throbber
THE APPLICATION OF THERMAL ENERGY STORAGE
`FOR DISTRICT COOLING AND COMBUSTION TURBINE INLET AIR COOLING
`
`KelUleth M. Clark, P .E.
`and
`Jerry A. Ebeling, P .E.
`Bums & McDonnell Engineering Company
`Kansas City, Missouri
`and
`Edward Godwin, P .E.
`Reedy Creek Energy Services
`Lake Buena Vista, Florida
`
`ABSTRACT
`
`The use of thermal energy storage is a proven and accepted technology for both district cooling
`and combustion turbine inlet air cooling. However, the two applications may never have been
`previously combined in a single project. Reedy Creek Improvement District is realizing the
`synergies available from this combination with their chilled water thermal storage project. This
`paper will discuss the modifications of an existing 20,000 ton district chilled water cooling
`system and 3 8 MW e combined cycle power plant to incorporate a chilled water thermal energy
`storage system for both comfort air-conditioning and gas turbine inlet air cooling. These
`modifications provide improvements to production, reliability, and economic performance. The
`conceptual and final design process will also be presented.
`
`KEYWORDS: Thermal Energy Storage, Turbine-Inlet Cooling, Chilled Water
`
`INTRODUCTION
`
`Reedy Creek Improvement District (RCID) is a municipal entity that services the utility needs of
`the Walt Disney Company in Florida. The RCID owns several utility systems including electric,
`gas, chilled water~ hot water, potable water, and sanitary sewer. The RCID Central Energy Plant
`serves the various needs of the Walt Disney World Resort. Reedy Creek Energy Services
`(RCES) is a private corporation providing design, build, operation and maintenance contract
`services to RCID for its utility systems.
`
`RCID and RCES recently modified the RCID Central Energy Plant. The modifications include
`the addition of a new chilled water thermal storage system and a new combustion turbine inlet air
`cooling system. The project also includes the addition of a new carbon monoxide (CO) catalyst
`
`85
`
`Page 1 of 13
`
`GE Exhibit 1005
`
`

`

`MAGIC KINGDOM
`Lake
`
`SCALE = 1" =2000'
`2000'
`I
`I
`GRAPHIC SCALE
`
`TES SITE
`FIGURE 1
`
`86
`
`Page 2 of 13
`
`GE Exhibit 1005
`
`

`

`·a
`-+----· - - - - -
`·-·-----
`
`
`
`' f , .-.1
`
`
`
`~-
`
`
`
`«$23.7.Wv.a;
`
`,.o.}''
`
`1
`
`
`
`SITE PLAN
`FIGURE 2
`
`Page 3 of 13
`
`GE Exhibit 1005
`
`87
`87
`
`Page 3 of 13
`
`GE Exhibit 1005
`
`

`

`system on the turbine exhaust. These modifications will provide improvements to the
`production, reliability, and economic performance of the Central Energy Plant..
`
`EXISTING FACILITIES
`
`The RCID Central Energy Plant is an integrated energy production and distribution facility
`located one-half mile north of the Walt Disney World (WDW) Magic Kingdom Theme Park.
`(See Figure 1 and 2). The plant is a cogeneration facility consisting of a nominal32 MW
`General Electric LM5000 gas turbine generator, a three-pressure level 90,000 pph Vogt heat
`recovery steam generator (HRSG) and a nominal 8.5 MW Elliott extraction-condensing steam
`turbine generator. Steam from the HRSG is supplied to absorption chillers and a hot water
`system.
`
`A high temperature hot water district heating system provides 350 degree water to several WDW
`facilities. Production is normally supplied by steam from the HRSG by a steam-to-hot water heat
`exchanger. Back up supply capability is provided by a dual-fuel hot water generator.
`
`A chilled water district cooling system provides 40 to 44 degree F water to the WDW Magic
`Kingdom theme park and area resorts. The chiller plant consists of 2 absorption chiller and 9
`electric motor driven centrifugal chillers with a total deliverable capacity of 17,500 tons. Chilled
`water is distributed to customers by two piping loops.
`
`PROJECT OBJECTIVE
`
`RCID was in need of replacing two electric centrifugal chillers. In addition they were seeking to
`reduce cooling energy costs and improve the efficiency and capacity of their gas turbine
`generator. Therefore, within the scope of this project are the following objectives:
`
`*
`
`*
`
`*
`
`Eliminate the need of replacing two chillers with 3325 tons of capacity. The
`chillers use CFC refrigerants and operated at efficiency's that were low compared
`to today' s standards.
`
`Generate cooling during low energy cost periods and store the chilled water for
`peak load periods.
`
`Provide cooling to the existing gas fired turbine-generator to enhance the
`performance of the turbine.
`
`88
`
`Page 4 of 13
`
`GE Exhibit 1005
`
`

