throbber
SUMMER PEAKiNG CAPACITY VIA CHILLED WATER STORAGE COOLING OF
`COMBUSTION TURBINE INLET AIR
`
`JOHN S. ANDREPONT
`Product Manager - Thermal Systems
`Chicago Bridge & Iron Company
`
`SANDRA L. STEINMANN
`Design Engineer
`CBI Technical Services Company
`Plainfield, fiIinoi.
`
`ABSTRACT
`
`The relationship of Combustion Turbine (CT) capacity to
`inlet air temperature is briefly presenterl, illustrating the
`value of inlet air cooling. Various inlet air cooling
`tC(:hnologies are described including the use of several
`oommercially available cool storage technologies. The pros
`and cons of each cooling option are summarized to illustrate
`tile types of design conditions likely to jnstify the economic
`application of each technology.
`
`The use of chilled water storage for CT inlet air cooling is
`described in detail. Potential applications for utility and
`non-utility CTs, for new and existing CTs. and for
`oombined cycle as well as simple cycle CTs are all
`illustrated. The results of a detailed technical and economic
`analysis of a specific utility application are reviewed. The
`findings include a net summer peaking capacity increase in
`CT plant output of 20%, a heat rate reduction of 5%, and a
`unit capital cost for the incremental capacity of roughly
`50% that of new simple cycle CT capacity.
`
`CTPERFORMANCE VERSUS TEMPERATURE
`
`It is. a common occurrence for summer-peaking or dual(cid:173)
`i"cl<lllg electric utilities, that peak demand for electric load
`"',"Cldes closely with periods of peak ambient air
`Itlllperatures. Therefore it is generally at such times that
`%illlple cycle combustion turbines (CTs) are dispatched to
`~Vldc peaking power. However, it is a characteristic of
`l>it~ that their rated power output decreases significantly
`" Increasing ambient air temperature. This is due to the
`1llllbthat the lower density air entering the CT at high
`lent temperatures results in a reduction in turbine mass
`""illlbu as well as in the flow of oxygen available Jot
`Iil<Jst stlon. The result is that when peaking capacity is
`1Il demand'
`.
`IS preclsely when CT capacity is most
`~erel '
`) derated. See Figure 1.
`
`FIGURE 1 - TYPICAL CT PERFORMANCE
`
`110
`
`100
`
`90
`
`80
`
`70
`
`60
`40
`
`%
`
`HEAT RATE
`
`CAPACITY
`
`60
`
`80
`
`100
`
`INLET AIR TEMP (OF)
`
`Various approaches can be employed for the cooling of CT
`inlet air.
`They
`include:
`evaporative, absorption,
`mechanical compression, and cool storage cooling. Each
`technology has its pros and cons, its concerns or limitations.
`Evaporative cooling can provide capacity at a low unit
`capital cost; however, it is limited by the ambient wet bnlb
`air
`temperature
`(thus offering only modest capacity
`the availability of large
`enhancement) and
`requires
`quantities of water (often mlavailable in dry climates where
`the technology would be most advantageous). Absorption
`cooling can utilize available waste heat from CT or CTCC
`(CT Combined Cycle) exhaust gases, as its input energy;
`however, both exhaust gas heat exchangers and absorption
`cooling equipment itself are capital intensive. Mechanical
`compression
`refrigeration
`systems
`are
`commercially
`available and can be specifically selected to snit any desired
`inlet air temperature; however, they too have high capital
`cost (associated with the high cooling capacities required)
`and typically will consume 30 percent or more of the
`incremental CT output in their own parasitic energy
`requirements.
`
`The addition of thermal energy storage to a non-storage CT
`cooling system provides the owner with several benefits. It
`allows downsizing of
`the
`refrigeration
`equipment,
`significantly decreasing capital costs; and it gives the added
`benefit of de-coupling the parasitic use of large refrigeration
`equipment from the real-time, on-peak need for CT inlet air
`cooling.
`
`FOR CT INLET AIR COOLING
`
`of CT inlet air is desirable during periods of
`peak d'
`th
`lSpatch, typically 4 to 6 hours per day.
`IIIO~Fse penods, ambient inlet air, at temperatures of
`orrno
`'d '
`i
`re, IS eSirably cooled to the 40 to 50°F
`, .c. cool en h '
`.
`.
`but
`oug
`to achIeve substantial CT capacIty
`Within ~t so cool as to initiate potentially damaging
`CT Inlet from the resultant condensation.
`
`Cool storage, also known as thermal energy storage (TES)
`involves the cyclical heating and cooling of a thermal mass
`or heat storage medium. Typically during periods of peak
`cooling demand, heat is rejected to a storage medium such
`as water or ice (thus heating the water or melting the ice);
`during subsequent off-peak periods, refrigeration is utilized
`to regenerate storage (i.e. recooling the water or refreezing
`the ice).
`
`1345
`
`Page 1 of 6
`
`GE Exhibit 1006
`
`

