throbber
Case 2:11-cv-10474-GAF-JCG Document 157 Filed 08/01/13 Page 1 of 5 Page ID #:3980
`
`
`
`
`Caroline H. Mankey, SBN 187302
`Email: caroline@cypressllp.com
`Robert J. Muller, SBN 189651
`Email: bob@cypressllp.com
`CYPRESS, LLP
`11111 Santa Monica Blvd., Suite 500
`Los Angeles, California 90025
`Telephone: (424) 901-0123
`
`Seth H. Ostrow (Pro Hac)
`sostrow@ostrowkaufman.com
`Matthew L. Kaufman (Pro Hac)
`mkaufman@ostrowkaufman.com
`Jeanpierre J. Giuliano (Pro Hac)
`jgiuliano@ostrowkaufman.com
`OSTROW KAUFMAN LLP
`555 Fifth Avenue, 19th Floor
`New York, NY 10017
`Telephone: (212) 682-9200
`
`Attorneys for Plaintiff
`Advanced Media Networks, LLC
`
`UNITED STATES DISTRICT COURT
`CENTRAL DISTRICT OF CALIFORNIA
`
`1
`
`2
`
`3
`
`4
`
`5
`
`6
`
`7
`
`8
`
`9
`
`10
`
`11
`
`12
`
`13
`
`14
`
`15
`
`16
`
`17
`
`18
`
`19
`
`20
`
`21
`
`22
`
`23
`
`24
`
`25
`
`26
`
`27
`
`28
`
`
`
`
`
`
`
`
`
`ADVANCED MEDIA
`NETWORKS, LLC,
`
`
`Plaintiff,
`
`Case No. CV-11-10474 GAF (JCGx)
`
`Assigned to: Hon. Gary Allen Feess
`
`MEMORANDUM OF POINTS AND
`AUTHORITIES SUPPORTING
`AMN’S UNOPPOSED MOTION TO
`VACATE THE CLAIM
`CONSTRUCTION ORDER DATED
`JUNE 14, 2013
`
`Date: September 9, 2013
`Time: 9:30 a.m.
`Place: Courtroom 740 – Roybal
`
`
`
`
`
`) ) ) ) ) ) ) ) ) )
`
`
`)
`)
`)
`)
`
`) ) ) )
`
`
`
`v.
`
`
`GOGO LLC, AIRCELL BUSINESS
`AVIATION SERVICES LLC, DELTA
`AIR LINES INC., NETJETS INC.,
`AND XOJET, INC.,
`
`
`Defendants.
`
`
`
`MOTION TO VACATE CLAIM CONSTRUCTION
`
`
`
`
`Petitioners' Ex. 1025 - Page 1
`
`

