throbber
BAKER HUGHES INCORPORATED
`BAKER HUGHES INCORPORATED
`AND
`Exhibit 1020
`BAKER HUGHES OILFIELD
`OPERATIONS, INC.
`Exhibit 1020
`Page 1 of 11
`
`

`
`2
`
`MS. VAN DOMELEN
`
`SPE 49523
`
`Case Study 1: Germany's Soehlingen Wells
`
`The Reservoir. The Rotliegendcs formation includes several
`sands that are productive in Gennany. The Netherlands and
`the Sotttllcnl North Sea. Rotliegendes sands are Inassivc (up to
`[000 It _u_ross]I with moderate poi'osity [I0-I2”-o} and t_vpica|l_v
`lo\\ pct"meal‘:ilIty ll'2Il'L.'l_\_' above It} Ind and often as low as 0.lll
`llltl]. The pre.~;e|Ice (1l‘(ll£Igt2llt2llt.' illilo in the pore space is the
`c;nis;e for low penncahi|it_v. Reservoir tlcptli lends to increase
`Iiniu ca. 9.000 feet in the southern North Sea to |6.0[}0 Feet as
`
`the trend Inovcs cast into German_x,'. Permeability also tends lo
`decrease in the eastward direction. (.‘ouunei‘cial production of
`natural gas from these low permeability. deep members of the
`Rotliegcndcs formations requires completion with propped
`hydraulic
`fractures.
`Exatnples
`of
`sttccesslitl
`fracture
`stimulations in the North Sea Rotliegendes can be found in
`references 2 to 5. Fracture stimulation of the Rotliegendcs
`formation in Germany is complicated by the higher reservoir
`temperature (290°F) and increased stress levels due to depth
`{l5_'i'00 ft TV D) and reservoir pressure (8,700 psi).
`
`The History. Germany's first massive hydraulic fiacturing
`[Ml-ll‘)
`treatments were
`conducted in
`[977
`in BEl3'S
`Goldenstedt Z7 wcll.° A total of 420,000 lbs of Ottawa sand
`was placed in two separate hydraulic fracturing treatments
`utilizing a total of 225,000 gal of polymer emulsion frac fluid.
`During pumping the average proppant concentration was less
`than 2 ppg. Post treatment production rates from the 0.1-0.5
`md formations were approximately 7 MM scfll).
`_A record—serting MHF treatment was conducted on the
`Hauptsandstcin of the Rotliegcndes formation in Mobil Oil
`AG‘s Soehlingen Z4 well in December of [9827 A total of l.2
`MM lbs. of high strength sintered bauxite was placed with
`690,000 gallons of titanate crosslinked fluid. As with the
`Goldenstedt Z7 well, the average proppant concentration was
`less than 2 ppg. At
`the time the Soehlingcn Z4 fracturing
`treatment was the largest ever conducted in Europe and the
`world’s largest in terms of bauxite placed. Fracture stimulation
`allowed the production rate from the 0,008 ‘.|TlCl fonnation to be
`increased fi'om 1.2 MM scflD at 260 psi to 6.7 MM scf‘/D at
`2,870 psi.
`It is interesting to note that the effective permeability of
`the Soehlingen Z4 well was 10 to 50-fold less than that ofthe
`Goldenstedt Z7 well yet
`similar production rates were
`achieved. The fracturing treatment on the tighter Soehlingen
`Z4 well used roughly three times as much proppant. The
`resulting production increases were the result of the larger job
`size as well as the use of stronger proppant {sintered bauxite
`instead of sand). It was the advances in fracturing technology
`which allowed the tighter Soehlingen Z4 well to be produced
`at a rate comparable to the Goldenstedt Z7 well and the
`treatment added an estimated 20 bcf of reserves to the field.
`Three vertical wells were drilled and fractured in the
`
`Soehlingen Field in the 1980's. Large fluid volumes were used