`

`II""
`
`(i '
`
`Such cool storage systems have been widely applied in air(cid:173)
`conditioning or process cooling applications in the 1980's
`and 1990's. Systems can be designed such that storage is
`used for 100% of the peak cooling load ("full storage") or
`for less than the full load ("partial storage"). Systems can
`also be designed to operate as daily cycles (which are fully
`charged and discharged in 24 hours) or as weekly cycles
`(which are fully charged during off-peak weekend periods
`and partially discharged and recharged cyclically during
`Monday through Friday).
`
`During the on-peak operation of the CTs cold
`wate .
`'
`pumped from the bottom of the thermally stratw' 1 d
`r Ii
`e cilill~
`.
`water storage tank to the au coolers. The cold w t
`'"
`a
`the hot, hmnid air approaching the CT' wann
`er COOls
`.
`'
`water <
`returoed to the top of the tank while cool air enters til
`IS
`increasing CT output and performance. During ofI~ CT,
`periods, warm water is removed from the top of the ~
`.Ilk.
`pumped to and chilled by the refrigeration system
`returned to the bottom of the tank for use during th' dnd
`e nex1
`on-peak period.
`
`Either chilled water or ice is an appropriate storage medium
`to consider for CT cooling. Ice storage temperature is 32°F
`(with typical melt water temperatures varyiog during
`discharge in the range of 33 to 44°F, depending on the type
`of ice storage equipment used, the rate of ice melting, and
`the amount of ice remaining urunelted); chilled water
`storage temperatures are practical down to 39°F (with a
`typical and constant discharge water temperature of 40°F
`being sustainably achieved throughout the discharge cycle).
`Another consideration is the space requirement for the
`storage medium.
`
`Although not usually the case for conventional air(cid:173)
`conditioning applications, full storage designs are both
`practical and appropriate for CT cooling due to the
`relatively short periods of peak CT dispatch. Either daily or
`weekly cycles can be appropriate choices for CT cooling,
`unless the utility expects to dispatch the CT on weekends as
`well as Monday through Friday; if so, a daily cycle would be
`the preferred design option.
`
`For each distinct utility application, various combinations of
`storage media (chilled water and ice) and cycle design
`In addition,
`(daily and weekly) should be considered.
`consideration should be given to the use of existing fuel oil
`tanks (available at some sites) as well as to the use of new
`cool storage tanks (necessary at most sites). All cases must
`consider the required number of hours per day of CT
`dispatch, Monday
`through Friday, and Saturday and
`Sunday. At the original prototype application of cool
`storage CT cooling, the design basis was four hours per day;
`but this value may be more or less at other sites.
`
`TIlE CHILLED WATER STORAGE SYSTEM
`
`Commercially available components can be integrated to
`The basic
`provide storage cooling of CT iulet air.
`configuration, illustrated in Figure 2, utilizes a patented
`chilled water thermal energy storage system with a
`conventional HFC or NH3 mechanical refrigeration, 'system
`and a cooling tower for heat rejection. (Note however, that
`an inherent flexibility of chilled water storage is that any
`water chilling technology, including absorption chilling,
`could be used to accomplish the recharge.)
`
`Figure 2 represents a design for a new cool stora
`installation applied to existing utility simple cycle c;C
`The technology is of course readily applied to cogeneratio~
`or independent power producer (IPP) CTs, as well as 1
`electric power utility CTs. Furthermore, cool storage ~
`inlet air cooling can be applied concurrently with lhe
`installation of new CTs, as well as in retrofits with eXisting
`CTs.
`Interestmgly, the technology IS also well sui led to
`CTCCs, even to those which are base loaded. Wherever
`there is a value to electricity which varies with the time of
`day (i.e. in virtually all situations), cool storage inlet air
`cooling can be dispatched as a peaking technology on top of
`the base load capacity of the CT or CTCC. For CTCe
`applications, although the inlet air cooling of the CT
`reduces the temperature of the CT exhaust, this is a lesser
`impact than the increase in exhaust gas mass flow. The
`result is an increased output potential in the steam turbine
`as well as in the CT itself.
`
`ANALYSIS AND RESULTS OF A SPECIFIC
`APPLICATION
`
`The design basis and assumptions were chosen by a host
`utility for evaluation of both chilled water storage and ice
`storage CT iulet air cooling. A specific site and ils six
`existing CTs (each roughiy 50 MW nominal outpul at
`summer design conditions) were the basis of a relrofit
`analysis. Two of three existing fuel oil storage tanks were
`considered for possible conversion to cool storage service;
`new storage tanks were also considered. Ice-an-coil (stalic
`ice) storage, ice harvester (dyoamic ice) storage, and chilled
`water storage were all considered. An initial analySIS
`narrowed the selection to the four confignrations wilh the
`best potential for low capital cost. The economies of scale
`(significant for relatively large applications) and
`the
`possible use of the existing fuel oil tanks led the utility and
`the independent evaluator to eliminate the static ice oplion'
`.
`.
`A single
`from the short hst of final confignratlOns.
`.
`confignration was chosen as a base case for detailed des~
`and cost estimating; budgetary costs were then develo
`for the three remaining configurations. The subsequent
`analyses contrasted storage media, weekly vs. daily cycles.
`and new vs. retrofit tanks.
`
`. D r lhe baS<
`The system design and equipment selectIOn 0
`1I
`case were developed in detail by analysis of the overa
`
`1346
`
`Page 2 of 6
`
`GE Exhibit 1006
`
`