`
`Case 2:11-cv-10474-GAF-JCG Document 157 Filed 08/01/13 Page 2 of 5 Page ID #:3981
`
`
`1
`
`2
`
`3
`
`4
`
`5
`
`6
`
`7
`
`8
`
`9
`
`I.
`
`Introduction
`
`Plaintiff Advanced Media Networks, LLC (“AMN”) submits this
`
`memorandum in support of its Unopposed Motion to Vacate the Claim Construction
`
`Order dated June 14, 2013. Defendants Gogo LLC, Aircell Business Aviation
`
`Services LLC, Bombardier Aerospace Corporation, Delta Air Lines Inc., Learjet Inc.,
`
`NetJets Inc., United Airlines, Inc., and XOJET, Inc. (collectively, “Defendants” and
`
`collectively with AMN, the “Parties”) do not oppose this motion.
`
`II. Background and Procedural History
`
`AMN filed its Complaint in the present case on December 19, 2011 and filed
`
`10
`
`its Amended Complaint on April 9, 2012. On February 8, 2013, the Parties submitted
`
`11
`
`their respective opening claim constructions briefs. (Dk. Nos. 78, 81). On February
`
`12
`
`28, 2013, the Parties submitted their responsive claim construction briefs. (Dk. Nos.
`
`13
`
`110, 113). The Markman hearing was held on April 10, 2013, and the Court issued its
`
`
`
`14
`
`claim construction ruling on June 14, 2013. (Dk. No. 140, the “Claim Construction
`
`15
`
`Order”).
`
`16
`
`Since the Court issued the Claim Construction Order, the Parties have been
`
`17
`
`engaged in settlement discussions and have agreed to a settlement of the action. The
`
`18
`
`agreement to settle the action is predicated on the Court granting the present motion
`
`19
`
`and vacating its Claim Construction Order. Upon this Court granting the present
`
`
`
`20
`
`motion, the Parties have committed to jointly file a Stipulated Order of Dismissal,
`
`21
`
`thereby terminating all disputes between the Parties in the present action.
`
`22
`
`23
`
`III. Legal Standard
`
`Federal Rule of Civil Procedure 54(b) grants this Court the authority to modify
`
`24
`
`any non-final judgment at any time. See Fed. R. Civ. P. 54(b). Claim construction
`
`25
`
`orders are “interlocutory in nature and [do] not fully adjudicate the rights and claims
`
`26
`
`of the parties.” See United States Gypsum Co. v. Pacific Award Metals, Inc., No. C
`
`27
`
`04-04941 JSW, 2006 WL 1825705, at *1 (N.D. Cal. July 3, 2006). As such, a claim
`
`28
`
`construction order “can be vacated at any time prior to final judgment.” Id.; Fed. R.
`
`MOTION TO VACATE CLAIM CONSTRUCTION
`2
`
`
`
`Petitioners' Ex. 1025 - Page 2
`
`

`
`Case 2:11-cv-10474-GAF-JCG Document 157 Filed 08/01/13 Page 3 of 5 Page ID #:3982
`
`
`1
`
`2
`
`3
`
`4
`
`5
`
`6
`
`7
`
`8
`
`9
`
`Civ. P. 54(b); see also Lycos, Inc. v. Blockbuster, Inc., 2010 U.S. Dist. LEXIS
`
`136252, *7 (D. Mass. Dec. 23, 2010) (“the court has the authority to modify claim
`
`construction prior to the entry of a final judgment”). Applying Ninth Circuit
`
`authority, district courts in this circuit have found that “[t]he standard for vacatur of a
`
`claim construction order, which is not final but interlocutory, is even less rigid.”
`
`RE2CON, LLC, v. Telfer Oil Co., 2013 U.S. Dist. LEXIS 46192, *7 (N.D. Cal. 2013)
`
`(citing Persistence Software, Inc. v. Object People, Inc., 200 F.R.D. 626, 627 (N.D.
`
`Cal. 2001)).
`
`The Supreme Court previously addressed the standard appropriate for an
`
`10
`
`appellate court to vacate a final judgment in connection with settlement. U.S.
`
`11
`
`Bancorp Mortgage Co. v. Bonner Mall Partnership, 513 U.S. 18, 29 (1994). The
`
`12
`
`Federal Circuit, however, has explicitly noted that “by its terms, Bancorp does not
`
`13
`
`apply to district courts but rather only to the Supreme Court and to courts of
`
`
`
`14
`
`appeals.” Dana v. E.S. Originals, Inc. 342 F.3d 1320, 1328 (Fed. Cir. 2003) (Dyk, J.,
`
`15
`
`concurring). Additionally, the Ninth Circuit has explicitly found that “a district court
`
`16
`
`should enjoy greater equitable discretion when reviewing its own judgments than do
`
`17
`
`appellate courts operating at a distance.”’ American Games, Inc. v. Trade Products,
`
`18
`
`Inc., 142 F.3d 1164, 1170 (9th. Cir. 1998).
`
`19
`
`
`
`Thus, while Bancorp may provide guidance, the test set forth therein is not
`
`20
`
`directly applicable to district courts considering vacatur of non-final interlocutory
`
`21
`
`orders. See e.g., Lycos at *8 (“[i]t follows that the ‘exceptional circumstances’
`
`22
`
`standard established by Bancorp does not necessarily apply here, where Lycos seeks
`
`23
`
`to vacate the non-final order of a district court”). Rather, a district should use
`
`24
`
`equitable discretion when determining whether vacatur of a non-final order is
`
`25
`
`appropriate. See Cisco Systems Inc. v. Telcordia Tech., 590 F. Supp. 2d 828, 830
`
`26
`
`(E.D. Tex. 2008).
`
`27
`
`IV. ARGUMENT
`
`28
`
`As a result of the Court issuing its Markman ruling, both sides have been
`
`MOTION TO VACATE CLAIM CONSTRUCTION
`3
`
`
`
`Petitioners' Ex. 1025 - Page 3
`
`