`on the three wells averaging 500,000 gallons of crosslinked
`fluid with 35% by volume pad with average proppant
`
`concentrations below 3 ppg. The results of the treatments were
`not fully satisfactory. The average sustained production rates
`of-1.5 MM sct?'D proved uneconomical,
`
`and
`chilling
`in
`developments
`The Challenge. Recent
`completion Icclmolog_}- allowed for a totally new approach to
`the tlcvclopment ol' the Soclilingen Zlll well. The project's
`ohicctlve was to attain pI'odnclinn rules
`tioln a multiple
`fractured luirizonlal well that are three to the times the rates
`
`attainable limit a vertical. C(}lI\'t?]lT.l(ll]?lll}' liactliicd well.“ This
`translates to a sustained rate of about [3 MM sefi'D.
`
`Siinilar to the previous Sochlingcn wells. the target for this
`well was to treat
`the Hauptsandslein of the Rotliegendes
`formation. The Z10 well was drilled to a total vertical depth of
`l5,688 ft, where it was deviated horizontally for 2,066 ft into
`the reservoir parallel to the least principal stress. The drilling
`ofthe well is discussed in detail in by Pust and Schamp.9 The
`well was completed with Sliding Side Doors (SSD) in 7 inch
`casing to allow for
`selective stimulation with multiple
`hydraulic Fractures. The completion ofthe well is discussed in
`detail by Chambers, ei.aI.'” In the fall of I994, 2.3 MM lbs of
`intcnnediate strength proppant were placed in the Z10 well in
`four separate fracturing treatments, applying approximately
`500,000 gallons of a delayed borate crosslinked fluid. This
`corresponds to an average pumping proppant concentration of
`5 Pris."
`Two world records were set by this treatment: one for the
`deepest horizontal well drilled and the other for the deepest
`multiple fractilres.”'” Initial post-fracture production was 23
`Min scDD at a flowing tubing head pressure of 4,350 psi.
`After 2 years, a sustained production rate of IS MM scf"D at
`4,350 psi was achieved from all four fractures?’ This rate
`exceeded the original target rate and demonstrated that it is
`technically possible to drill, complete and have multiple
`stilnulations in long horizontal sections in a very deep, light
`reservoir under extreme high pressurefhigh temperature
`operating conditions.
`
`Past and Present. Below, fracturing techniques used in the
`past and new technological advances that were crucial to the
`success of Soehlingen Z-10 will be compared and discussed.
`Results of fracture simulations for the Z4 and Z10 wells are
`
`presented in Table 1. Key design and treatment data are given
`in Table 2. Treatment results are sutrunarizcd in Table 3.
`
`Examination of these three tables provides a good illustration
`of the technological advances made since 1982.
`Fracture 0pa'nu'zrm'tm. The first step in the optimization
`process for fractured horizontal wells is to determine the
`required length of the horizontal section,
`the number of
`fractures required and the length of the individual fractures.
`For the Z10 well,
`it had been decided to use transverse
`fractures. See Figure
`I
`for an illustration of transverse
`fractures in a horizontal wellbore. Production predictions for
`the Zl0 well were provided by Hunt for various combinations
`of multiple transverse fractures, fracture half-lengths and total
`drainage areas.” The prediction technique that was used is
`
`Page 2 of 11
`Page 2 of 11
`
`

