throbber
LMK Technologies, LLC Ex. 2025
`BLD Services, LLC v. LMK Technologies, LLC
`IPR2014-00770
`
`1
`
`

`
`The First Few
`Feet of the
`Service Line
`
`Joints
`
`Service Line
`Connections
`
`A chemical grout barrier
`outside manholes stops
`leaks, but it also protects
`interior linings from
`hydrostatic pressure.
`
`Special lateral
`packers can stop
`leaks at service
`connections and
`in the first few
`feet of the
`service lines.
`
`2
`
`

`
`TABLE OF CONTENTS
`
`Intent
`
`Exterior Seal
`
`Stabilize Soil and Fill Voids
`
`Application
`
`Equipment
`
`Overview of Test/Seal Procedure
`
`Grout Types
`
`Grout Comparison Table
`Gel-Time Test
`
`Barrel Test
`
`Packer/Camera Relationship
`
`Pipe Wall Control Test
`
`Test Joint
`
`Test Notes
`
`Seal Joint
`
`Joint Sealing Verification
`
`Residual Sealing Material
`Records
`
`Production Rates
`
`Warranty
`
`Variables Which Affect the
`
`Difficulty of Joint Sealing
`Groundwater Pressure Formula
`
`\I\lO\O\O\mChU14-*-0~JUJL»Jo.JoJ[\)[\Jr-—Al--4+-—\>—A+—4
`
`3
`
`

`
`Intent
`
`The intent of chemical grouting in sewer
`systems is to seal leaks and stop infiltration
`and exfiltration. Most leaks in structurally
`sound sewer systems are through pipe joints,
`manholes, service connections, and the first
`few feet of service laterals. The most economical
`
`way to stop those leaks is with chemical grout.
`
`Exterior Seal
`
`Chemical grouts do not stop leaks by simply
`filling joints and cracks. instead, grouting
`chemicals are forced through cracks and joints
`out into the surrounding soil where they gel
`with the soil (See illustration on the front cover).
`This gelled mass forms a waterproof collar
`around leaking pipes and manholes which
`cannot be extruded back into the sewer system.
`
`This watertight collar adheres to the outer
`surface of the pipe or manhole where it will
`stay indefinitely unless removed by excavation.
`If groundwater pressures increase, the collar
`will be pressed even more tightly against the
`structure, increasing its ability to prevent leaks.
`
`If the humidity in the soil declines for a
`long period, the grout may begin to dry. How-
`ever, when the soil humidity returns, the grout
`will absorb moisture and return to its original
`condition. Line flow and soil humidity around
`leaking manholes and sewers are almost always
`high enough to prevent any significant grout
`shrinkage. Additives which prevent shrinkage
`may be used in situations where dryness could
`be a problem.
`
`seen and monitored. However, the situation is
`very different with the rest of the sewer system.
`For small diameter (24" and less) pipes, all
`testing and sealing operations must be
`performed from inside the pipes with remote-
`controlled equipment. As a result, the test/seal
`process discussed herein will concentrate on
`circular cracks in the pipe, pipe joints, the
`connection between lateral service lines and
`
`the main, and the first few feet of service laterals ,
`(See illustration on the inside of the front cover).
`When any of these locations are mentioned in
`the text, all of the locations are implied.
`
`In application, a device called a test/seal
`packer is used to pressure test every joint in a
`manhole-to-manhole pipeline section to
`determine whether or not the joints are
`watertight. The packer is also used to seal any
`joints which fail the pressure test.
`
`Sealing leaks with chemical grout is
`generally applicable in structurally sound
`pipelines. Although chemical grout may stop
`leaks through cracks and breaks in pipes, it is
`not a structural repair. Though it rarely does,
`the inflatable packer used to test and seal pipe
`joints can actually cause additional damage to
`a cracked or broken pipe.
`
`Joint testing and sealing cannot be
`performed effectively in a pipe which has roots,
`debris on the invert, excessive roughness, cracks,
`breaks, severely offset joints, or other conditions
`which prevent the inflatable ends (sleeves) of
`the packer from making continuous, tight
`contact with the pipe on each side of the target
`joint.
`
`Stabilize Soil and Fill Voids
`
`Equipment
`
`In addition to forming a watertight collar
`around pipes, chemical grout is also an
`excellent product to stabilize soil and to fill
`underground voids without excavation.
`
`Application
`
`Since manholes are accessible to workers,
`chemical grout is usually applied there with
`hand-held equipment, and the results are easily
`
`(See illustration on inside of the back cover.)
`
`The basic test/seal equipment consists of:
`
`(1) Closed—circuit TV system to locate the
`packer over the pipe joint
`
`(2) Test/Seal packer
`
`(3) Control panel to control power winch, TV
`camera, packer inflation, joint test sequence,
`chemical injection, and to record data, and
`to View the operations
`
`4
`
`

