throbber
Attachment 1a
`
`
`
`CHAPTER 6
`
`BASIC SCHEDULING
`
`This chapter continues the nuts and bolts of making the Planning system work With regard
`to scheduling. The chapter shows exactly how to do the scheduling-
`.
`..
`d I'
`In actual practice.
`it may be helpful to note that persons may con.51der “hf: “dag:
`somewhat vague term. To be more precise. advance or ii‘ceki’y scheduling means a so. 6 -
`uler allocating an amount of work orders for a week without settlng 5P3?1fic days‘or time:
`to begin or complete individual work orders. Likewise._ (lad-‘- 'ul‘lmdllling meant: gal—Cl;
`supervisor assigning specific work orders to SPCClfiC individuals to begin ll“? nest mill-€535
`maintenance group uses both weekly schedules and daily schedules. This Chagterl Escovers
`the activities to accomplish weekly and daily scheduling. In addition. Uiefc 3}? e on rou-
`how maintenance personnel stage material and tools. Although this bool:i ocus‘j‘sSflll out-
`tine maintenance. the book also explains key SChedUImg concepts baht: (13‘ch hwith the
`ages. Finally.
`the chapter compares and contrasts the concepts of sc e a ing
`COncepts of quotas. benchmarks. and standards.
`
`WEEKLY SCHEDULING
`
`.
`-
`'obs
`The scheduler performs most of the tasks of advance scheduling. The SClleqll1:r\f—:$L%::::ciule_
`from the waiting-to-he—scheduled file and any work rammed iron} the Prelim: next week. The
`The scheduler then allocates them into each crew‘s work hour females! t(‘erutealso makes other
`scheduler allocates jobs by work order priOFlfy- then “umber Of Work Ollndulina worksheets for
`considerations per lhe scheduling principles. The scheduler utilizes SC. tile [0 C'Emplete the next
`assistance. The end product is a package ofjobs that the crew should be J wisor The Scheduler
`week. The scheduler then delivers the jobs for each crew to the CIT-w sup; the guppofiin" craft.
`also sends a copy ofeach work order that will need intercraftcoort1;rlflftr10;1n the work 0rdeli a110-
`Each day the crew supervisor makes the daily SChefjme “105E y .0d'vidual crew members
`cated in the weekly schedule. The crew supr‘n‘ViSOr uSSignS work [0 m I
`-
`r attends a (1le
`based on the current day’s activities and progress 0“ work. The SUpingsorepresemame to
`scheduling meeting with other craft supervisors and the operations {:11 erzisor returns to the
`coordinate work for the next day. Near the end of the week. the crexxéhsmpweek The scheduler
`scheduler the jobs that he or she does not EXPCCL the crew to start
`I
`k
`then considers them for inclusion in the advance sc
`kly scheduling. This is the type of
`Here are the step-by-step actual activities for wee
`u
`tar CMMS would mimic.
`PhYs‘ical Process which must be understood and which a comp
`
`Forecasting Work Hours
`
`Each crew supervisor forecasts the crew’s available work hours as the first step in the
`advance scheduling process.
`
`6.1
`
`CiM Ex. 1060 Page 1
`
`Attachment 1a
`
`CiM Ex. 1060 Page 1
`
`