`
`SPE 49523
`
`ENHANCED PROFlTABlLlTY WITH NOMCONVENTIONAL IOR TECHNOLOGY
`
`3 g
`
`discussed by Soliman, el.al."' Norris, et.al. provides a good
`overview of cturent
`technology for prediction of fractured
`horizontal performance.” Once the well was drilled and the
`reservoir’
`permeability more
`accurately
`known.
`linal
`uptiniimtioii inilicatcd an optinnnn hoi'i'/.ontal length of 2.000
`feel with foul‘ perpendicular li'acItu'es equally spacctl along the
`|rori'/.unl:i| section. The most elTecti\'e li'at:1urc length was
`helietetl to be Frill} fct:l. asstiririlig inlinilt: curitltitztirily. Talile
`l contains the results of |i'actuI'c (rc~]:aiinulalion.~:
`[1L2I'lill‘llIcLl
`\-rill‘: data
`[ruin the Z4
`and ZIU well
`Iiles.
`tlsing 2|
`connnercially available fracture simulator ll-"r'aci’ro).
`It is very
`interesting to note that
`the designed fracture length {total
`length, not halflength) for the Z4 well is about the same as the
`optimized length ofthe horizontal wellbore in the Zl0. It is of
`further
`interest
`to note that
`the calculated total
`pr'up_nct.-’
`fracture areas for the two wells are nearly identical. Yet the
`2.10 well
`significantly out-perfonned the Z4 well. This
`demonstrates that a fiactured horizontal well can eli'ecti\'ely
`cli'ain a larger area than a fracture vertical well.
`Perfiirtttirirt Con.t'ira'er.rm'0rr.s‘. Mitch research has been
`done on the optimization of perforations for horizontal well
`fracttiring.'fi"') Table 2 contains perforation details for the Z4
`and Zl0 wells- along with other relevant design and treatment
`data. A short perforated interval was used in the ZIO well to
`avoid the creation of multiple fractures. High shot density and
`large holes ensured that perforation skin effects would be
`mininrizecl. Extreme overbalance perforating?" was also used
`in the ZIO well to minimize fracture initiation presstnes. The
`fracture-specific perforation design was. combined with the
`placement of SSDS in the horizontal completion to allow the
`four fracturing treatments to be selectively placed and allow
`selective isolation and re-entry. These advances in perforating
`and completion technology contributed significantly to the
`ability to effectively fracture-stimulate the high-pressure
`intervals in the Z|0 well, Specific details of the perforation
`techniques used in the Zl0 well are given in reference 10. A
`simplified completion diagram is show in Figure 2.
`Flair! Crm.1':'derrrtiorr.r. Advances
`in
`fracturing fluid
`technologies
`allowed
`significantly
`higher
`proppant
`concentrations to be placed in the Zl0 well. (See Table 2)
`This contributed to a reduction in fluid volumes and allowed
`
`more efficient packing of the tinctures. Tip Screen Out {T30}
`designs“ were used to provide additional conductivity in the
`near wellbore area, the portion .of fi'actI.ire where the highest
`flow rates occur. High conductivity was required due to the
`relatively small perforated intervals and anticipated non—Darcy
`effects. A tail—in of resin coated proppant was used to prevent
`proppant back production. Break times were significantly
`reduced to ensure that the proppant was trapped in the fracture
`with minimum settling. To take advantage of the known
`improvements in borate fracturing fluid technologies”, an
`extensive
`fluid optimization program was
`conducted?)
`Viscosity behavior as a function of time, interaction between