`
`(4) Hose and reel system to deliver air and
`chemicals to the packer
`
`. Center the packer on the first pipe joint or
`lateral line.
`
`(5) Chemical tanks, pumps, air and electric
`systems
`
`(6) Remote-controlled winches
`
`The design of test/seal packers varies from one
`manufacturer to the other, but all share certain
`characteristics. Mainline packers are cylindrical
`devices which can be positioned in a pipeline
`by means of cables attached to each end. They
`have inflatable ends which can be expanded
`to isolate a short length of pipe and create a
`void into which either air pressure or chemical
`grout can be pumped. Most are hollow to permit
`some sewage flow, even when the packer is
`inflated. Lateral packers have additional
`equipment which allows them to insert a device
`into lateral lines to seal the lines while they are
`pressure tested and, if necessary, sealed with
`chemical grout.
`
`The equipment must be assembled in such
`a way as to provide a means for introducing a
`test medium or grout chemicals, under pressure,
`into the void created by the expanded ends of
`the packer. It must also provide a means for
`continuously measuring the actual static
`pressure of the void area during both the testing
`and sealing operations.
`
`Overview of Joint Test/ Seal Procedure
`
`The following description assumes the proper
`test and seal equipment has been positioned
`near a manhole, and that the pipeline has been
`cleaned:
`‘
`
`1. Examine and test the specified grout
`chemicals above ground.
`(See Grout Types
`and Gel-Time Test)
`
`Test packer’s pressure test system above
`ground (See Barrel Test)
`
`Examine the relationship between the packer
`and the TV camera
`
`(See Packer/Camera Relationship)
`
`Place TV and packer equipment in the
`pipeline and make a control test on the pipe
`wall (See Pipe Wall Control Test)
`
`6.
`
`If the joint or connection is visibly leaking,
`it is not necessary to perform a pressure
`test. Otherwise, perform a pressure test. (See
`Pressure Test)
`
`If the joint or connection fails the pressure
`test, chemical grout should be injected (See
`Grout Injection)
`
`8. Repeat the pressure test.
`
`If the joint or connection passes the pressure
`test, move on to the next joint or lateral
`line and repeat steps 5-9. Otherwise, repeat
`steps 7-9.
`
`Grout Types
`
`Before each new batch of grout chemicals is
`mixed, verify that the chemicals are exactly as
`specified in the contract.
`
`There are four major types of chemical grout
`which are commonly used to seal manholes,
`sewer pipe joints, service connections, and the
`first few feet of service lines:
`
`Acrylamide
`Acrylic
`Acrylate
`Urethane
`
`All of the chemicals listed above are prepoly-
`mers, except Acrylamide, which is a monomer.
`After curing, all of the polymers are non-toxic,
`stable, inert, and permanent when used below
`grade. These chemicals quickly gel outside the
`pipe into a tight-fitting, waterproof seal which
`can permanently prevent infiltration through
`a joint, crack, or lateral connection.
`
`, Gel grouts have a viscosity similar to water
`when they are applied. As a result, they pass
`through cracks and other openings in pipes
`and gel very quickly. In neat form, cured gels
`look like stiff gelatin or rubber. In actual use,
`they penetrate the soil outside the pipeline
`and form a gel/soil matrix that is impermeable
`to water.
`
`Urethane foam grouts are important in
`sealing treatment plant structures and
`
`5
`
`

