to future wind-farm sites. Not only would it prevent future opportunities to
`developers, but also it would limit the market for manufacturers.
`
`Scotlan
`d
`
`Location of
`Fault
`
`Fault Location
`
`15 - 30% Volts
`
`40 - 50% Volts
`
`60 - 70% Volts
`
`80 - 90% Volts
`
`0 - 15% Volts
`
`30 - 40% Volts
`
`50 - 60% Volts
`
`70 - 80% Volts
`
`East Coast Round 2 Connection Area
`
`Figure 4.
`
`Network retained voltage during a transmission system fault.
`
`In consideration of these issues, NGC developed a set of technical requirements based on
`the minimum stability needs of the Transmission System. They where supported through
`system studies, manufacturer liaison meetings (Appendix 2 Section 7 [11]), publicly available
`literature and the requirements specified by overseas utilities [5], [6], [7] and [8]. Although
`alternatives, such as fast disconnection and reconnection of turbines, were initially
`investigated, these were rapidly rejected on the basis that they would not meet the stability
`requirement. The fault ride through requirements are detailed in the Grid Code [14]
`Connection Conditions clause, CC.6.3.15, and can be summarised as follows:-
`
`1)
`
`The plant should remain connected and transiently stable for any fault on the 400 or
`275 kV Transmission System for a total fault clearance time of up to 140 ms.
`
`

`

`Vestas Ex 1019-p. 8
`Vestas v GE
`
`Wind Engineering 29-3_final 17/8/05 5:31 pm Page 208
`
`THE DEVELOPMENT OF GRID CODE REQUIREMENTS FOR NEW AND
`RENEWABLE FORMS OF GENERATION IN GREAT BRITAIN
`
`Following fault clearance, the plant should generate at least 90% of the pre-fault
`active power which should be available within 0.5 seconds of recovery of the
`voltage at the connection point. During the period of the fault, the plant is required
`to generate maximum reactive power without exceeding the rating of the machine.
`In addition, the plant shall be required to remain connected and transiently stable
`for other disturbances which could include remote faults cleared in backup
`operating times. To achieve this objective, the plant is required to remain connected
`and transiently stable for supergrid voltages above the heavy black line shown in
`Figure 5.
`
`Supergrid Vo ltage
`(% of Nominal)
`
`208
`
`2)
`
`3)
`
`90
`85
`80
`
`15
`
`
`
`0.14s
`
` 1.2s
`
`
` 2.5s
`
` 3 minutes
` Supergrid Voltage Duration
`
`Figure 5.
`
`Voltage Duration profile.
`
`4)
`
`5)
`
`For slow clearing faults, the plant is required to achieve the same requirements as
`defined in item 2) above, although the active power restoration is only required in
`proportion to the retained supergrid voltage. In addition, 90% of the active power
`must be achieved within 1 second of restoration of the supergrid voltage to nominal
`levels. An allowance is made if the wind speed has dropped after the disturbance
`has been cleared.
`Relaxation’s were added to these requirements in the situation where less than 5%
`of the turbines were running or under very high wind speed conditions when more
`than 50% of the turbines in a wind farm had been shut down.
`
`While specific to Great Britain, the above requirements are consistent with those of other
`international utilities. A large number of manufactures advised that solutions were available
`which would result in minor additional costs. In addition, independent studies [9]
`demonstrated that fault ride through capability was cost effective for customers if large
`penetration levels were to be accommodated within the system.
`
`