`the fracture fluid and resin coated proppant and compatibility
`studies with the formation and completion fluids were
`investigated. Specific details of the fluid optimization are
`
`601
`
`iven in reference II. The lluid fonnulation used in the Z10
`well represented one of the most aggressive tests of borate
`cliemistry to date. This is due to the high BIIT [290°F} and
`high coliccntratioris ofcurahle resin coated proppant (up to l2
`ppg). Both of tliesi: [actors are known to :1dvci'.~aely ellect the
`stability of horntc llnirls as well as the pei'llu'rri:Iricc of high
`tr.-nipemttm:
`l)l'C£ll(I.:t'.‘i.
`l3:il:ineing the lluirl
`.N'lItl1llll}'
`(luring '
`puinpirig and the rapitl hreak time \vas a lcchnienl challenge in
`the Zltl well and would not
`l1(l\'L‘ been pussililc with the
`lDCllllt1lttg_)‘
`that was
`a\':iil:tl}lt: wliclt
`the
`'/.-l well was
`completctl.
`Pmpprrmt Iierrrilv. The fracturing treatment on the Z4 used
`high-strength sintercd bauxite. Even though high quality
`intermediate strength ceramic (ISC) proppants had just been
`introduced to the industry, they had not yet gained acceptance
`and were therefore not used for this treatment. The use of [SC
`
`in the Zl0 well resulted in significant cost reduction, while
`still maintaining the desire for high conductivity. The high
`concentrations of proppant that were placed allowed the ISC
`to be strong enough, even at stress levels as high as 10,000 psi.
`The use of resin coated (RC } proppant
`for tail-in,
`limited
`proppant baclt-pl'0CllICllCln. The desire to use RC propparrt with
`a borate fluid necessitated additional testing as high pH fluids
`can adversely affect
`the ultimate
`compressive strength
`obtained with curable RC proppants. Commercially available
`RC proppants were evaluated which consolidate in the
`fracture, but not in the wellbore in case of premature screen-
`out.” The use of such proppants, particularly in a high-
`tempcrature borate
`fluid,
`is another
`illustration of
`the
`technological advances that were made in the time between
`the fracturing ofthe Z4 and Z10 wells.
`important
`the most
`Trerrmierrr Executr'rm.
`Perhaps
`advances in fracturing technology have been in the area of
`treatment execution. Proper fonnation breakdown techniques,
`along with variable-rate injection tests and erosion sand
`slugsw“ helped to limit surface treating pressures which were
`slightly higher in the Z10 well than in the Z4 well. (See Table
`2). In addition, proper minifrac analysis as well as real-time
`monitoring of the bottom hole treating pressure allowed
`greater confidence in executing the T80 designs. Automated
`control of the
`fracturing equipment provided execution
`consistency not available at
`the time the Z4 well was
`fractured. Specific details of the treatment execution are given
`in references 8 and I I.
`
`Treatment Results. Table 3 compares the treatment results
`for the Soehlingen Z4 and Z10 wells. The use of multiple
`fractures in the horizontal Z10 well provided a four tirnes
`higher well productivity than the Z4 well. The best summary
`of this project is obtained by quoting directly from the Mobil
`engineers "The pioneering project provided evidence that the
`integration of horizontal well and stimulation techniques will
`mobilize new reserves
`from very low permeability gas
`reservoirs. Above all, this represents a breakthrough for the
`future development of light gas reservoirs.“
`
`Page 3 of 11
`Page 3 of 11
`
`