`
`manholes in sanitary sewers. They are also
`often used to seal pipe joints in storm sewers
`and to fill the annulus at the manhole after
`
`slipline installations. They are seldom used in
`small diameter sanitary sewers. The flexible
`urethane foams create a seal in cracks and
`
`joints, as opposed to forming a grout collar on
`the outside of pipes.
`
`Grout Comparison Table
`VISCOSITY
`(CENTIPOSE)
`
`CATALYST
`
`BEST
`use
`
`Acrylamide 1-2 cps
`(Very low)
`
`Chemical
`
`Sewer
`
`Acrylic
`
`Acrylate
`
`1-2 cps
`(Very low)
`
`1-2 cps
`(Very low)
`
`Chemical
`
`Sewer
`
`Chemical
`
`Sewer
`
`Urethane
`Gel
`
`10-20 cps
`(Low)
`
`Water
`
`Sewer
`
`Urethane 150-500 cps Water Manholes
`Foam
`(Medium)
`
`Gel-Time Test
`
`Each time a new batch of grout chemicals is
`mixed, the gel time should be checked. A small
`quantity of the chemicals should be taken from
`the ends of the packer hose and mixed in a
`paper cup. The gel time should be within the
`range specified by the manufacturer. It should
`be recognized that the temperature under
`ground may be significantly different from the
`one above ground. As a result, the gel time will
`probably differ, also. If the chemicals gel too
`quickly, it will limit the amount of mixed
`chemical that can be forced into the soil
`
`surrounding the pipe. If the chemicals do not
`gel quickly enough, they may increase grout
`usage unnecessarily.
`
`Barrel Test
`
`Since much of the chemical grout installation
`takes place out of sight, it is necessary to make
`sure the installation and test equipment is in
`good working order. For instance, if a packer
`gauge is miscalibrated, an operator cannot
`
`know the true condition of a joint or
`connection. Therefore, an above-ground barrel
`test should be conducted at the beginning of
`each work shift, and at other random times,
`to be sure the equipment is properly calibrated.
`The National Association of Sewer Service
`
`Companies (NASSCO) has developed a control
`test (Barrel Test) which they recommend. A
`test cylinder is constructed to simulate the
`barrel of a sewer pipe, so the equipment can
`be tested above ground. This allows the test
`cylinder to be positioned where the pressure
`reading on both the test cylinder gauge and
`the void pressure monitoring gauge can be
`continuously observed together during the
`test. The reading on both. gauges should be the
`same throughout the test. This test will also
`Verify whether or not the packer is capable of
`holding adequate pressure under ideal
`Conditions. (See diagram on the inside of the back
`cover.)
`
`During the test, the packer sleeves should
`be inflated to the pressure recommended by
`the manufacturer. Then, the test medium
`(either air or water) is to be injected into the
`packer void until the maximum pressure used
`to test the actual pipe joints is reached. This
`pressure is to be held for at least one minute
`to verify that the packer will hold pressure.
`After one minute the shutoff valve should be
`
`opened to simulate a leak. Both gauges should
`quickly return to zero. It is recommended that
`this test be repeated at least three times. No
`actual test/seal operations should be performed
`until the equipment can pass this test.
`
`Packer/Camera Relationship
`
`The distance between the TV camera and the
`
`packer is very important because it controls
`the perspective from which the packer and the
`pipeline are viewed. The packer must be aligned
`visually with the pipe joint or lateral
`connection, so the packer manufacturer’s
`specifications must be followed exactly.
`
`Pipe.Wall Control Test
`
`A structurally sound section of pipe which
`
`6
`
`