`

`......,._,. ---
`
`.,..~
`
`Vestas Ex 1019-p. 9
`Vestas v GE
`
`Wind Engineering 29-3_final 17/8/05 5:31 pm Page 209
`
`WIND ENGINEERING VOLUME 29, NO. 3, 2005
`
`209
`
`B. Frequency range
`The NGC Transmission System operates to a nominal frequency of 50 Hz. Currently all the
`plant of system users is required to operate over a continuous frequency range of 47.5 – 52.0
`Hz and 47.0 – 47.5 Hz for a period of 20 seconds.
`The ability of generating plant to maintain operation over this frequency range is required
`in order to (i) avoid a frequency collapse for additional generation losses, and (ii) minimise the
`risk of partial or total system shutdowns during larger system disturbances. Since the system
`frequency is dependant on the total generation and load, it is essential that all generating plant
`is capable of operating over the same frequency range. On this basis, the same frequency
`range was applied to renewable generating plant as was to synchronous generating plant.
`Manufacturers were able to confirm that their plant was capable of meeting such a
`requirement.
`
`C. Power frequency characteristic
`Whilst the generation connected to the System is required to operate over the full frequency
`range, it is essential that the power output of the generating plant over this range is controlled
`to minimise the effect of a system frequency collapse or over-speed situation. Existing
`synchronous generating plant is required to maintain 100% of its active power output between
`49.5Hz – 50.4 Hz. Between 49.5 to 47.0 Hz the power output should not fall by more than pro-
`rata with frequency (i.e. at 47.0 Hz, the power output should be no less than 95% of that at 49.5
`Hz). For frequencies in excess of 50.4 Hz, the power output should be reduced by at least 2% of
`output for each 0.1 Hz rise in system frequency above 50.4 Hz.
`The requirement for the power output not to fall by more than pro-rata with frequency
`below 49.5 Hz is to ensure that the additional generation loss is not greater than the natural
`drop in demand that accompanies falling system frequency. The requirements which exist for
`synchronous plant were therefore applied to renewable generating plant (including wind
`farms). Similar requirements had been adopted in Germany [5] and manufacturers confirmed
`such a requirement would not create technical or commercial issues.
`
`D. Frequency control
`One of the principle requirements of the Electricity Safety, Quality and Continuity
`Regulations 2002 is that there should not be a permanent change in system frequency outside
`the statutory limits of 50.0 Hz ± 0.5 Hz.
`
`5 0 .4
`
`5 0 .3
`
`5 0 .2
`
`5 0 .1
`
`5 0
`
`4 9 .9
`
`4 9 .8
`
`4 9 .7
`
`4 9 .6
`
`4 9 .5
`
`4 9 .4
`
`FREQUENCY (Hz)
`
`Frequenc y Trace, 2 6-M ay-200 3
`
`Pr(cid:0)im(cid:0)ar(cid:0)y R(cid:0)es(cid:0)po(cid:0)ns(cid:0)e (cid:0)0 (cid:0)- (cid:0)30(cid:0) s(cid:0)ecs(cid:0)
`
`Se(cid:0)co(cid:0)nd(cid:0)ar(cid:0)y R(cid:0)es(cid:0)po(cid:0)ns(cid:0)e 30(cid:0) s(cid:0)ec(cid:0)s (cid:0)- (cid:0)30(cid:0) m(cid:0)in(cid:0)s(cid:0)
`
`5 0 .4
`
`5 0 .3
`
`5 0 .2
`
`5 0 .1
`
`5 0
`
`4 9 .9
`
`4 9 .8
`
`4 9 .7
`
`4 9 .6
`
`4 9 .5
`
`4 9 .4
`
`FREQUENCY(Hz)
`
`00:37:00
`
`00:36:00
`
`00:35:00
`
`00:34:00
`
`00:33:00
`
`T IM E ( G M T)
`
`frequency
`
`target freq
`
`Figure 6.
`
`Secured credible instantaneous generation loss of 1175 MW.
`
`

`

`F""~,.,, I i
`
`:
`
`'
`
`Time(c)
`
`~ : \ ............ ~ -:--: - - -~
`
`r,
`
`T n -------r.:1~:::~:::,"""'=·"''"'""'""'~,m~--- T o
`
`I
`
`T,
`
`()um'lltd
`WinclPo""'c-r
`(MW)
`
`RHDQOSI! fi:om a Wind Farm for a Hieb SV.mm....uealllD&Y..
`i ...... / \ .. (············\······.·\r-=
`
`j
`
`_.,,.._.. ..... --..
`
`••• Polenlllal Peak Outpd
`
`-
`
`RHponslvti Output
`
`Frcqumcy
`Oni.tion
`(1h)
`• 0.5
`
`I
`
`: v
`
`Timc(t)
`
`\.,__
`
`1in1t(t)
`
`Vestas Ex 1019-p. 10
`Vestas v GE
`
`Wind Engineering 29-3_final 17/8/05 5:31 pm Page 210
`
`210
`
`THE DEVELOPMENT OF GRID CODE REQUIREMENTS FOR NEW AND
`RENEWABLE FORMS OF GENERATION IN GREAT BRITAIN
`
`In order to achieve this, it is essential for generating plant to be equipped with a governor
`which will control MW output following a sudden rise or fall in system frequency. Figure 6
`illustrates an actual instantaneous generation infeed loss secured by frequency responsive
`generation plant and some demand management.
`From an international perspective, the GB power system (and hence its overall inertia) is
`comparatively small, certainly in relation to the wider European UCTE system. On this basis,
`frequency control capability is an essential requirement from all forms of generation
`(including wind generation), especially because of the range in system demand that can be
`experienced and the expected volume of wind generation.
`It is acknowledged that active power from a wind farm will be constrained by wind speed,
`however this will not restrict the ability of a wind farm to provide frequency response. In
`Figure 7a, the delivery of low frequency response is illustrated. The top red dotted line
`indicates the power that could be exported by a wind farm extracting the maximum available
`power from the wind, whilst the lower blue line indicates the effect of part loading through the
`action of blade pitching. As the system frequency changes, the power output will increase (or
`decrease) in proportion to the frequency. In contrast, Figure 7b shows the delivery of high
`frequency response only. For this restricted service, the spilled renewable energy is small, as
`the wind farm is free to operate at full output at a nominal system frequency of 50 Hz.
`
`Figure 7a.
`
`Illustration of high frequency response from a Wind Farm.
`
`Discussions with wind turbine manufacturers and publicly available literature [10]
`demonstrated that frequency control could be implemented within a wind farm. On this basis,
`and in view of the construction phase of the Round 2 projects, the Grid Code requires that wind
`farms in operation after 1 January 2006 shall be capable of contributing to frequency control.
`
`Figure 7b.
`
`Illustration of high frequency response from a Wind Farm.
`
`