`

`Gi)£IIATC5I
`
`el·S
`
`AIR COOLER
`
`~,
`
`AIR COOLER
`
`(El£MT<Jl
`
`en
`
`IDERAI~
`
`CH
`
`AIR COOLER
`
`~.
`
`AIR COOLER
`
`AIR COOLER
`
`IlOEPATC5I
`
`CT -2
`
`~-,
`
`AIR COOLER
`
`IlJ(AAT~
`
`CH
`
`~-,
`
`______________________ CJ
`,
`
`:£_------
`
`I ~ I COOLING
`
`E-l
`TOWER
`
`CHILLER PACKAGE
`
`I"F-
`
`-F;
`
`F
`
`PUMPS
`
`CHILLED '&lATER
`
`STORAGE TANK
`CHILLED \lATER
`
`STRATIFIED
`THERMAllY
`
`T -1
`
`FIGURE 2 -FLOW SCHEMATIC -CT INLET AIR COOLING SYSTEM -DAILY CYCLE WITH NEW TANK
`
`"
`-(cid:173)
`............ ~ ~_ "" U) P. ""
`;:~-(!)()""l:5::::::"""
`
`'" >-l ---
`
`l< 1'1-
`
`"
`
`gf."~
`;::t.~~
`
`~
`
`c.:I~(1)SJgn-'lo
`t:;. --, .....
`$I! "''''-5''"'_
`
`-
`
`...,>--3(")9.,
`'" ~ n (=5>5
`
`S'::j
`
`" - o
`
`0
`
`~,......;.:n;!l
`e> ~. n' 0
`o
`a~ ~:::­
`
`_ _. ('1> -. n
`.....
`
`_
`tTl-
`
`::In".,o..n",,,,,,,o..n~·'"
`-.
`;:::;. J:;:.~' < ::;:!
`
`_
`
`_ ~ __
`
`-~ "'i -. g $2 e c:. g c:. ~ = g 0-~
`v. ~ IJ'e
`'6,;0 6'-g ...... a -..
`
`.-
`
`, .
`
`'-I
`.j:>.
`IN
`
`~
`
`~ ~ = ~
`a cr
`
`Page 3 of 6
`
`GE Exhibit 1006
`
`