`

`Attachment 1a
`
`6.2
`
`CHAPTER Six
`
`This activity takes place near the end of the work week. usually at the beginning of the
`last shift for the period already in progress. For example. this would be Friday morning for
`a crew that works Monday through Friday, 8-hour day shifts or Thursday morning for a
`crew that works Monday through Thursday, lO-hour day shifts.
`Near the end of the work week, the scheduler takes a Crew Work Hours Availability
`Forecast worksheet (shown in Fig. 6.1) to each crew supervisor. Taking the availability fore-
`cast worksheet to the supervisors impresses upon the supervisors that next week they will be
`responsible for completing the amount ofwork for which they have labor. They are involved
`in the process. The scheduler is only helping them determine how many and which jobs
`should be selected from the backlog.
`The Crew Work Hours Availability Forecast worksheet has blanks to guide the crew
`supervisor in determining how many hours each craft level has available. This section and
`the following sections illustrate the crew supervisor’s use of this form.
`The crew supervisor fills out and returns the availability forecast worksheet as soon as
`possible after receiving it from the scheduler. The supervisor receives the forecast work-
`sheet from the scheduler at 8 AM. The crew supervisor should already have an idea of who
`Will be in training and who has requested vacation for the next week. On the other hand. the
`supervisor may need to check on jobs currently in progress to determine which ones the
`crew will probably not finish this week. Thosejobs will need carryover hours reserved for
`them next week. In addition, the supervisor needs to assess which new jobs the crew will
`start today. Some of thesejobs might be finished or might also run over into next week. One
`thing the supervisor does not plan for is unexpected absences. Scheduling is not based on
`the unexpected. The supervisor may later use unexpected absences that occurred to explain
`why the crew did not meet a schedule. When the crew supervisor finishes these determina-
`tions, he or she gives the scheduler the completed Crew Work Hours Availability Forecast
`worksheet. The crew supervisor also hands over any physical work orders which the crew
`received to do this past week, but will not start. The crew supervisor makes all these deter—
`minations by 10 AM and returns the worksheet. This gives the scheduler time to create the
`weekly schedule by 1 PM after lunch. (The scheduler must finish the weekly schedule by
`early afternoon so that the crew supervisor can make a daily schedule for the first day of
`the coming week. The crew supervisor must attend a late afternoon daily scheduling meet-
`ing to give the operations group information on clearances for the beginning of the follow-
`111g week and initiate coordination with other crafts, if necessary. The supervisor may also
`begin to make individual technician assignments.)
`The maintenance group can easily computer-lee the availability forecast worksheet. Many
`CM'MS' packages contain work calendars for the crew supervisor to update crew member
`anlab‘hty for the coming work days. Then the scheduler can access the data whenever
`needed. Of course, the crew supervisor must keep the data current. Even without a CMMS
`system or CMMS labor calendar module, the company can use a computer network. The
`scheduler can make a form on email or attach a spreadsheet program or word proceSsing
`document with a representation cf Fig. 6.1. By exchanging this form back and forth by
`email, the crew supervisor and scheduler produce the necessary forecast information.
`Without getting current information from the crew supervisor, the scheduler might use
`a standard forecast 0f hOW many work hours were normally available. In other words. the
`scheduler would presume for a given crew that a certain number of labor hours were avail-
`able every week. This standard forecast might presume that for a 10-person crew, one per-
`son would be unavailable for one reason or another. So the scheduler would schedule for
`nine persons each week. The scheduler and the crew supervisor would meet together occa-
`sionally to assess any needs to adjust the standard. The problem with using a standard fore-
`cast is that crew supervisors may not take the resulting schedule seriously. Whether or not
`they finish all their scheduled work. they will get the same amount of new work the next
`period. There is not much attention to carryover work which could be a significant prob-
`lem. This approach figures that carryover work from the previous work remains about the
`
`CiM Ex. 1060 Page 2
`
`Attachment 1a
`
`CiM Ex. 1060 Page 2
`
`

`

`Attachment 1a
`
`BASIC SCHEDULING
`
`6.3
`
`CREW WORK HOURS AVAILABILITY FORECAST
`
`For week of:
`
`...._._.._..—
`
`For crew:
`
`to
`
`/
`
`/
`
`By:
`
`Date:
`
`finished and will run over into the forecast period-
`
`Craft
`
`#Persons
`
`Carry— Avail
`.
`Paid
`Hrs Leave Train Misc over"
`Hrs
`
`*Carryover work is any work which has been
`physically started in the current period, bl“ “Vi.“ "0t be-
`
`FIGURE 6.l Worksheet to assist crew supervisors forecast how many labor hours are available
`for scheduling work the following week-
`
`same each week. Carryover work would be work that the crew started the previous week
`bUI did not complete. One of the main reasons to base weekly scheduling on a prec1se
`weekly forecast is to facilitate communication about performance. Scheduling to a standard
`forecast hinders achieving this purpose. Nonetheless, this approach may be necessary in sit—
`uations of extreme crew reluctance and minimal management support.
`_
`.
`_
`Figures 6.2 and 6.3 illustrate the use of the Crew Work Hours Availability Forecast
`worksheet for a mechanical maintenance crew working a 10-hour shift. B. Jones. supervi-
`sor of A Crew, has just received the availability forecast worksheet from the scheduler. The
`crew consists of fivo persons: one skilled welder, one apprentice. one painter. and two
`
`CiM Ex. 1060 Page 3
`
`Attachment 1a
`
`CiM Ex. 1060 Page 3
`
`