`
`contains no joints or lateral connections should
`be tested to establish the maximum perform-
`ance of a good joint. This test will also demon-
`strate whether or not the packer can maintain
`the void pressure necessary to properly test
`and seal the pipe joints.
`
`After entering each manhole section, the
`packer should be positioned on a sound section
`of sewer pipe which has no joints, cracks, or
`incoming lines. Then, the packer sleeves should
`be inflated to the pressure recommended by
`the manufacturer and held for one minute.
`
`If the void pressure cannot be held for at
`least one minute, grout sealing will not be
`effective because the grout cannot be forced
`through cracks because it will leak past the
`packer sleeves. Since no joint can possibly test
`better than a sound section of the barrel of the
`
`pipe itself, the reason(s) for the failure must
`be found and corrected if the pipeline is to be
`sealed properly. In order to properly test and
`seal a pipeline, all pressure loss in the packer
`void must be limited to leaks through joints
`or other openings in the pipe itself. Some
`possible reasons the test may fail:
`
`r'*E*’.N.*‘
`
`Debris on the pipe invert
`Roughness of the pipe
`Porosity of the pipe
`Leaking fittings or hoses on the test/seal
`equipment
`
`Test Joint
`
`After the requirements of the previously
`described tests have been met, the test/ seal
`packer can be moved to the first pipe joint or
`lateral line connection. A joint or connection
`that is actively leaking need not be tested; the
`sealing operation may begin immediately. All
`joints, cracks, and incoming lines which are
`not actively leaking or structurally damaged
`should be tested. To properly test a joint, the
`following steps should be taken:
`
`1. The packer must be centered on the joint
`or lateral connection to be tested. If the
`
`packer is not centered, the test results may
`be false. Verify that the packer manufacturer's
`
`alignment instructions are being followed.
`
`2. The packer sleeves should be expanded until
`they make circular contact with the pipe on
`both sides of the joint or connection to be
`tested. At this point, some air and water will
`be trapped in the packer void unless the
`pipe is dry. Since the packer sleeves are
`touching the pipe, but not pressing tightly
`against it, the void will not hold pressure.
`If the joint were tested at this point, it would
`fail the test.
`
`. The packer sleeves should now be inflated
`to the pressure recommended by the
`manufacturer.
`
`. As the packer sleeves are expanded to press
`and seal against the pipe, the packer void
`becomes smaller, and one of the following
`conditions will result:
`
`(a) Void pressure may increase because the
`volume has decreased due to the
`
`expanding packer sleeves and there is no
`leakage from the void.
`
`(b) Void pressure may increase until it equals
`groundwater pressure due to infiltration
`into the void. Unless care is taken, one
`could mistake the steady pressure as an
`indication of a good joint.
`A
`
`(c) Void pressure may decrease or show no
`change because there is leakage past the
`packer sleeves or through the pipe joint.
`
`. Testing is usually performed by pumping a
`test medium (liquid or air) into the void and
`monitoring the resulting void pressure. In
`» other cases, testing may be performed by
`expanding the center section of the packer
`to compress the air and the water trapped
`in the packer void when the packer sleeves
`were inflated. In either case, it is necessary
`to develop a void pressure greater than
`groundwater pressure outside the pipe in
`order to tell whether or not the joint is
`leaking (See Groundwater Pressure Formula).
`
`7
`
`