`

`Vestas Ex 1019-p. 11
`Vestas v GE
`
`Wind Engineering 29-3_final 17/8/05 5:31 pm Page 211
`
`WIND ENGINEERING VOLUME 29, NO. 3, 2005
`
`211
`
`There was concern from wind farm developers that they would be commercially
`penalised for de-loading before providing frequency response, as no benefit would be gained
`from a corresponding reduction in fuel cost and even more the loss of incentives (eg ROC’s).
`However, the current market arrangements allows the Generator to specify the price (the
`‘bid’) at which they are willing to be de-loaded. Once de-loaded, the Generator will also
`receive two additional payments for providing frequency response (holding and response
`energy payments). Therefore. the economics of de-loading for provision of frequency
`response could be reflected in the Generation Bid prices. After 1 October 2005, the holding
`price is also set by the plant owner. This situation is demonstrated in Figure 7a, where the
`lower blue line indicates the wind farm is operating to a defined contract position in the GB
`electricity market. Under some circumstances, e.g. minimum demand, provision of high
`frequency response without de-loading may be an attractive service.
`
`E. Reactive power and voltage control
`Reactive power and voltage control are required in order to protect plant from over-voltages,
`facilitate the transfer of active power, maintain adequate voltage quality and stability, and
`assist in securing the system under post fault conditions. The principle method of voltage
`regulation on the HV Transmission System is through the control of the excitation system on
`synchronous generating units. Whilst synchronous generating units have an inherent
`capability to provide reactive power, a wind farm comprised of pure induction generators and
`collection network could result in the uncontrolled absorption or generation of reactive
`power onto the transmission network. In order to control and provide voltage quality to
`customers, additional reactive support may be needed from adjacent synchronous generation
`or dedicated reactive compensation plant. In developing th

This document is available on Docket Alarm but you must sign up to view it.


Or .

Accessing this document will incur an additional charge of $.

After purchase, you can access this document again without charge.

Accept $ Charge
throbber

Still Working On It

This document is taking longer than usual to download. This can happen if we need to contact the court directly to obtain the document and their servers are running slowly.

Give it another minute or two to complete, and then try the refresh button.

throbber

A few More Minutes ... Still Working

It can take up to 5 minutes for us to download a document if the court servers are running slowly.

Thank you for your continued patience.

This document could not be displayed.

We could not find this document within its docket. Please go back to the docket page and check the link. If that does not work, go back to the docket and refresh it to pull the newest information.

Your account does not support viewing this document.

You need a Paid Account to view this document. Click here to change your account type.

Your account does not support viewing this document.

Set your membership status to view this document.

With a Docket Alarm membership, you'll get a whole lot more, including:

  • Up-to-date information for this case.
  • Email alerts whenever there is an update.
  • Full text search for other cases.
  • Get email alerts whenever a new case matches your search.

Become a Member

One Moment Please

The filing “” is large (MB) and is being downloaded.

Please refresh this page in a few minutes to see if the filing has been downloaded. The filing will also be emailed to you when the download completes.

Your document is on its way!

If you do not receive the document in five minutes, contact support at support@docketalarm.com.

Sealed Document

We are unable to display this document, it may be under a court ordered seal.

If you have proper credentials to access the file, you may proceed directly to the court's system using your government issued username and password.


Access Government Site

We are redirecting you
to a mobile optimized page.





Document Unreadable or Corrupt

Refresh this Document
Go to the Docket

We are unable to display this document.

Refresh this Document
Go to the Docket