`
`4
`
`M.S.\i'AN DOMELEN
`
`SPE 49523
`
`Case Study 2: Phillips UK's Joanne Field
`
`The Reservoir. The .luclyr'Joanne Fields are located in the UK
`sector of the central North Sea, commonly known as the J
`Block. The original field development plan consisted ofa 24-
`slot platfonn for Jud)‘ and a
`l2-slot subsca template for
`.loaune. Wells in the Joanne produce priInaril_v from Dauirut
`sediments with the iutertals of iI'.IcI'est the likolisk and Tor
`
`chalks. These fonnrttions tend to be snll. Reservoir prcssut'e is
`=':'.ll00 psi 'at1dteInpe1'at1ire is 2~l0°F. Depth ram__vcs litun 9.000
`to l l_000 ii. Experience with other North Sea cltalks showed
`that extensive acid stimulation programs are required in order
`to achieve commercial production rates.‘i5':7 Each chalk well
`would
`contain multiple
`producing
`intervals.
`Selective
`placement of the acid stimulatious was therefore critical to the
`success of the project.
`
`The History. Phillips’ original plan was to drill up to I2
`deviated. wells, however, because drilling horizontal wells
`would allow a reduction in the nulnber of well slots,
`the
`decision was made to complete horizontally,” The new wells
`were designed to intersect the most productive reservoir layers
`twice, to further maximize production. A review of similar
`completions carried out by other North Sea operators indicated
`that an excessive amount of rig time would be required to
`perform the selective stimulations, typically 3-4 days per zone.
`From the initial review, it was apparent that the project could
`not support the increased rig costs. and thus. an altematit-"e
`completion and stimulation method was needed.
`
`The Challenge. Completion systems for selective stimulation
`of horizontal wells had been used in the Danish sector of the
`
`North Sea for several 3'ears.2°‘m These systems, however,
`require an additional
`trip with the drill string with each
`interval to be selectively perforated, stimulated and isolated.
`Hence, there is a significant increase in rig time and time on
`location for the stimulation vessel. The goal was to develop a
`new completion so that each zone could be treated directly
`afier the previous zone. Simplicity, rig savings and stimulation
`cost reduction were the primary driving factors during the
`design stage.
`
`The Solution. An innovative completion design that allows
`rapid, multiple
`stimulations
`(fracture or matrix)
`to be
`perforrned in horizontal wells was developed. Specific system
`details are given by Thomson and Nazaroo.” This field-
`proven system allows acid stimulation of up to I0 different
`zones in a single trip without
`through-tubing intervention.
`Figure 3 shows a typical Joanne completion. The key element
`of the completion system is a Multi-Stage Acid Frac (MSAF)
`tool that is similar to a sliding sleeve circulating device and is
`nin in the closed position. Up to 9 MSAF tools have been run
`in the Joanne completions. Zonal
`isolation is achieved by
`hydraulic-set retrievable packers positioned on each si_de of the
`MSAF tools. Each sleeve contains a threaded ball seat with the
`
`smallest ball seat in the lowest sleeve and the largest ball seat
`
`in the highest sleeve. With this system, stimulation of ten
`separate zones is accomplished with no tubing trips or planned
`shut—down during stimulation services.
`
`Completion and Stimulation. Before running the l\-IS.-\l-'
`completion. each well was peifotntctl
`\\'llll
`luhin_t,'-convc_vctl
`perforation {TCP} grins. Multiple packers were spacer! out in
`order to isolate the zones to be slimulzttetl. The completions
`were run in one trip to the safety valve and pa-:l~:ers were set
`sin1u|taneousl_\' (up to ten packers at a time!) .-\|"ter all
`the
`surface equipment was
`installed.
`the
`lower most pump
`outfcycle plug was expelled and stimulation operations were
`ready to commence.
`.5'rr'mu!trt'r'mt of the MT. The first well, Ml _ was completed
`and stimulated by the Big Orange XVIII in August I994. A
`total of 200,000 gallons of 28% H Cl was used to acidise seven
`zones in less than eight hours. Pump rates during stimulation
`ranged from 25-40 BPM at surface pressures of 5,500 to 8,500
`psi. During stimulation, pumping operations were continttous.
`The pump rates were reduced to 5 BPM to lubricate each ball
`into the wellbore. The pnmp- rate was then increased to 20 to
`25 BPM to transport each ball to within 500 ft of its mating
`seat. The rate was reduced to 5 BPM until the ball seated.
`
`Once each ball found its seat, the pressure was increased until
`the shear screws sheared, allowing the sleeve to move down to
`the open position. The ball provided positive isolation of the
`zone that had just been treated and allowed stimulation of the
`next zone to commence. The process was repeated until all
`seven zones were stimulated. After treatment, all six balls
`were flowed back to surface and caught
`in a ball catcher
`during clean-up operations.
`Srr'm:rIm‘iwt of the M5. Provisional treatment designs for
`the following three wells required 320,000 to 390,000 gallons
`of 28% HC I per well.) ' These wells have ten zones each, to be
`stimulated selectively. This presented a new challenge, as
`available raw acid storage capacity on North Sea vessels is
`limited to 180,000 gallons. The use of a single vessel required
`a retum to port in order to re-load and a minimum of 36 hours,
`per trip, would be added. The solution was to use two vessels.
`The original plan was to stimulate the first five zones with one
`vessel, then the last five by the second vessel. The M5 was
`stimulated in June 1995 by the Western Renaissance followed
`by the Vestfonn. Unfortunately, surface treating pressures on
`the M5 reached 9,500 psi and subsequently the treatment rates
`had to be reduced. The treatment time was extended, and the
`pumps were required to run at 9,500 psi for the greater part of
`the job. This type of pumping was hard on the conventional
`pumps as the treatment pressures were only slightly below the
`pumps' 10,000 psi maximum.” Individual ptunp failures
`increased the total stimulation time to 24 hours for the M5.“
`In spite of the problems during pumping, the treatment was
`considered a success.
`
`Srinurlrtrion aftlie M4 rim! M3. It was decided that the M4
`and M3 would be
`treated with both vessels pumping
`simultaneously. The use of l4 pumps, at the same time, would
`lessen the strain on each pump and reduce the consequences of
`
`Page 4 of 11
`Page 4 of 11
`
`