`
`(a) If the required test pressure cannot be
`developed, the joint will have failed the
`test.
`
`(b) If the required test pressure can be
`developed, the flow of the test medium
`may be stopped. If, in the case of a liquid
`test, the pressure cannot be maintained
`for one minute with less than 1/4 gpm
`flow, the joint will have failed the test.
`If, in the case of an air test, the void '
`pressure decreases by more than 2 psi
`within 15 seconds, the joint will have
`failed the test. For more information
`
`about pressure tests, see Test Notes below.
`
`Test Notes
`
`The manner in which pressure in the packer
`void changes during a test depends upon
`several factors:
`
`1. The test medium: Water and air perform
`very differently when used as the test
`medium.
`
`(a) Air will be above the water in the void,
`unless it leaks out.
`
`(b) Air escapes through a leak about 15 times
`faster than water.
`
`(c) Air may be compressed. Air pressure will
`slowly dissipate through a very small
`leak due to the air volume in the packer
`void and the hose.
`
`((1) Air escapes through a small hole so easily
`that a leak which is too small to seal
`
`effectively with chemical grout can be
`detected. A leak of the same size may
`pass a water test.
`
`(e) If water is present in the packer void, it
`will always be at the bottom of the Void.
`
`(f) Water cannot be compressed. In theory,
`if one drop leaks out of a fixed volume,
`all pressure is lost.
`
`(g) Water creates its own static pressure.
`Water in a hose that is connected to a
`
`pressure gauge 23 feet below will create
`a static pressure head of 10 psi at the
`pressure gauge. Therefore, packer void
`
`pressure must be measured at the void
`and the information must be transferred
`
`by some means other than a hose filled
`with water.
`
`2. The location of a leak: There can be a
`
`significant difference in test results depending
`upon whether a leak is located at the top or
`at the bottom of the packer void, and
`whether the test medium is air or water.
`
`(a) Air test, leak at top of packer void: Air is
`pushed out through the leak, so pressure
`may not rise.
`
`(b) Water test, leak at top of packer void:
`Water will push air out through the leak
`until the packer void is filled with water;
`then the pressure may rise.
`
`(C) Air test, leak at the bottom of the packer
`void: Air goes to the top and will push
`water out through the bottom leak. The
`leak is tested with water until air fills the
`
`packer void; then pressure will fall quickly
`as the air escapes through the leak.
`
`leak at the bottom of the
`((1) Water test,
`packer void: Pressure may rise at first,
`then begin to slowly fall after water source
`is cut off.
`
`Seal Joint
`
`If the joint passes the pressure test, that fact
`should be noted on the records (See Records)
`and the packer should be moved to the next
`joint or lateral connection where the five steps
`described under Test Ioint should be repeated.
`If the joint fails the test, it should be sealed.
`The sealing process involves the following:
`
`1. Pump the grout chemicals into the packer
`void. The two parts of the chemical grout
`system may be pumped through the hoses
`from the chemical tanks to the packer void
`by either pressurized air or mechanical,
`positive displacement proportioning pumps.
`In either case, the two grout components
`must be pumped in a correct and adequate
`ratio of base material to activator. The two
`
`parts of the chemical grout system must be
`adequately mixed in the packer void or the
`
`8
`
`