`

`To meet these objectives, the owner elected to develop the project in a design/build arrangement.
`The first step was to retain a consultant to develop the "scope documents" so that competitive
`design/build proposals could be obtained. The scope documents contained a description of the
`components, capacities and design criteria required for the project. A detailed description of the
`site development, control schemes, tank storage criteria and turbine-inlet-cooling requirements,
`component specifications were included in the scope documents.
`
`Competitive bids were obtained and the contract was awarded to the successful bidder. The
`bidders were given some latitude to develop the best, cost-effective design and proposal. The
`project was completed in April of 1998.
`
`CHILLED WATER SYSTEM
`
`Eleven chillers in the north Central Energy Plant (CEP) chiller building and two chillers in the
`Contemporary Hotel provide total sustainable cooling of 17,750 tons which supplies the Magic
`Kingdom and several hotel/resort complexes. The sustainable capacity is defined as the amount
`of tonnage the chillers are estimated to be capable of sustaining for more than one hour. The
`chillers in the CEP are separated into two groups, the West Chiller Group and the East Chiller
`Group. A cross connection with valving in the distribution system allows these chiller groups to
`operate together or supply their individual east and west chiller distribution systems. Either the
`East Group or the West Group of chillers can be isolated in case of a line break, leaving the other
`chiller group in service. The chillers are capable of operating at a ;::.. T of l5°F which provides for
`a chilled water flow of 1.6 gpm per ton. The chilled water supply temperature is normally near
`4JOF, but can be varied between 40°F and 44°F.
`
`The west chiller group consists of five chillers with a total cooling capacity of 10,000 tons. The
`east chiller group consists of six chillers with a total cooling capacity of 4,775 tons. The
`Contemporary Hotel chiller group consist of two chillers with a total capacity of2,975 tons. With
`the largest chiller out of operation, the total plant capacity is 14,950 tons. This total is still in
`excess of the peak load of 14,600 tons.
`
`The distribution system consists of two supply loops: the East Loop, supplying the Magic
`Kingdom, service areas, and several hotels; and the West Loop supplying additional hotels.
`These two loops are supplied from a single underground distribution header on the north side of
`~he chiller building. The two chillers at the Contemporary Hotel provide chilled water to the east
`loop of the system. These two chillers are used continuously as part of the chilled water supply
`system and are not normally cycled off during lower demand periods. Of the chilled water
`supplied to the cooling loops from the CEP chiller building, approximately 25% of the total
`cooling load is supplied to the west loop and 75% is supplied to the east loop.
`
`89
`
`Page 5 of 13
`
`GE Exhibit 1005
`
`