`
`
`
`ENHANCED PROFITABlL|TY WITH NON—CONVENTlONAL IOR TECHNOLOGYSPE 49523 5
`
`
`
`individual pump failures.” This would be the first time that
`two dynamically-positioned North Sea stimulation vessels had
`been rigged up on the same well simultaneously. Fewer
`problems were encountered and the time to stimulate each of
`these wells was about halfthe time needed for the M5. Table 4
`
`contains a summ2u'_v ofthc total time to install completions and
`earn’ out the stimulalions on the tour .loaune wclls.
`
`tie|tl—proven i|rl’l1i|lips'
`tool was lirst
`Results. The h|S.—\l-‘
`Joanne Field. One 7—zone completion and three
`I0-zone
`completions were run in the summers ol‘ I994 and I995. Large
`volumes of fluid. 300,000 gallons of 28% HCI a11d l30_000
`gallons of gelled pad were selectively placed. An additional
`I0-zone completion was installed in Phillips’ Hewett 48129-
`Bl 1 well. Most recently, the MSAF completion has been used
`in the Ekofisk Field in the Norwegian sectoriof the North Sea.
`Cost savings due to rig time reduction more than offset the
`cost of the completion. Tables 5 and 6 illustrated the economic
`value to the customer (E\/C} realized through the use of the
`MSAF completion.” Not only was the total number of wells
`required reduced significantly, but significant savings per well
`were demonstrated as a result of the substantially reduced rig
`time. Advances in completion and stimulation technologies
`allowed the marginal Joanne Field to be economic.
`
`Case Study 3: High Relief, Marginal Chalk Fields in
`the North Sea
`
`The History. Chalk fields have been on production in the
`North Sea since the early 1970's. The best known are Phillips’
`Ekofisk, A1noco's Valhall and Maerslfs Dan Field. These
`fields
`are
`located in the Central North Sea, near
`the
`intersection of the Norwegian, Danish and UK sectors. As
`early as the mid-l9?0’s, marginal fields were discovered in
`this area, however,
`technology at
`the time did not allow
`colnmercial development. One of the first marginal fields to be
`developed was State-il's Tommeliten Field. This project, a
`subsea development in water depth of 250 ii, is based upon the
`use of existing infrastructure of the Ekofisk Complex.
`Completion and stimulation of the conventional deviated wells
`took place during the
`summer of
`1988.21 Stimulation
`programs, which consisted of alternating stages of crosslinked
`pad and gelled acid diverted at high rates with ball sealers,
`were very successful. Today the Tommcliten wells continue to
`produce above expectation and no interventions have been
`required during the 10 years since initial completion.“
`
`The Challenge. Several marginal fields were discovered in
`the UK sector of the North Sea, in an area that is commonly
`called the Central Graben. Water depth in this area ranges
`from 300 to 350 ft. The distinguishing feature of these fields is
`that the chalk reservoirs are draped over a salt diapir and of‘
`very high relief {up to 60°). Reservoir uncertainty was high
`due to seismic imaging problems as a result of the steep dip
`and poor reflections off the adjacent salt dome. Appraisal
`
`wells were drilled near-vertical and conventionally deviated.
`Some DST results were promising (2,500 to 3,500 BOPD},
`however, others were lack-luster {400 to 600 BOPD). Less
`than economical
`test
`rates were attributed to both well
`
`these
`ln addition.
`arcliilccunc and inadequate stimulaiimi.
`tiehls dirl not have the hen-zlil
`tit‘ an existing infrastructure.
`whieli cmnplicuterl :u1d delayed tlcvelopnient.
`
`The Rt-‘servuir. Two lields will he discussetl: both have a
`similar Llescription. The reservoirs consist of fracttircd chalk
`adjacent to a large salt diapir. The zones otiiutcrest include the
`El-colisk and Tor. The bull: ofthe reserves lie in the tight chalk
`matrix with production coming from the natural
`fracturér
`network. Due to the high relief and thickness of the reservoir
`rock {200 to 600 ft} the oil columns can be high at 3000 ft.
`Figure 4 shows a typical reservoir cross-section. True vertical
`depths (TV[)} can range from 3,500 to 7,500 ft. Bottom hole
`temperatures range from I90 to 220°F, depending upon TVD.
`The reservoirs are slightly overpressured with initial gradients
`of about 0.58 psilft at
`the top of the structure and fluid
`gradients of 0.28 to 0.30 psifft in the reservoir. Identification
`and stimulation of the primary natural fracture networks is
`considered crucial to the success of the developI'nenls_
`
`The Results. Many advances in tecluiology contributed to the
`ability to develop these high relief, marginal chalk fields.
`Structural mapping was improved by the advent of 3D seismic
`data analysis, Natural
`fracture identification was enhanced
`through detailed evaluation of mud losses while drilling."
`Borehole image logs {both sonic and resistivity tools} and
`nuclear magnetic resonance logs complimented the drilling
`data.” Steering using paleontology and advances in directional
`drilling allowed the stratigraphically horizontal wells to be
`accurately positioned.
`In later developments, water—based
`drilling fluids were used to minimize damage to the natural
`fracture network. The use of early production systems (EPS)
`allowed the opportunity to resolve reservoir uncertainties prior
`to full
`field Cl€\-'ClD[JlTlEt‘ll,'“"‘s
`Finally,
`the
`integration of
`completion and stimulation
`design delivered the high
`productivity essential for economic development. “H”
`B!’ Mr:c'I:nr. Located in Block 23i'26a of die UK sector of
`
`the Nort.h Sea. the Machar Field represents the next step up
`from an Extended Well Test (EWT) to an EPS, ultimately
`resulting in full field development of a marginal field. A 300-
`day EWT following completion and stimulation of the Machar
`wells is thought to have lead to a reserves upgrade. estimated
`at about 62 million barrels,"""“ Details of the well design and
`stimulation treatments
`in the Machar are presented by
`Gilchrist. stat.-‘° Drilled at z55° deviation, the objective of the
`Machar wells was to intersect as many of the primary natural
`fracture systems in the reservoir as possible. The main
`completion
`design
`objective
`was
`to
`ensure
`good
`wellbore;"fi'acture communication. Two completion options
`were considered; an uncemented liner with external casing
`packers (ECPS) or a cemented liner, selectively perforated
`across the zones of natural fracturing. Although cementing
`
`603
`
`Page 5 of 11
`Page 5 of 11
`
`