`

`Attachment 1a
`
`5.4
`
`CHAPTER SIX
`
`mechanics. Jones feels that one of the mechanics possesses a very high degree of mechan-
`ical skill. but the other mechanic is significantly less capable at the present time. Jones
`knows that none of the crew will be in training any of next week, but the painter will be off
`2 days for vacation. Jones considers the current jobs in progress. The welder’s currentjob
`will not be finished today and requires about 5 hours next week to finish. The higher skilled
`mechanic has been working a job for the past 2 days and claims it will take 5 hours next
`week as well. The other mechanic will finish one job and start anothcrjob today that will
`also take about 5 hours next week to finish. The other crew members should finish their cur-
`rent work today as well. Jones plans to have them start and finish a new assignment. With
`this information, Jones estimates the total carryover Work to be 5 hours of skilled welding,
`5 hours of highly skilled mechanic work, and 5 hours of lesser skilled mechanic work.
`Figure 6.2 shows that the supervisor begins completing the availability forecast work-
`sheet by starting with a craft skill level listing for this specific crew. First. note that the
`worksheet considers apprentices simply as helpers. This plant does not regard apprentices
`as strictly in training for their craft and may utilize them where the high priorities of the
`plant lie. It is expedient to follow this philosophy in the forecasting phase of the schedul-
`ing, but to use the daily scheduling assignments to try to keep apprentices within their craft
`Specialties. Second, note that the scheduler and the supervisor use the term mechanic to des-
`ignate a fairly well-skilled mechanic technician. They use the term technician to designate
`a less skilled technician in the primary craft of the crew, in this case mechanical. This use
`of the terms allows planners, schedulers, and supervisors to communicate regarding skill
`level even within a standard classification. Although the plant does not have a certification
`program, Significant differences between the skill levels of the mechanics exist. The plant
`needs to ensure not to allocate too manyjobs requiring highly skilled mechanics at the same
`time. Normally a company could distingUish overall skill level through some certification
`process or a progression of rank such as third, second, and first class mechanics to identify
`the better mechanics. However, the subject plant has only mechanic, apprentice, and trainee
`formal designations. Therefore. the planners and schedulers informally address the needs
`forjobs by using the terms technician and mechanic on thejob plans. When a planner uses
`the term technician, the job plan does not require a more capable mechanic.
`Figure 6.3 shows the availability forecast worksheet after the supervisor enters all the
`quantities for persons and hours. Jones only forecasts for the 2 days of vacation approved
`for the painter. Supervisors do not presume there will be unexpected absences due to per-
`sonal illnesses or sudden vacation day requests. The advance schedule sets a goal based
`on current knowledge and encourages everyone to meet the schedule. Typically. man-
`agement above the supervisor directs training and special meetings. Management decides
`and sends various persons to different training claSSes or schools as well as coordinates
`special meetings such as safety or outage planning. Management does the crafts a great
`favor by SChEdUhng these types of special events at least a week ahead of time. Once
`maintenance has set a weekly advance schedule, management assists maintenance in
`building the plant’s confidence in the schedule by not encouraging deviation. Jones‘s
`management has not scheduled training or meetings for anyone. Jones‘ 5 estimate of car—
`ryover hours 18 important because the scheduler must allow the crew time to finish jobs
`already in progress. The scheduler must not allocate new work for these labor hours. The
`supervisor’s estimate of the amount of time required to finish carryover work is adequate.
`Finally, the supervisor completes the total’s line for each type of work hour. The total’s
`line helps in several ways. First, it helps to check the entries for accuracy of addition and
`subtraction. It also draws attention to how many hours exist in the various categories. The
`total magnitude of paid hours available to the crew and the effect of lost hours due to
`training or carryover work often are unappreciated. In this case, 200 labor hours repre-
`sent a significant company expense. Out of this 200 paid hours, the supervisor forecasts
`165 available for work next week in the shown crafts and skill levels. Finally, the totals
`lend themselves to tracking areas for improvement.
`
`CiM Ex. 1060 Page 4
`
`Attachment 1a
`
`CiM Ex. 1060 Page 4
`
`