`
`Case 2:11-cv-10474-GAF-JCG Document 157 Filed 08/01/13 Page 4 of 5 Page ID #:3983
`
`
`1
`
`2
`
`3
`
`4
`
`5
`
`6
`
`7
`
`8
`
`9
`
`working towards settlement for several weeks and have now reached a conditional
`
`settlement agreement. The Federal Circuit has encouraged such behavior, repeatedly
`
`emphasizing that there is a “strong public interest in settlement of patent litigation.”
`
`Dana at 1328 (J. Dyk concurring). The Parties have conditioned their settlement on
`
`vacating the claim construction order of this Court. As in Dana, the public interest
`
`favors “allowing the parties to a settlement at the district court level to determine the
`
`collateral estoppel effect of earlier orders in the litigation” and thus lends further
`
`support towards vacatur. Id. Such a settlement between the Parties would remove the
`
`potential threat of a final judgment on issues such as infringement and validity while
`
`10
`
`allowing the Parties to focus energy and resources on their customers and the general
`
`11
`
`public they service, as opposed to continued litigation.
`
`12
`
`In addition to the foregoing, absent vacatur and the closing of the settlement
`
`13
`
`agreement thereafter, at least one of the Parties is likely to appeal certain claim
`
`
`
`14
`
`construction issues, which could potentially result in years of further appellate
`
`15
`
`litigation and potential additional subsequent litigation before this Court, albeit
`
`16
`
`delayed. As of 2008 nearly forty percent of claim construction orders have been
`
`17
`
`reversed across all districts. Cisco, 590 F.Supp.2d at 830. Further, the Federal Circuit
`
`18
`
`has reversed claim construction orders from this district at a rate of approximately
`
`19
`
`43.5%. See David Schwartz, Claim Construction Reversal Rates I – Overall
`
`
`
`20
`
`Reversal Rates, PATENTLY-O (Feb. 27, 2008), http://www.patentlyo.com/
`
`21
`
`patent/2008/02/claim-construct.html.
`
`22
`
`Vacating the Claim Construction Order would render such appeals moot. As
`
`23
`
`stated in Bancorp, “the judicial economies achieved by settlement at the district-court
`
`24
`
`level are ordinarily much more extensive than those achieved by settlement on
`
`25
`
`appeal.” Bancorp, 513 U.S. at 28. Thus, the potential negative effects of any appeal
`
`26
`
`of the Claim Construction Order clearly favor vacatur. Additionally, vacatur of a
`
`27
`
`claim construction order may eliminate any confusion with respect to potential
`
`28
`
`preclusive effects and reduces the inconsistent execution of the law between forums.
`
`MOTION TO VACATE CLAIM CONSTRUCTION
`4
`
`
`
`Petitioners' Ex. 1025 - Page 4
`
`