`
`chemical grout will not form properly.
`
`2. If proper pressure is applied (See Groundwater
`Pressure Formula), the mixed chemicals will
`be forced out of the pipe through the leak.
`Depending upon chemical type, mixing
`ratios, and temperature, the chemical will
`gel in a predictable time after the chemicals
`are mixed together (See Gel-Time Test). When
`the chemicals gel outside the pipe, they form
`a tight-fitting, Waterproof collar around the
`pipe which cannot be forced back into the
`pipe. The maximum life expectancy of
`properly mixed and placed grout is not yet
`known, but samples have been examined
`after 30 years and found to be in "like new”
`condition. If the joint is actively leaking,
`the packer void may be filled with water
`when the chemicals are pumped into the
`void. The water in the void will dilute the
`
`incoming chemical grout components.
`
`. Injection of chemical grout should be
`terminated when void pressure approaches
`10 psi. If 10 psi is not reached rather quickly,
`pumping should be stopped for a period of
`time at least equal to the duration of the
`grout's gel time. At that point, additional
`grout may be pumped. If the pressure has
`not begun after pumping additional grout,
`it may not be possible to seal the leak with
`chemical grout. In this event, the client’s
`inspector and the grout operator should
`decide if another attempt should be made.
`In this situation, the opinion of an
`experienced operator is usually correct.
`
`4. The packer sleeves should now be deflated.
`The void pressure may drop to minus 2 psi
`and then return to 0 psi. The deflating packer
`sleeves often create a vacuum before they
`lose their seal against the pipe surface.
`
`pressure does not return to zero, the contractor
`should clean and/or adjust the equipment so
`accurate void pressure readings can be made.
`Then, the leak should be tested again (See Test
`loint). Leaks that fail to meet the specified test
`criteria should be resealed and retested until
`
`the specified test criteria can be met.
`
`If the leak passes the pressure test, the
`packer and camera should be moved to the
`next joint, crack, or incoming lateral line where
`the test/seal/test process will be repeated.
`
`Residual Sealing Material
`
`Residual sealing materials that extend into the
`pipe reduce the pipe’s diameter and restrict
`flow, so they should be removed. Sealed joints
`should be left reasonably flush with the existing
`pipe surface. If excessive grout accumulates in
`the pipeline, the pipe section should be cleaned
`to remove the residual material.
`
`Records
`
`The installation contractor should keep the
`following records for each job:
`
`1. The identity of each manhole-to-manhole
`section where work is done.
`
`. The location (footage) of each joint, crack,
`or incoming lateral line that was tested. The
`pressure used should be recorded as well as
`the result (pass or fail).
`
`. The location (footage) of each joint, crack,
`or incoming lateral line where grout was
`applied, how much grout was injected, and
`whether or not the joint was sealed.
`
`. The exact identification of the grout that
`was used.
`
`5. If the leak was sealed, it should be tested
`again (See Ioint Sealing Verification).
`
`Production Rates
`
`Joint Sealing Verification
`
`After a leak has been sealed, the packer should
`be deflated and moved. This will break up the
`gel ring around the packer and cause the void
`pressure meter to return to zero. If the void
`
`The amount of time and material required to
`test and seal leaks may vary considerably from
`one section of the country to another, between
`pipes of different diameter, or even from one
`pipeline section to another. Therefore, the
`ability to accurately estimate production rates
`can only be gained through experience.
`
`9
`
`

`
`However, this information can be extremely
`useful when estimating costs of future jobs or
`when comparing contractors or contract bids.
`
`Warranty
`
`Grouting specifications often include provisions
`for an eleventh month inspection of at least
`10% of the total joints tested in the original
`contract. The line sections to be re-tested should
`
`be selected at random by the owner and should
`represent the same mix of sizes as the original
`contract. All joints in the selected lines must
`be re—tested and any joints which fail must be
`resealed at the contractor’s expense. If 5% or
`more of the tested joints fail, the contractor
`must continue to test and seal until at least
`
`95% of the total joints tested pass the test, By
`making these tests during the eleventh month,
`the quality of the job may be varified before
`the warranty expires.
`
`Variables Which Affect the Difficulty
`of Joint Sealing
`
`Many variables can impact a contractor’s
`performance, production, and cost on any
`particular test/seal job. Some of these variables
`follow:
`
`1. Locating and exposing manholes and
`removing manhole covers.
`
`2. Terrain, traffic, and other impediments to
`accessing manholes.
`
`3. Condition of manholes (steps, cleanliness,
`and structure).
`
`4. Condition of the sewer (debris, roughness,
`and porosity of a pipe can prevent proper
`operation of a sealing packer).
`
`5. Depth of the sewer line (difficulty and safety
`of entry).
`
`6. Depth and velocity of sewage flow.
`
`7. Availability of water for threading the sewer
`line.
`
`8. Plugging requirements (ability to plug or
`necessity to bypass).
`
`9. Presence of explosive gas or combustible
`liquid.
`
`10.0ffset joints, intruding joint materials or
`service connections, curved or crushed pipe
`or other obstructions which could prevent
`the passage of a camera/packer
`combination.
`
`11. Cleanliness of the pipe invert and the
`presence of roots, grease, or other debris
`which could foul the camera lens or prevent
`the packer sleeves from seating properly on
`the pipe.
`
`12. Size of the pipe affects ease of entry into
`the pipeline and the amount of chemical
`grout that is used.
`
`13.The cost of sealing is sensitive to the number
`of setups required.
`
`14.Weather (rain and snow lower production
`rate, and snow hides manholes).
`
`Groundwater Pressure Formula
`
`In the absence of groundwater pressure data,
`the pressure may be determined by inflating
`a packer on an active leak and measuring the
`resulting pressure in the packer void. A safe
`"rule-of-thumb” is to use a pressure setting
`equal to 1/2 psi per vertical foot of pipe depth
`or 3 psi, whichever is greater. Unless the soil
`is saturated with water up to the surface, 1/2
`psi per vertical foot will be greater than the
`groundwater pressure outside the pipe.
`
`In general practice, 10 psi is used for the
`packer void pressure. Some test/seal packers
`cannot retain much more than 10 psi in the
`packer void without leaking (blowby). The
`actual pressure which can be held is determined
`by pipe cleanliness, surface roughness of the
`pipe, packer sleeve material, and the inflation
`pressure used.
`
`10
`
`10
`
`