`

`Attachment 1a
`
`BASIC SCHEDULING
`
`5.5
`
`CREW WORK HOURS AVAILABILITY FORECAST
`
`For week of:
`
`to
`
`/
`
`I
`
`For crew:
`
`By:
`
`Date:
`
`Craft
`
`#Persons
`
`Carry- Avail
`Paid
`Hrs Leave Train Misc over" Hrs
`
`Mech
`
`:40:
`
`.—
`
`——.—_._—-
`'
`'
`
`'
`
`Heidi——
`
`finished and will run over into the forecast pBI‘IOd-
`
`*Carryover work is any work which has been ‘
`physically started in the current period, bllt WI.“ “M be
`
`FIGURE 6.2
`
`Input of normal craft and skill level designations.
`
`Figure 6.4 illustrates the use of the Crew Work Hours Availability Forecast worksheet
`for another mechanical maintenance crew. J. Field, supervisor of B Crew._has Just
`received the availability forecast worksheet from the scheduler. The crew consrsts of 15
`persons. The crew has tWo welders, two machinists, and six mechanics. Field consrders
`three of the mechanics to be significantly more capable than the others. Two trainees and
`three apprentices make up the remaining five employees. Field w11| forecast the crew
`available work hours from the following information. One of the welders requested 2
`days of vacation next week. All B Crew apprentices must attend an entire day of class-
`room training. B Crew will have a 1-hour safety meeting on Wednesday. After checking
`on jobs in progress, Field makes an estimate for carryover work. Carryover work will
`
`CiM Ex. 1060 Page 5
`
`Attachment 1a
`
`CiM Ex. 1060 Page 5
`
`

`

`Attachment 1a
`
`6.6
`
`Cl—lAP’TER SIX
`
`CREW WORK HOURS AVAILABILITY FORECAST
`
`
` For week of: 5/10/99 to 5/13/99
`
`For crew: A Crew
`By: B. Jones Date: 5/ 6/ 99
`
`
`
`
`Paid
`Carry- Avail
` Craft
`# Persons
`Hrs Leave Train Misc over"
`Hrs
`
`
`
`
`
`Mech
`35
`
`‘
`35
`
`
`
`—_._——-—-————
`
`
`
`*Carryover work is any work which has been
`physrcally started in the current period, but will not be
`finished and will run over into the forecast period.
`
`
`
`FIGURE 6.3 Completed forecast for the A Crew.
`
`con51lstof2 days of welding needing a welder and a helper. l day of machine work, 1 day
`of skilled mechanlc work, and another day of less demanding mechanic work.
`As before. the supervisor classifies the mechanics according to skill describing them as
`three mechanics and three technicians. The supervisor forecasts five helpers including the
`three apprentices and both trainees. The classroom training makes only 30 hours unavailable
`since out of the five helpers, only the apprentices must attend. The safety meeting on
`Wednesday makes 1 hour for each person unavailable for scheduling in the Miscellaneous
`column. The specific day of the week is irrelevant to both the forecast and the weekly allo-
`cation. Only the available hours for the entire week matter. The daily scheduling routine later
`will take this into account. Finally, out of the 600 paid hours. 455 are available for new work.
`
`CiM Ex. 1060 Page 6
`
`Attachment 1a
`
`CiM Ex. 1060 Page 6
`
`