`
`Case 2:11-cv-10474-GAF-JCG Document 157 Filed 08/01/13 Page 5 of 5 Page ID #:3984
`
`
`1
`
`2
`
`3
`
`4
`
`5
`
`6
`
`7
`
`8
`
`9
`
`Accordingly, this weighs in further favor of vacatur in view of the tentative
`
`settlement reached by the Parties.
`
`Vacating the Claim Construction Order and subsequent settlement would
`
`significantly save both the Court’s resources as well those of the Parties. In the event
`
`that certain constructions adopted by the Claim Construction Order are reversed on
`
`appeal, there is the potential for increasing expenses and utilization of resources that
`
`will occur if the case progresses towards trial. As noted in Cisco, while “the court
`
`expends significant resources in construing the claims during a Markman hearing, the
`
`court expends even more resources prior to and during trial.” Cisco at 831–2.
`
`10
`
`Vacatur of the Claim Construction Order and the resulting settlement of the
`
`11
`
`action will substantially contribute to the conservation of resources. Accordingly, the
`
`12
`
`Court should support the settlement entered into by the Parties, conditioned as it is on
`
`13
`
`the Court vacating the Claim Construction Order prior to final dismissal of the case.
`
`
`
`14
`
`15
`
`V. Conclusion
`
`Given the interests of the public, the Parties and the Court, AMN requests that
`
`16
`
`this Court vacate its Claim Construction Order, and Defendants do not oppose this
`
`17
`
`request.
`
`18
`
`
`
`Dated: August 1, 2013
`
`
`
`19
`
`20
`
`21
`
`22
`
`23
`
`24
`
`25
`
`26
`
`27
`
`28
`
`
`
`
`
`
`
`By: /s/ Seth H. Ostrow
`Seth H. Ostrow
`
`OSTROW KAUFMAN LLP
`Seth H. Ostrow (pro hac)
`sostrow@ostrowkaufman.com
`Matthew L. Kaufman (pro hac)
`mkaufman@ostrowkaufman.com
`Jeanpierre J. Giuliano (pro hac)
`jgiuliano@ostrowkaufman.com
`555 Fifth Avenue – 19th Floor
`New York, NY 10017
`Telephone: (212) 682-9200
`Facsimile: (212) 682-9222
`
`MOTION TO VACATE CLAIM CONSTRUCTION
`5
`
`Petitioners' Ex. 1025 - Page 5

This document is available on Docket Alarm but you must sign up to view it.


Or .

Accessing this document will incur an additional charge of $.

After purchase, you can access this document again without charge.

Accept $ Charge
throbber

Still Working On It

This document is taking longer than usual to download. This can happen if we need to contact the court directly to obtain the document and their servers are running slowly.

Give it another minute or two to complete, and then try the refresh button.

throbber

A few More Minutes ... Still Working

It can take up to 5 minutes for us to download a document if the court servers are running slowly.

Thank you for your continued patience.

This document could not be displayed.

We could not find this document within its docket. Please go back to the docket page and check the link. If that does not work, go back to the docket and refresh it to pull the newest information.

Your account does not support viewing this document.

You need a Paid Account to view this document. Click here to change your account type.

Your account does not support viewing this document.

Set your membership status to view this document.

With a Docket Alarm membership, you'll get a whole lot more, including:

  • Up-to-date information for this case.
  • Email alerts whenever there is an update.
  • Full text search for other cases.
  • Get email alerts whenever a new case matches your search.

Become a Member

One Moment Please

The filing “” is large (MB) and is being downloaded.

Please refresh this page in a few minutes to see if the filing has been downloaded. The filing will also be emailed to you when the download completes.

Your document is on its way!

If you do not receive the document in five minutes, contact support at support@docketalarm.com.

Sealed Document

We are unable to display this document, it may be under a court ordered seal.

If you have proper credentials to access the file, you may proceed directly to the court's system using your government issued username and password.


Access Government Site

We are redirecting you
to a mobile optimized page.





Document Unreadable or Corrupt

Refresh this Document
Go to the Docket

We are unable to display this document.

Refresh this Document
Go to the Docket