`

`process as several major subsystems, plus controls and
`instrumentation, and auxiliary systems. Each system is
`designed to provide inlet air cooling 6 hours per day,
`Monday through Friday. Key design differences between
`the base case and the three alternative configurations were
`flow
`the development of process
`evaluated
`through
`schematics, equipment layouts, plot plans, and turnkey cost
`estimates. Surprisingly, whether ice or water storage is
`employed, similar site layouts apply, including the storage
`volume and footprint; water storage volume was minimized
`through the use of a daily (rather than weekly) cycle and a
`large
`chilled water
`supply-to-return
`temperature
`differential. The required storage volumes for the chilled
`water storage options were actually slightly less than the
`volume for the ice storage option.
`
`Operation and Maintenance issues and requirements were
`considered; and contrasts between the configurations were
`identified. Although the ice storage systems were somewhat
`more complex, no unusual O&M issues were identified for
`any ofthe cases studied.
`
`A detailed analysis of system performance was performed
`for each of the four configurations under study; results (see
`Table 1) were quantified for the following:
`
`•
`•
`•
`•
`
`off-peak power and energy for recharging storage,
`on-peak increases in CT power and efficiency,
`on-peak parasitic power and energy consumed, and
`net power increases for the entire CT facility.
`
`Key points of contrast include the fact that the 40°F inlet air
`temperature achieved with ice storage provides a net facility
`power increase of 66.46 MW (21.5%) after discounting for
`inlet pressure drop and parasitics, while the 46°F achieved
`with water storage pro,ides 58.95 MW (19.1%). However,
`the ratio of off-peak electric consumption (kWh in per
`week) to on-peak incremental electric production (kWh out
`per week) is 0.53 for ice storage versus only 0.31 for water
`storage (see Table 2).
`
`The scope of supply which has been analyzed and cost(cid:173)
`estimated is based on firm fixed-price supply of a total
`turnkey design-build installation. The turnkey schedule is
`competitive with CT procurement;
`and permitting
`requirements are likely to be less than those for other
`peaking capacity additions.
`
`A detailed total price was developed for the base case, as
`were budgetary
`total prices
`for
`the other
`three
`configurations. Other factors which impact price were
`identified and evaluated, not the least of which is the
`number of hours per day for CT operation. Realistically
`achievable target price ranges were developed (see Table 3).
`For the specific site under analysis, the median unit costs
`are as follows:
`
`Hours of CT Cooling per Day
`W1dy Ice Storage with Retro Tank
`Daily Water Storage with Retro Tank
`Daily Water Storage with New Tank
`
`6
`$30iikw
`239
`269
`
`4
`$2721kW
`209
`239
`
`Major conclusions of the evaluation are significant E'
`ice or water storage provides capacity at unit C~st Ithcr
`. '
`sWell
`below
`those assOCiated WIth new CT
`installat'
`However, the incremental cost of ice versus water st;ons"
`(for the increment of increased output) is $750 to 800~~
`as shown in Table 3. The findings are in agreement
`.
`an independent study which recently analyzed sir~~th
`applications.
`I ar
`
`CONCLUSIONS
`
`The findings of this evaluation, although specific to the
`particnlar application analyzed here, are in agreement With
`the results of another, independent study listed in the
`bibliography.
`All
`the
`technologies considered are
`technically feasible for application as CT Inlet Air Cooling
`Systems. No technology developments are necessary, as the
`systems will employ hardware of a type and size already in
`use in commercial, industrial, or utility applications.
`
`Static ice storage technology (such as ice-an-coil or
`encapsulated ice storage systems) was not found to be
`capital cost competitive with either dynamic ice storage
`technology
`(ice harvester) or chilled water storage
`technology for
`this particnlar CT Inlet Air Cooling
`application, due to the economies of scale associated with
`relatively large storage applications (and due to the possible
`use of the existing fuel oil tanks). For ice harvester
`applications, weekly design cycles will be more cost
`effective than will daily design cycles. For chilled water
`storage applications, the converse is true: daily cycles will
`be preferred. One net resnlt is that when comparing the
`optimum choice for
`ice storage systems (weekly
`ice
`harvesters) with the optimum choice for water storage
`systems (daily chilled water storage), the required storage
`volumes are virtually identical, with water storage actually
`reqniring slightly less volume.
`
`Either water or ice storage systems will provide ve~'
`substantial CT output
`increases for summer peaking
`operation (roughly 20% as analyzed for the 6 existing CTs
`at the installation studied here). If a particular ice storage
`system design can provide a supply of low temperature
`water (e.g. 34°F, versus 40°F for chilled water storage) and
`if the CT manufacturer allows operation with inlet arr
`conditions of 100% R.H. at temperatures below 45'F, thell
`ice storage systems can offer modestly larger outp~t
`increases than can water storage systems. Hmvever, tlu~
`additional incremental output comes only with adde
`system complexity and at a substantial cost increase.
`
`1348
`
`,
`
`.Q!I
`Sto
`eyl
`Tali
`.Qg!
`bas
`inc
`dec'
`net
`net
`on(cid:173)
`net
`~
`
`£m
`Sto
`Cyr
`Tar
`
`Off
`•
`•
`•
`•
`Opr
`Off
`
`On·
`Opr
`On·
`
`Off.
`
`~ eyel
`
`Tani
`
`&t
`Med
`Pow
`Unit
`!Jnit
`
`Ill£!
`Capi
`Pow
`Unit
`!Jnit
`
`Page 4 of 6
`
`GE Exhibit 1006
`
`