`

`UPGRADE TO CHILLED WATER SYSTEM
`
`Thermal Storage Planning for the Central Energy Plant
`
`Due to economic considerations resulting from the age of two of the existing chillers, with their
`high operating cost per ton, and their increasing maintenance costs, the decision has been made
`to provide a chilled water storage facility to take the place of the on-line capacity of these two
`chillers. This chilled water storage system also provides emergency chilled water backup
`capacity, allows for use of off-peak electricity at potentially lower rates, and reduces dependency
`on regulated "environmentally unfriendly" refrigerants. The chilled water storage system will
`also take into account the additional cooling load added to the chilled water system for providing
`turbine inlet cooling to the electric generation system. This turbine inlet cooling system will add
`electrical generating capacity to the generating plant, as well as increasing its efficiency at times,
`by cooling the inlet combustion air to the turbine generator. The chilled water storage facility
`will consist of a chilled water storage tank, charge I discharge pumps, and system controls.
`
`Planning for the Chilled Water Distribution System
`
`The chilled water distribution loop system is vulnerable to a partial shutdown in case of failure
`of, or required maintenance on, the W1derground distribution header located just north of the CEP
`chiller plant. A new East I West Loop Connector was provided to reroute chilled water from the
`chiller group remaining in operation after a distribution main shutdown. This new connector will
`allow chilled water to be rerouted and supplied to both east loop and west loop distribution
`systems. The new chilled water storage tank supply and return piping was tied into this loop
`connector to provide its cooling capacity to both the east and west loop distribution systems.
`
`Chilled Water Storage Tank and Supply Pump Sizing
`
`The load capacity of the chilled water storage system will take into account the removal of the
`on-line capacity of two chillers totaling 3,325 tons, as well as an increase of2,000 tons of
`cooling for the turbine inlet cooling system. It is assumed that the present peak cooling load of
`14,600 tons must also be met with the largest chiller out of service. The minimum size of the
`chilled water storage tank is determined as follows:
`
`PRESENT FIRM CAP A CITY
`Present peak chiller capacity
`Elimination of two chillers on-line capacity
`
`Total on-line tons available without old chillers
`
`Tonnage removed with largest chiller off-line
`
`Tons normally available without largest chiller
`
`90
`
`17,750 tons
`-3.325 tons
`
`14,425 tons
`
`-2.800 tons
`
`11,625 tons
`
`Page 6 of 13
`
`GE Exhibit 1005
`
`

`

`TANK CAP A CITY REQUIRED
`Peak system cooling load
`Less tons available from plant
`Plus additional tons for turbine inlet cooling
`
`Tons to be supplied by tank storage system
`Plus 10% contingency
`
`14,600 tons
`11,625 tons
`+ 2.000 tons
`
`4,975 tons
`500 tons
`
`Total required peak on-line capability to be supplied by tank
`
`5,500 tons
`
`Assuming that a 1 0-hour discharge time and 14-hour charge time are used, the volume of the
`storage tank required is determined by flow requirements of the system. As indicated above,
`2,000 tons of cooling is provided for turbine inlet cooling with the remaining 3,500 tons provided
`for comfort cooling. The comfort cooling system normally uses water supplied to the loop
`system near 40°F and returned 15° warmer. This combination requires water to be supplied for
`comfort cooling at the rate of 1.6 gpm/ton of cooling:
`
`Comfort Cooling Flow Rate= 3,500 tons x 1.6 gpm/ton = 5,600 gpm
`
`The turbine inlet cooling system normally uses water supplied near 40°F and returned 30°
`warmer. This requires water to be supplied for turbine inlet cooling at the rate of 0.8 gprn/ton of
`cooling:
`
`Turbine Inlet Cooling Flow Rate= 2,000 tons x 0.8 gpm/ton = 1,600 gpm
`
`The total flow rate from the tank is the sum of the comfort cooling flow rate (5,600 gpm) and the
`turbine inlet cooling flow rate (1,600 gpm) or 7,200 gpm. Using the 10 hour discharge time
`indicated above, the total usable volume of the tank must be:
`
`Minimum Usable Tank Volume= 7,200 gpm x 10 hours x 60 min./hour= 4,320,000 gal.
`
`With a storage efficiency (Figure of Merit) of approximately 0.9, the actual tank volume to be
`supplied is 5.000.000 gallons.
`
`The usable energy stored is as follows, assuming an averaget. T of 18.3°F and a figure of merit of
`0.9 minimum:
`
`Usable Energy = (5,000,000 ga1.)(0.9 FOM)(8.34 lb/gal)(l BTU/lb/°F)(18.3°F)
`
`= 6.87 x 108 BTU = 57,000 ton-hours usable at 18.3°F t. T
`
`The total flow rate from the chilled water storage tank as indicated above is 7,200 gpm. This
`water will be supplied by two chilled water pumps sized at 3,600 gpm each. An additional
`standby pump will be provided for emergency use and to allow quick storage tank recharge with
`
`91
`
`Page 7 of 13
`
`GE Exhibit 1005
`
`