`
`6
`
`M.5. VAN DCIMELEN
`
`SPE 49523
`
`posed the risk of either damaging or ‘‘missing'' the natural
`fractures,
`the cemented liner approach was selected based
`-upon wellbore stability studies and resen'oir management
`considerations. Although it was recognized that a water-based
`lI'IllLl was preferred to an oil-based one (from a formation
`tlntnagc viewpoint). drilling problems on an earlier well
`iicccssitatcd the switcli to an oil-based tnnd system.
`|\lassi\'e acid li'acluring treatments were perfonncd on the
`i\|ui:|1:n' liiz and 205' wells in the Sll!‘Itlt1Cl'S of I99-l and I995.
`I'c.~:pccti\'ely. The treatment design was very similar to the
`approach that had been used successfully in the Tonuneliten
`Field.” Specific attention to the execution and evaluation of
`the Machar stimulation treatments was given by Lietard, et.
`al.“ Examination of Table '2’ shows some very interesting
`highlights from the stimulation treatment results. In all of the
`treatments, the number of stages was related to the number of
`perforated intervals. Note that although stimulation of the near
`vertical 132 well "resulted in a substantial
`increase in the
`Productivity Index (Pl), production for
`this well was not
`economic. The two stratigraphically horizontal wells not only
`sltowecl a record increase in PI” but also resulted in sustained
`average production rates of 23,000 BOPD and the production
`of 14.6 million ban'els over the 21-month project.”
`results
`(fmmco Bmrflf Encouraged by
`the
`positive
`achieved by BP in the Machar EWTIEPS; Conoco and
`partners entered into Phase l of the Banif development
`in
`Blocks 29r‘2a and 22f2?a in the summer of 1996. Phase 1
`
`consisted of two stratigrapliically horizontal production wells
`and one truly holizontal water injection well. The drilling,
`completion and stimulation strategies
`for
`the two Banff
`producers were almost identical to the BP Machar plans, with
`the exception being that recent advances in drilling fluid
`technology allowed water-based muds to be successfully used
`in Banff. Details of the well tests before and after stimulation
`
`in Banff are not published, however, production during the last
`3 months of 1996 was reported to average 25,630 BOPD."
`This represents a substantial improvement over the discovery
`well results which ranged from a low of 563 BOPD to a high
`of 3,200 BoPD.*° Results of the 6-month EWT allowed
`Conoco to better estimate the oil reserves at about 60 million
`
`barrels.“ Approximately 5 million barrels were produced
`during Phase I.” First oil from Phase II is scheduled for June,
`I998.
`
`Improved Recovery. The BF Machar and Conoco Banff
`examples demonstrate how advances in technology can be
`lead to IOR. The importance of designing a well “from the
`reservoir up" and integrating drilling, logging, completion and
`stimulation design is clearly illustratedln the short term, the
`EPS phase of these projects resulted in the recovery of nearly
`20 million barrels of oil, which could not have been
`economically produced several years
`ago.
`In addition,
`approximately [20 billion barrels of reserves were added to
`these two compar1y’s assets.
`
`Conclusions
`
`l.
`
`The Soehlingen case history demonstrates that economic
`production can be achieved from deep, low permeability
`reservoirs through application of fracturing technology in
`horizontal wells.
`
`'4.)
`
`2. The Joanne case history illustrates the importance of
`evaluating a project “as a whole". What might have been
`viewed as an increase in completion costs. was more than
`offset by reduction in drilling and stimulation costs.
`The high relief chalk case histories confirm the NPD
`definition of IOR. Technological advances allowed these
`marginal
`fields
`to be economically produced in the
`1990's, nearly 20 years after initial discoveries.
`4. The importance of designing a well “from the reservoir
`up" and integrating drilling,
`logging, completion and
`stimulation design is clearly illustrated.
`
`Acknowledgments
`In many ways, it is not fair for me to be the only author on this
`paper. Although I have been involved to some extent in all of
`the case histories presented,
`I can not ignore the significant
`contributions of my colleagues at Halliburton and some of the
`customers who have been instrumental
`in these projects’
`success. These people have often provided guidance and
`many stimulating conversations.
`In particular, I would like to
`mention Klaas van Gijtenbeek, of Ha1liburton’s EuroFrac
`Team, and the researchers at Hallibur1on's European Research
`Centre.
`I would also like to thank the crew of the Skandi
`
`Fjord with whom it has been my pleasure to work with and
`learn from on many projects. Last but not least, special thanks
`to both Ibrahim Abou-Sayed and Wadood El Rabaa, Mobil,
`both of whom have helped to expand my expertise from
`acidising into hydraulic fracturing.
`
`References
`l. Econornides, M. and Ogle, K.C.: "Horizontal Wells: Completion
`& Evaluationi, PE307 Petroleum Engineering! 1993} I]-IRDC.
`2. de Pater, C.J., et.al.:
`"Propped Fracture Stimulation in Deviated
`North Sea Gas Wells", paper SPE 26794 presented at
`the
`Offshore European Conference, Aberdeen, September 7-10,
`1993.
`
`“Fracture Stimulation of Horizontal
`3. Baumgartner, W.E., et.al.:
`Well
`in a Deep. Tight Gas Reservoir: A Case History from
`Offshore The Netherlands“, paper SPE 26795 presented at the
`Offshore European Conference, Aberdeen, September 7-10, 1993.
`4. Rylance, M., et.al.: “Novel Fracture Technology Proves Marginal
`Viking Prospect Economic, Part I Implementation of Fracttire
`Treatments”, paper SPE 36472 presented at the Annual Technical
`Conference and Exhibition. Denver, CO, October 6-9, 1996.
`S. Haidar, S., et.al.: “Novel Fracture Technology Proves Marginal
`Viking Prospect Economic, Part 11 Well C]ean—Up, Flowback and
`Testing”, paper SPE 36473 presented at the Annual Technical
`Conference and Exhibition, Denver, CO, October 6-9, 1996.
`6. Brinkman, F.W.:
`"Status report on fracturing of deep and low
`permeability fonnations in West Germany," paper SPEIDOE
`9352, presented at the SPFJDOE Low Penneability Symposium,
`Denver, Colorado, May 27~29. 1981.
`7. Bleakley, W.B.: "Mobil AG scores with massive frac,“ Pet. Eng
`l_1'_t§l_., (Jan. 1984}, p 72-83.
`
`Page 6 of 11
`Page 6 of 11
`
`