`

`"er
`'ell
`ns.
`1ge
`,w
`itll
`lar
`
`the
`ith
`the
`are
`ing
`the
`in
`
`or
`be
`1ge
`Ige
`,ng
`itb
`ble
`ter
`osl
`tee
`lill
`ne
`ice
`Igc
`19o
`Ily
`
`Configuration
`storage Type
`Cycle Type
`Tank Type
`On-Peak Callarity rMWl
`base per CT (@95°F)
`increase (due to L\ T)
`decrease (due to L\P)
`nct increase per CT
`net increase for 6 CTs
`on-peak parasitics
`net increase for facility
`% increase for facility
`
`TABLE 1 - NET FACILITY POWER INCREASES
`
`A
`Chilled Water
`Weekly
`Retrofit
`
`B
`Chilled Water
`Daily
`Retrofit
`
`C
`Chilled Water
`Daily
`New
`
`D
`Ice Harvester
`Weekly
`Retrofit
`
`51.4
`+10.0
`- 0.14
`+9.86
`+59.16
`- 0.21
`+58.95
`+19.1
`
`51.4
`+10.0
`- 0.14
`+9.86
`+59.16
`- 0.25
`+58.91
`+19.1
`
`51.4
`+10.0
`- 0.14
`+9.86
`+59.16
`- 0.21
`+58.95
`+19.1
`
`51.4
`+11.3
`- 0.14
`+11.16
`+66.96
`- 0.50
`+66.46
`+21.5
`
`TABLE 2 - OFF-PEAK CONSUMPTION VERSUS ON-PEAK NET PRODUCTION
`
`Configuration
`Storage Type
`Cycle Type
`Tanle Type
`
`A
`Chilled Water
`Weekly
`Retrofit
`
`B
`Chilled Water
`Daily
`Retrofit
`
`C
`Chilled Water
`Daily
`New
`
`D
`Ice Harvester
`Weekly
`Retrofit
`
`Off-Peak Capacity (kW)
`• Chillers
`• Wann Water Pumps
`• Cooling Tower Pumps
`• Cooling Tower Fans
`• Total
`Operating Time (hrs/wk)
`Off-Peak Energy (kWh/wk)
`
`3,741
`44
`127
`---ID
`4,079
`x 138
`562,902
`
`On-Peak Net Power (kW)
`Operating Time (hrsiwk)
`OO-Peak Net Energy (kWh/wk)
`
`58,950
`x30
`1,768,500
`
`Off-PeakiOn-Peak Ratio
`
`0.318
`
`5,663
`127
`127
`---ID
`6,084
`x90
`547,560
`
`58,910
`x 30
`1,767,300
`
`0.310
`
`5,663
`52
`207
`207
`6,129
`x90
`551,610
`
`58,950
`x30
`l, 768,500
`
`0.312
`
`6,921
`207
`246
`---.11i
`7,649
`x 138
`1,055,562
`
`66,460
`x 30
`1,993,800
`
`0.529
`
`TABLE 3 - NET INCREMENTAL COST OF POWER
`
`~uration
`CT Operation (ms/day)
`Storage Type
`CYcle Type
`Tank TyPe
`
`&u:ncreases
`~edian Target Price ($ x 10')
`\ olVer Output (MW)
`Unit Cost ($/jeW)
`Unit Cost ($/kWhiday)
`~entvs.B
`p Plta\ Cost ($ x 10')
`U":" Output (MW)
`Unit Cost ($/kW)
`~Cost ($/kWhiday)
`
`A
`6
`CHW
`Wkly
`Retro
`
`15.0
`58.95
`255
`42.5
`
`-
`-
`-
`-
`
`B
`6
`CHW
`Daily
`Retra
`
`14.1
`58.91
`239
`39.8
`
`-
`-
`-
`-
`
`D
`6
`I. H.
`Wkly
`Retro
`
`20.1
`66.46
`302
`50.3
`
`6.0
`7.55
`795
`133
`
`C
`6
`CHW
`Daily
`New
`
`15.9
`58.95
`269
`44.8
`
`-
`-
`-
`-
`
`1349
`
`A
`4
`CHW
`Wkly
`Retro
`
`13.3
`58.95
`225
`56.3
`
`-
`-
`-
`-
`
`B
`4
`CHW
`Daily
`Retro
`
`12.3
`58.91
`209
`52.3
`
`-
`-
`-
`-
`
`C
`4
`CHW
`Daily
`New
`
`14.1
`58.95
`239
`59.8
`
`-
`-
`-
`-
`
`D
`4
`I. H.
`Wkly
`Retro
`
`18.1
`66.46
`272
`68.0
`
`5.8
`7.55
`768
`192
`
`Page 5 of 6
`
`GE Exhibit 1006
`
`