`

`three operational pumps when the off-peak load allows. Pump speed and flow will be adjustable
`using variable frequency drive speed controllers on the pumps.
`
`Chiller Capacity for Chilled Water Storage Tank Recharging
`
`After a full usable capacity tank discharge, the chilled water storage tank is normally recharged in
`14 hours overnight. The pumping system is designed so that two pumps can pump the warm
`water from the top of the storage tank and into the chiller return piping system. The existing
`CEP chiller pumping system then circulates the water through the chillers,.cooling it, and
`returning it back to the bottom of the storage tank. As indicated above, one standby tank pump is
`provided for backup operation. In a quick charge situation, the third pump may be operated to
`decrease the recharge time from 14 hours to 6. 7 hours. The chilled water storage tank is
`recharged using chiller capacity that is not required for the normal night time operating cooling
`load on the east and west loops. The required extra chiller capacity during this recharge time is
`as follows:
`
`Extra chiller capacity for 14-hour charge cycle = 57.000 ton-hours
`14 hours
`
`= 4,100 tons excess capacity required.
`
`Minimum tank pump size = (1.6 gpm/ton)(4.100 tons) = 3,280 gpm per pump
`(for recharge)
`2 pumps
`
`Supply pumps sized at 3,600 gpm are required for the discharge cycle, so this
`determines actual pump sizes.
`
`Extra chiller capacity for maximum = 57.000 ton-hours = 8,500 tons
`quick charge using 3 pumps
`6.7 hours
`
`THERMALENERGYSTORAGETANK
`
`As mentioned above, the tank capacity is 5,000,000 gallons. The tank is an above ground steel
`tank. The tank is insulated with rigid insulation board and aluminum jacketing. The tank is
`required to have a maximum capacity of57,000 ton-hours at an 18.3° 6 T. The advantage of
`combining the turbine inlet cooling system (with its 30° 6 T) can be seen. If the cooling load was
`strictly comfort cooling with the 15° 6 T the capacity of the tank would be only 46,700 ton-hours.
`The tank and foundation was designed and provided by the tank manufacturer. The tank is 116
`feet in diameter and is 67 feet tall.
`
`92
`
`Page 8 of 13
`
`GE Exhibit 1005
`
`