`
`SPE 49523
`
`ENHANCED PROFITABILITY \t‘li'lTH NOMCONVENTIONAL IOR TECHNOLOGY
`
`10
`
`I5.
`
`“Fraced horizontal well shows
`Schueler, S. and Santos, R.:
`potential of deep tight gas”, Oil_& Gas .1. (Jan. 8, 1996) pp. 46-53.
`Pust, G. and Sch-amp, J.: “soehlingen Z I 0: Drilling Aspects of a
`Deep Horizontal Well for Tight Gas“, paper SPE 305 30 presented
`at
`the Offshore Europe
`(‘c-nference. Alierdecn, Scotland,
`September 5-8, I995.
`“Well
`.-\'.
`i\l_\\-'_ and (ii'tissttitti1.
`Cltrtmbers,
`l\I.l{., Mueller,
`('un1p|ction D-.'si:__-n and Operaliotts liar

This document is available on Docket Alarm but you must sign up to view it.


Or .

Accessing this document will incur an additional charge of $.

After purchase, you can access this document again without charge.

Accept $ Charge
throbber

Still Working On It

This document is taking longer than usual to download. This can happen if we need to contact the court directly to obtain the document and their servers are running slowly.

Give it another minute or two to complete, and then try the refresh button.

throbber

A few More Minutes ... Still Working

It can take up to 5 minutes for us to download a document if the court servers are running slowly.

Thank you for your continued patience.

This document could not be displayed.

We could not find this document within its docket. Please go back to the docket page and check the link. If that does not work, go back to the docket and refresh it to pull the newest information.

Your account does not support viewing this document.

You need a Paid Account to view this document. Click here to change your account type.

Your account does not support viewing this document.

Set your membership status to view this document.

With a Docket Alarm membership, you'll get a whole lot more, including:

  • Up-to-date information for this case.
  • Email alerts whenever there is an update.
  • Full text search for other cases.
  • Get email alerts whenever a new case matches your search.

Become a Member

One Moment Please

The filing “” is large (MB) and is being downloaded.

Please refresh this page in a few minutes to see if the filing has been downloaded. The filing will also be emailed to you when the download completes.

Your document is on its way!

If you do not receive the document in five minutes, contact support at support@docketalarm.com.

Sealed Document

We are unable to display this document, it may be under a court ordered seal.

If you have proper credentials to access the file, you may proceed directly to the court's system using your government issued username and password.


Access Government Site

We are redirecting you
to a mobile optimized page.





Document Unreadable or Corrupt

Refresh this Document
Go to the Docket

We are unable to display this document.

Refresh this Document
Go to the Docket