`

`Either water or ice storage systems can provide summer
`peak capacity increases at unit capital costs well below
`those of conventional new CT installations. However, for
`the present application, the incremental cost of ice storage
`(associated with the incremental output increase due to the
`slightly lower inlet air temperature of ice versus water
`cooling) is in the range of $750 to 800/kW. This is
`typically an unjustifiable amount compared to the cost of
`either conventional new CT capacity or a combination of
`new CTs with chilled water storage cooling.
`
`Additional inherent differences between the subject chilled
`water storage and ice harvester systems were evident:
`
`systems
`
`•
`
`•
`
`•
`
`•
`
`•
`
`reqnire
`
`smaller
`
`the water storage systems do not reqnire chiller
`eqnipment specifically snited for low temperature
`operation;
`storage
`the water
`refrigerant charges;
`the water storage systems are less complex, with
`fewer refrigeration system components and less
`refrigerant piping;
`the water storage systems consume approximately
`40% less off-peak energy (per unit of net on-peak
`energy produced); and
`the water storage systems will likely incur lower
`O&Mcosts.
`
`Cool storage capacity enhancement can be us d
`dispatchable peaking technology either with sim el as a
`CTs or with CT Combined Cycles (CTCCs). T~ e CYcle
`Cool Storage CT lulet Air Cooling is an econo~ ute of
`technically proven option for CT capacity enhance~a and
`should not be overlooked by utilities when procurent. It
`lUg or
`planning for summer peaking capacity additions.
`
`BmLIOGRAl'HY
`
`Chicago Bridge &
`Iron Company, Enginee .
`Specification for a Cool Storage System, CB! ST -o~~
`Oak Brook, IL, Augnst 1992.
`'
`
`Chicago Bridge & Iron Company, Technical and EconOmic
`for NSF
`Evaluation of Cool Storage Options
`Combustion Turbine Inlet Air Precooling. Oak Brook,
`IL, September 1992.
`
`Ebeling, Jerry A., Combustion Turbine lulet Air Cooling
`With Thennal Energy Storage, Burns & McDonnell
`Engineering Company, Power-Gen '91, Tampa, FL,
`December 1991.
`
`Stovall, Therese K., Baltimore Aircoil Company (!lAC) Ice
`Storage Test Report, Oak Ridge National Laboratory
`(ORNLfTM-I1342), Oak Ridge, TN, March 1991.
`
`Either water or ice storage systems can be procured as total
`The
`lumpsum
`turnkey design-bnild
`installations.
`construction schedule is competitive with the procurement
`of new CT capacity. Permitting reqnirements should be less
`(possibly a lot less) than for alternative new capacity
`additions. Optimization of system design and capital cost
`for each specific site will reqnire the perfonnance of
`detailed and knowledgeable
`trade-off analyses.
`The
`optimum technology (or air temperature) for one application
`may be qnite different from the optimum choice for another
`application.
`
`Cool storage technology is equally applicable as a retrofit
`for existing CTs or as an
`capacity enhancement
`enhancement procured concurrently with new CT capacity.
`
`Stovall, Therese K., Calmac Ice Storage Test Report, Oak
`Ridge National Laboratory (ORNLfTM-IlS82), Oak
`Ridge, TN, Augnst 1991.
`
`Stovall, Therese K., Turbo Refrigerating Comoanv Ice
`Storage Test Report, Oak Ridge National Laboratory