`
`11
`
`TYPICAL EQUIPMENT USED TO TEST AND SEAL JOINTS IN SEWER LINES
`
`Pressure Gauge or
`Digiiai Readout
`
`.
`
`«v--—~--—v~-r---4»~--'~«--I---v~--w'--v-—
`
`"1
`
`\\\\‘
`
`lll//
`
`:
`
`W
`
`L... _,,
`
`Packer
`Void
`
`Packer
`Packer
`Sleeve Wheels
`
`Hollow Packer
`Core
`Pad
`
`Chemical Pressure Pressure
`Injection
`Sensor
`Sensor
`Fons 2
`Element
`Line
`
`L .:;i
`
`Sleeve Pressure Chemical Chemical
`Air Line TeLsil Air
`‘A’ Line
`'8' Line
`ne
`
`TYPICAL BARREL TEST
`
`
`
`
`Digital Readout or Gauge
`for Void Pressure on
`Controi Panel
`
`Packer Void
`
`11
`
`

`

`
`‘
`
`T
`
`/,\I'5‘ I'AVA'\
`uni
`
`USA
`
`21 Long Pond Road
`Jackman, ME 04945
`Tel: 800-246-5988
`Fax: 418-653-5746
`
`info@|ogibalI.com
`
`Canada
`
`440 Papin Street
`Quebec, QC G1P 3T9
`Tel: 418-656-9767
`Fax: 41 8-653-5746
`
`info@logiba|l.com
`
`www. Iagiball. com
`
`12

This document is available on Docket Alarm but you must sign up to view it.


Or .

Accessing this document will incur an additional charge of $.

After purchase, you can access this document again without charge.

Accept $ Charge
throbber

Still Working On It

This document is taking longer than usual to download. This can happen if we need to contact the court directly to obtain the document and their servers are running slowly.

Give it another minute or two to complete, and then try the refresh button.

throbber

A few More Minutes ... Still Working

It can take up to 5 minutes for us to download a document if the court servers are running slowly.

Thank you for your continued patience.

This document could not be displayed.

We could not find this document within its docket. Please go back to the docket page and check the link. If that does not work, go back to the docket and refresh it to pull the newest information.

Your account does not support viewing this document.

You need a Paid Account to view this document. Click here to change your account type.

Your account does not support viewing this document.

Set your membership status to view this document.

With a Docket Alarm membership, you'll get a whole lot more, including:

  • Up-to-date information for this case.
  • Email alerts whenever there is an update.
  • Full text search for other cases.
  • Get email alerts whenever a new case matches your search.

Become a Member

One Moment Please

The filing “” is large (MB) and is being downloaded.

Please refresh this page in a few minutes to see if the filing has been downloaded. The filing will also be emailed to you when the download completes.

Your document is on its way!

If you do not receive the document in five minutes, contact support at support@docketalarm.com.

Sealed Document

We are unable to display this document, it may be under a court ordered seal.

If you have proper credentials to access the file, you may proceed directly to the court's system using your government issued username and password.


Access Government Site

We are redirecting you
to a mobile optimized page.





Document Unreadable or Corrupt

Refresh this Document
Go to the Docket

We are unable to display this document.

Refresh this Document
Go to the Docket