`

`Attachment 1a
`
`BASIC SCHEDULING
`
`6.7
`
`Sorting Work Orders
`
`In preparation of allocating work orders into the crew availability forecast. the scheduler
`Sorts the plant‘s backlog. If the crew is responsible for only a certain area of the plant. the
`scheduler will only sort those work orders. Later after all the scheduler allocates work for
`every crew. the scheduler might be able to recommend that certain crews assist other crews.
`The scheduler sorts the hacklogged work orders in order to preferentially select work orders
`to allocate If there are more job hours in the backlog than the forecast. obviously the sched-
`uler cannot expect the crew to complete all the work. Ifthe backlog has 1000 hours ofjobs.
`then a crew expecting to have 455 labor hours cannot do all the work in a single week. The
`
`CREW WORK HOURS AVAILABILITY FORECAST
`
`For week of: 5/11/99 to 5/14/99
`For crew: B Crew
`By: J. Field Date: 5/ 7/ 99
`
`Craft
`
`. Carry- Ava“
`Paid
`#Persons Hrs Leave Train Misc over” Hrs
`
`Mech
`LIL/elder
`
`..
`
`3 x40:
`2 K40:
`
`=
`
`finished and will run over into the forecast period.
`
`=_1L}1_
`=
`38
`
`68
`
`2'“
`
`*CE'TYOver work is any work which has been .
`physically started in the current period, but Will not be
`
`FIGURE 6.4 Completed forecast for the B Crew.
`
`CiM Ex. 1060 Page 7
`
`Attachment 1a
`
`CiM Ex. 1060 Page 7
`
`

`

`Attachment 1a
`
`6.8
`
`CHAPTER SIX
`
`scheduler must select 455 hours worth of work to allocate for the Week. The scheduler sorts
`the backlog of work orders into an overall order that will help determine which panicular
`work orders are appropriate. Note that this presumes Scheduling Principle 4. proceeding
`with a preference to schedule 100% of the forecasted crew work hours. not more ( 120%)
`or less (80%). The procedure for allocating the work hours into the backlog proceeds with
`assigning the higher priorities before the lower priority work. The procedure also makes
`allowance forjobs on the same system and proactive work. In addition. the process shows
`how to select among jobs of equal priority and Work type.
`The scheduler returns to the planning office after delivering the Crew Work Hours
`Availability Forecast worksheet for the crew supervisor to complete. The scheduler collects
`all the planned work orders for a particular crew from the waiting-to-be-scheduled file and
`organizes them on a conference room table. The scheduler sorts them into separate piles.
`one pile for each priority. The waiting—to-be-scheduled file might already have separate
`{elders for each priority to facilitate this step. Appendix J describes the priority codes for
`the work order system. Then. the scheduler sorts each pile into a particular order.
`The scheduler first sorts the highest priority pile. priority 1 (urgent). Note there are
`no priority-0 (emergency) jobs in the backlog. Emergencyjobs would already be under
`way and so are neither planned nor scheduled. By definition. all priority—l work is Clas-
`sified as reactive work. Why is this reactive work sorted ahead of any proactive work?
`The ideal situation would be to have only proactive work in a plant. The plant prefers
`doing lower priority. proactive work to head off emergencies and urgent work.
`However, priority-l work is urgent. It must be addressed. usually to restore lost capac-
`ity or remedy an immediate threat to production. The purpOse of proactive work is to
`head off any reactive work, but when proactive action has failed to prevent a reactive
`situation, the situation must be addressed. Maintenance must first schedule urgent work
`to restore the plant. However. lower priority. reactive work should wait until after equal
`priority proactive work. In giving general preference to proactive work in this manner.
`the incidence of reactive situations diminishes. Therefore. the scheduler considers pri-
`ority-l work. which is all reactive and urgent, first.
`The scheduler sorts the priority-l jobs into order with jobs requiring the highest total of
`work hours on top. When the scheduler later allocates the work orders. jobs with more total
`work hours are put in the schedule first. This will allow fitting smaller jobs of equal priority
`into gaps of time remaining during the allocation process. This gap fitting would be more
`difficult if the scheduler allocated smallerjobs first. The scheduler would have to allocate
`only portions of largerjobs unnecessarily. The scheduler makes an exception to this sorting
`for smaller jobs encountered if they belong to the same system as larger jobs already higher
`in the group. In that case, the scheduler physically removes the smaller work order from its
`natural order and staples it to the work order for the larger job in the same system.
`reasons.
`Scheduling work together for the same system is important
`for several
`Productivity increases if technicians can move from one job to a nearby job on the same
`system. They do not need to lose time familiarizing themselves with a different system at
`the start of each job. They avoid having to demobilize, travel. and move personal tool boxes
`to a different site to set up again. Sometimes they can use the same scaffolding or insula-
`tion clearing to get to the work. There is also a psychological boost to remaining on the
`same system. Frequently the time between jobs is taken advantage of as being a logical time
`to take breaks or “rest a moment" even when the jobs only last an hour or less. When jobs
`are scheduled on the same system. there is a tendency to look at the entire system as a sin-
`gle job through which to proceed with minimal delay. On the operations or production side,
`combining same system jobs also helps improve plant operations. An operator prefers to
`clear up a single system a single time for several jobs. A less organized scheduling effort
`might have the operator clear up the demineralizer on Monday and Wednesday for two jobs
`that could have both been done on Monday. Then on Friday. when the maintenance group
`
`CiM Ex. 1060 Page 8
`
`Attachment 1a
`
`CiM Ex. 1060 Page 8
`
`