`(ORNLfTM-1l6S7), Oak Ridge, TN, June 1991.
`
`Zwillenberg, M.L., et al, Assessment of Refrigeration-Typ<l
`Cooling of Iulet Air for Essex Unit No.9, Public
`Service Electric and Gas Company, Electric Power
`Research
`Institute,
`and
`Joseph
`Technology
`Corporation, Inc., ASME Paper No. 91-JPGC-GT-4,
`International Power Generation Conference, San
`Diego, CA, October 1991.
`
`Al!stract
`A review (
`j)lJtor resea
`~ications
`""totype I11
`~shave b
`}¥J1Chronoil!
`Ji;monstrate
`IIl'S field v
`!!o<luced a
`Measured H
`lood
`is p
`1ijllJonstrat\
`
`Inlrodueli'
`The 1987 I
`(IlTS) mate
`1IljlCrcondu
`wpcrcondu
`vl'liquid r
`IjlOrating t
`previous s
`@ling at
`fIlIintain t
`wpcrcondt
`(\)~s prm
`reonornica:
`lilIlgawatts
`ilIousands
`
`iIltliancc E
`!!egan a
`mibility
`ttl~lerials
`!he synd
`winding
`~nmcrci1
`Will have
`I!llhe sta
`lilIor, n
`1(;00 hpj
`1Ij)craled ~
`~!ergy sa
`lJllllicatio
`
`llIe expc
`~ciency
`IIF a dire
`ll1.l\{jing I
`
`Page 6 of 6
`
`GE Exhibit 1006
`
`

This document is available on Docket Alarm but you must sign up to view it.


Or .

Accessing this document will incur an additional charge of $.

After purchase, you can access this document again without charge.

Accept $ Charge
throbber

Still Working On It

This document is taking longer than usual to download. This can happen if we need to contact the court directly to obtain the document and their servers are running slowly.

Give it another minute or two to complete, and then try the refresh button.

throbber

A few More Minutes ... Still Working

It can take up to 5 minutes for us to download a document if the court servers are running slowly.

Thank you for your continued patience.

This document could not be displayed.

We could not find this document within its docket. Please go back to the docket page and check the link. If that does not work, go back to the docket and refresh it to pull the newest information.

Your account does not support viewing this document.

You need a Paid Account to view this document. Click here to change your account type.

Your account does not support viewing this document.

Set your membership status to view this document.

With a Docket Alarm membership, you'll get a whole lot more, including:

  • Up-to-date information for this case.
  • Email alerts whenever there is an update.
  • Full text search for other cases.
  • Get email alerts whenever a new case matches your search.

Become a Member

One Moment Please

The filing “” is large (MB) and is being downloaded.

Please refresh this page in a few minutes to see if the filing has been downloaded. The filing will also be emailed to you when the download completes.

Your document is on its way!

If you do not receive the document in five minutes, contact support at support@docketalarm.com.

Sealed Document

We are unable to display this document, it may be under a court ordered seal.

If you have proper credentials to access the file, you may proceed directly to the court's system using your government issued username and password.


Access Government Site

We are redirecting you
to a mobile optimized page.





Document Unreadable or Corrupt

Refresh this Document
Go to the Docket

We are unable to display this document.

Refresh this Document
Go to the Docket