`

`COMBUSTION TURBINE INLET AIR COOLING
`
`A combustion turbine's electrical generating capability is directly related to the mass flow of
`combustion air through the unit. Because combustion turbines have fairly constant volumetric
`inlet air flow, the mass flow of the combustion air increases as the density of the air increases.
`For most utilities, including Reedy Creek Energy Services, the requirements for peak capacity
`occur during times of highest ambient temperatures. These high air temperatures result in lower
`air density and reduced capacity from the combustion turbine generator at the time the capacity is
`needed the most. However, cooling the ambient air before it enters the combustion turbine
`increases the air density and, therefore, allows the unit to generate electricity at a substantially
`higher capacity. Capacity enhancements of up to 3 5 percent can be realized with inlet air cooling.
`Additionally, cooler combustion air improves the combustion turbine efficiency and lowers the
`exhaust temperature.
`
`Several combustion turbine inlet air cooling projects have been successfully completed
`throughout the world in the past several years. This new application of existing technologies has
`become widely accepted in the utility industry as an economical method of capacity
`enhancement.
`
`Based on the success of existing combustion turbine inlet air cooling projects, Reedy Creek
`Energy Services requested an evaluation to utilize the proposed chilled water thermal energy
`storage system to supply chilled water for inlet air cooling of their existing General Electric
`LMSOOO combustion turbine generator. It was determined that inlet air cooling would provide
`economical peaking capacity and energy, as well as providing a method of controiiing the
`temperature of the chilled water returning to the storage tank.
`
`The design parameters used for the design of the combustion turbine inlet air cooling system
`were as follows:
`
`•
`•
`
`•
`•
`
`•
`•
`•
`•
`•
`•
`•
`
`Air Flow
`Ambient Temperatures
`Dry Bulb
`Wet Bulb
`Inlet Air Cooled Temperature
`Chilled Water Temperatures
`Supply_
`Return
`Chilled Water Flow Rate
`Air Velocity Across Coils
`Air Pressure Drop Across Coils
`Tube Material
`Tube Wall Thickness
`Fin Material
`Fin Spacing
`
`219,200 scfm
`
`95 degrees F
`79 degrees F
`50 degrees F
`
`40-44 degrees F
`
`1600 gpm
`500 fpm
`1.2 inch H 20
`Copper
`0.049 inch
`Aluminum
`8 fins/inch
`
`93
`
`Page 9 of 13
`
`GE Exhibit 1005
`
`

`

`The existing inlet filter house is located on top on the existing combustion turbine building and
`has four separate horizontal inlet air openings that converge into a common plenum. This
`common plenum connects vertically into the compressor section of the LMSOOO combustion
`turbine. The new air cooling coils were located in four banks at the entrance to the existing
`combustion turbine air intake. The existing evaporative coolers, inertia separators and associated
`materials were removed from the inlet filter house. The exposed surfaces of the existing inlet
`filter house and plenum past the new air cooling coils were insulated and lagged for thermal
`efficiency and condensation protection.
`
`OPERATION
`
`Chilled Water Storage and Chiller System
`
`There are an infinite number of load conditions that the system may encounter depending on time
`of year, time of day, sky condition, humidity, park and hotel occupancy~ etc. A large number of
`different modes of operation were analyzed to ensure that the central plant, thermal storage
`system and new distribution system can function effectively under varying load conditions. The
`effect of chiller outages and distribution system breaks were also evaluated to develop means to
`keep the system in operation. See the attached Figure 3 for system schematic.
`
`The storage system has approximately 14 different control modes. However, it boils down to
`three primary modes.
`
`*
`*
`*
`
`Tank Recharge Mode
`Tank Discharge Mode with bias to the central plant chillers
`Tank Discharge Mode with bias to the chilled water storage tank
`
`The pumping schemes for the three primary modes are further described as follows:
`
`Tank Recharge: The tank distribution pumps draw water from the top of the tank and supply it to
`the chiller plant. The chilled water is then returned to the bottom pf the tank.
`
`Tank Discharge, Central Plant Bias: The central plant chillers and pumping system supply a
`preset flow level (base load) to the distribution system. The tank pumping system supplements
`this base load. The control system will vary the chilled water supply flow from the tank by
`adjusting the pump(s) VFDs to maintain system pressure.
`
`Tank Discharge. Tank Bias: Under this control scheme the tank pumping system is set to
`maintain a preset chilled water supply level to the distribution system. This level is maintained
`
`94
`
`Page 10 of 13
`
`GE Exhibit 1005
`
`