`

`Attachment 1a
`
`BASIC SCHEDULING
`
`6.9
`
`requests the operator to clear up the deinineralizer a third time. the operator must refuse.
`The operator must explain that the plant is in jeopardy of not having enough water in its
`storage tanks. This scenario frequently occurs when no advance scheduling exists. The
`supervisor then assigns work by picking. through the entire plant backlog for each nextjob.
`The scenario also can occur if the scheduler does not place thejobs together in an advance
`allocation. Unnecessarily clearing tip a system multiple times wastes time and frustrates the
`operators.
`Then the scheduler similarly sorts the priority—2 (serious) work orders by work order
`size. biggestjobs on top. with three exceptions. The first exception is that the scheduler puts
`all PM. preventive maintenance. jobs at the top of the pile. PM jobs are always prioritized
`33 I’l'ic’l’itY-i2 jobs. They are considered serious and not simply routine maintenance With a
`lower priority. The scheduler sorts PM jobs by job size within themselves. larger-ones first.
`The second exception is similar as for priority-i work orders. If a work order is encoun—
`tered that belongs in a system for which a larger or higher priority work order has already
`been sorted, the work order is moved up and attached to the previously sorted work order.
`This is done even if it means moving a work order from the priority-2 pile to the pnonty—l
`pile to attach it to the other work order. The third exception is that for work orders of
`approximately the same size with the same priority. the scheduler places a proactive work
`order ahead of a reactive one.
`Then the scheduler sorts the pile for priority-3 work orders with larger work orders on
`[UP and PTt)3€1ive work getting preference for work orders ofapproxnmately the same Size:i
`The scheduler physically moves any work order for a system already encountered an
`attaches it to the other work order. even if it is in a higher priority pile.
`Finally. there is 25
`‘
`Similarly, the scheduler sorts each pile of same—priority work orders.
`finished group for each priority arranged from top to bottom by size. There are esceptlonfi
`_
`for same-system work orders stapled together, exceptions for similar-Sized proactiv: 331:4 K
`ahead of reactive work. and PM work orders at the top of the priority-2 stack (unles
`‘ Th
`was moved to the priority-i stack to be with a same system work order)-
`Note that the advance scheduling process does not consider aging of work orders.
`1t:
`concept 0f aging is that an older work order should get higher attention than a Similar “50hr
`order only recently written. That is. a low priority work order written 9 months ago mtgl
`justify more attention than a serious work order written only yesterday. Aging might 2ch
`a Work force that does not have weekly scheduling. If a crew‘is only compltfllng the to
`priority work With low productivity. increasing the relative prionty of an Older-#3:” PU?“
`ity job might encourage the crew to include it as well. Aging 15 not as helpful i
`ekrnainl;
`tenance group allocates and expects a crew to complete a proper amount of wor eac
`week. A properly sized maintenance crew is capable of handling all the work that comes
`“Pa ”OtJUSt the high priority tasks. That means that the crewcan complete all the woak so
`aging is not necessary to bring olderjobs to the top. Scheduling keeps the crew from ow—
`ering its productivity to handle only the high priority work. Scheduling Pnncrple 2 states
`the importance of correct priorities. Working lower priority JObS ahead of Clearly more
`important jobs leads a crew to doubt its leadership. Doing the mostimportant work first
`gives the plant more benefit by definition. So aging is really a tool to increase a crew 5 low
`productivity. Aging would interfere with an already highly productive crew. Aging figures
`that a crew is less productive than it should be. Aging figures that a crew is only deing'the
`high priority work by choice. So aging simply raises the priority of some of the work into
`the higher priority work to which the crew will give attention. On the other hand, a crew
`already getting as much work done as it should can only give attention to another Job by
`not doing a job already intended. So aging for the highly productive crew has Just made the
`crew complete a lower priority job instead of a higher priority Job to the plant’s detriment.
`Claiming that less important work should not be done ahead of more important work
`does not say work should never be reprioritized. If an older, low priority work order for
`
`CiM Ex. 1060 Page 9
`
`Attachment 1a
`
`CiM Ex. 1060 Page 9
`
`

`

`Attachment 1a
`
`6.10
`
`CHAPTER SIX
`
`some reason merits more importance recently, then the priority should be increased. With
`the same reasoning, perhaps a higher priority work order is now less important than previ-
`ously thought. The planning system should allow for changing the priority of each of these
`type work orders. One of the helpful additions to a planning group in this respect is an oper-
`ations coordinator. This person or any knowledgeable operator can benefit a planning
`group by a monthly review of an extensive backlog. The operations coordinator can deter-
`mine if some work orders should be reprion'tized. This person has the authority to change
`the priority of any work order on the spot.
`The scheduler receives two things from the crew supervisor a few hours after the last
`shift starts. The scheduler receives the completed Crew Work Hours Availability Forecast
`worksheet and any work orders which had been scheduled, but are now not going to be
`started this week. The supervisor has had time to assess the crew projected attendance for
`the next week as well as the status of current jobs-in-progress. In the case of an entirely
`paper-driven system, the crew supervisor physically hands over the work orders that the
`crew will not start. (In the case of an entirely computer driven system. the maintenance
`group might only print out the physical work orders when assigning them to the field tech-
`nicians, if at all. The supervisor updates the computer changing each job to "in—progress“
`at the beginning of the shift or the end of the previous shift for the coming day. Therefore,
`the scheduler may consult the CMMS each week to determine which allocatcdjobs will not
`be started.) The scheduler takes the jobs not to be started and places them into the priority
`piles of work orders if they have already been arranged. The scheduler places these new
`work orders into the piles where they would belong if they had already been in the back-
`log. The actual allocation sequence can now take place.
`Tables 6.1 through 6.3 illustrate sorting a plant backlog. The backlog belongs to
`mechanical maintenance A Crew. An earlier illustration used this crew as an example for
`forecasting. Table 6.1 shows the backlog arranged by work order number. The backlog
`consists of 243 total estimated work hours as planned. Because A Crew has only 165 work
`hours forecasted available, the scheduler must select the proper 165 hours to allocate for
`the next week. A plant also generally prefers to have 2 to 3 weeks of backlog available. This
`plant has less than 2 weeks of backlog. If this shortage is the normal case. the plant might
`not be identifying enough corrective maintenance situations to head off later breakdowns.
`The plant might also not be creating enough PM tasks. On the other hand, the maintenance
`crew might be overstaffed for the work area. 0f the work orders in the backlog. work order
`codes as defined in App. J define certain information necessary for scheduling. First. the
`unit code N01 shows that most of the work orders are for North Unit 1. which is A Crew's
`primary responsibility. Second, within Unit 1. the system codes show that a variety of dif-
`ferent systems need work. Third, work type codes indicate the nature of the work. Code 5
`is breakdown and failure. Code 7 is preventive maintenance. Code 8 is work recommended
`by predictive maintenance. Code 9 is corrective maintenance that can head off failure and
`breakdown. Fourth, outage code 0 illustrates that the scheduler considers only work not
`requiring an outage of the entire unit for the normal work week.
`Table 6.2 shows the backlog after the scheduler has physically grouped the work orders
`into different priorities. In addition, the largest work orders have been placed ahead of
`smallerjobs within each priority group. Note the scheduler places W0 (work order) no. 012
`requiring 16 total labor hours ahead of WO no. 004 requiring only 14 hours. Similarly. W0
`no. 004 is ahead of W0 no. 002, which requires only 10 labor hours. Each priority group is
`similarly arranged with the only exception being for the priority-2 work orders. The sched—
`uler must place PM work orders first within the priority-2 work orders. Work type code '7
`defines the work as preventive maintenance. Therefore. the scheduler places W0 no. 005
`at the head of the priority—2 group even though it has the fewest hours.
`Table 6.3 shows the backlog after the scheduler has adjusted the groups considering
`same-system work and other proactiVe work. First. the scheduler takes W0 no. 006 from the
`
`CiM Ex. 1060 Page 10
`
`Attachment 1a
`
`CiM Ex. 1060 Page 10
`
`

`

`Attachment 1a
`
`BASIC SCHEDULING
`
`6.11
`
`
`
`TABLE 6.! Plant Backlog for the A Crew Listed by Work Order NumberW
`No. of
`
`Est.
`Est.
`persons
`W0 NO. duration Unit System Priority Work type Outage and craft hours
`
`
`
`
`
`
`
`
`
`
`
`
`
`001
`002
`003
`004
`
`005
`
`006
`
`007
`
`008
`009
`
`010
`
`0‘1
`
`012
`
`NH”
`N0]
`NH]
`N0]
`
`NM
`
`N0!
`
`Ntll
`
`N0]
`N0]
`
`NO]
`
`NOI
`
`N01
`
`XE
`CP
`CV
`FC
`
`CP
`
`FC
`
`JC‘
`
`JX
`CP
`
`IF
`
`CD
`
`BV
`
`4
`1
`t
`1
`
`2
`
`3
`
`2
`
`3
`4
`
`3
`
`2
`
`1
`
`5
`5
`9
`5
`
`7
`
`5
`
`5
`
`9
`S
`
`9
`
`3
`
`5
`
`O
`0
`0
`0
`
`U
`
`0
`
`0
`
`0
`0
`
`0
`
`0
`
`0
`
`l welder
`1 tech
`l painter
`] tech.
`l helper
`1 tech.
`2 helpers
`I tech.
`I helper
`l mech.
`l helper
`] painter
`I niech.
`1 helper
`1 tech.
`l helper
`l tnech.
`l helper
`l welder.
`l helper
`
`35
`10
`40
`7. 7
`
`6. l2
`
`IS. IS
`
`20. 20
`
`4
`2. 2
`
`3. 3
`
`10. 10
`
`S. 8
`
`35
`10
`40
`7
`
`6
`
`IS
`
`20
`
`4
`2
`
`3
`
`10
`
`3
`
`priority-3 stack and attaches it behind WO no. 004 in the priority-l group. These work orders
`are both in the same system. FC. Second. the scheduler takes W0 no. 005 from the priority-
`2 stack a

This document is available on Docket Alarm but you must sign up to view it.


Or .

Accessing this document will incur an additional charge of $.

After purchase, you can access this document again without charge.

Accept $ Charge
throbber

Still Working On It

This document is taking longer than usual to download. This can happen if we need to contact the court directly to obtain the document and their servers are running slowly.

Give it another minute or two to complete, and then try the refresh button.

throbber

A few More Minutes ... Still Working

It can take up to 5 minutes for us to download a document if the court servers are running slowly.

Thank you for your continued patience.

This document could not be displayed.

We could not find this document within its docket. Please go back to the docket page and check the link. If that does not work, go back to the docket and refresh it to pull the newest information.

Your account does not support viewing this document.

You need a Paid Account to view this document. Click here to change your account type.

Your account does not support viewing this document.

Set your membership status to view this document.

With a Docket Alarm membership, you'll get a whole lot more, including:

  • Up-to-date information for this case.
  • Email alerts whenever there is an update.
  • Full text search for other cases.
  • Get email alerts whenever a new case matches your search.

Become a Member

One Moment Please

The filing “” is large (MB) and is being downloaded.

Please refresh this page in a few minutes to see if the filing has been downloaded. The filing will also be emailed to you when the download completes.

Your document is on its way!

If you do not receive the document in five minutes, contact support at support@docketalarm.com.

Sealed Document

We are unable to display this document, it may be under a court ordered seal.

If you have proper credentials to access the file, you may proceed directly to the court's system using your government issued username and password.


Access Government Site

We are redirecting you
to a mobile optimized page.





Document Unreadable or Corrupt

Refresh this Document
Go to the Docket

We are unable to display this document.

Refresh this Document
Go to the Docket