`

`~=- ·
`
`~
`(11
`
`I
`
`10 IG1I15
`
`om Lo:P
`
`-T
`
`•
`
`ID 14 sm.v
`---
`
`~~
`"'\ =--......
`'
`I
`
`•
`
`I
`
`·-·~ ""
`
`;
`
`,.__,
`
`(Vo.UNU
`1RBI}
`
`~7/J V-:1
`
`,
`,,._
`
`'f-;
`
`~~ll
`
`Jl
`
`~· 7/f'.
`
`6 1U.li>U _,_
`
`t.~
`
`';-~
`
`~~~-'
`- •
`~-
`
`I
`
`~~
`
`.
`
`••m•newi!J.C!w
`
`J(IUAf
`u~
`
`L
`
`•
`
`,_
`
`1'-X~.,_k
`,_,(nml1.111CIIOf'
`:1-f
`1-fi:XSI1101 W('l(
`11<11 u:J~Unoe V"-~
`,.. ICQo!'<llll\001
`
`P1. .,R:_,
`
`ms cti'IJ.lD•oUf\J
`0« O<IUtl> .. QI~
`"" .C01 'eP tAJVt )..fii\J
`.,,. lO# ...... o II(U..
`""'
`e. """"'"..:"'"
`;::::;~ .......
`
`liO VWJiiltllff'ORt"\t4..'tf
`M
`M~) ... (.U'I' v•~
`'£-~~Yfe..:C
`s-:1 V.Wifrta.fU.Ytl\(
`-
`IOJNJC
`-
`omncmiC
`[!0......_,_._
`m~·..r.-­
`l!D fiD0' . . \1:1'
`@JJU!f•-llllll
`llil\L\(1 ""'"""'""'
`[B!] "'"""",..,.
`
`~ -
`··~ auu Ill~::)
`
`I~C"-1:{
`
`9 _..,
`
`IE!J -......
`I!E!l -Dr
`G!:D -lU1I!!T'f
`
`DB
`
`~
`~­... lllm'-
`
`FIGURE 3
`TES
`SCHEMA TIC DIAGRAM
`
`Page 11 of 13
`
`GE Exhibit 1005
`
`

`

`and adjusted by flow transmitters in the chilled water supply to each distribution loop. The
`central plant pumps will adjust their flow to maintain system pressure.
`
`Combustion Turbine Inlet Air Coolinfl System
`
`The intended use of the inlet air cooling system is to cool the combustion air for the GE LMSOOO
`existing combustion turbine. Cooling provides more mass flow of air thus increasing the
`generating capacity of the unit. The air cooling coils will be used for up to 24 hours per day, but
`will primarily be used during the highest temperature periods of the day, typically 10 hours.
`
`The operation of the combustion turbine inlet air cooling system is accomplished by a new
`programmable logic controller (PLC), and was integrated with the existing Reedy Creek Energy
`Services, F omey and Woodward control systems. The plant operator has the ability to start and
`stop inlet air cooling as well as control the air cooling temperature from ambient temperature
`down to the design cooled temperature of 50 degrees F.
`
`CONCLUSIONS
`
`RCID has been able to realize significant energy and economic advantages of the Chilled Water
`Thermal Storage System. These include the following:
`
`*
`
`*
`
`*
`
`*
`
`*
`
`*
`
`Utilization of off-peak electrical energy to provide a significant portion of their
`cooling requirements.
`
`Capacity enhancement of turbine-generator by up to 35% during wann weather
`conditions.
`
`Provide a reliable source of cooling during the day, if a chiller is taken out of
`service during peak load conditions.
`
`Provide for 20,000 ton-hrs of cooling (35 percent of the tank capacity) for the
`turbine-inlet-cooling system by adding only 25 percent additional storage volume
`to the thermal storage tank (due to the increased h.. T between the supply and return
`to the tank).
`
`Eliminated the need to replace 3,325 tons of chiller capacity. Also, reduced
`reliance on CFC refrigerants for real time cooling.
`
`With the addition of the new chilled water cross-tie between the east and west
`loops: realized an increase in system reliability in the distribution system.
`
`96
`
`Page 12 of 13
`
`GE Exhibit 1005
`
`

`

`The entire project provided adequate savings in energy usage to provide a good rate of return on
`RCID's investment. The exact economic impact is not available for publication.
`
`97
`
`Page 13 of 13
`
`GE Exhibit 1005
`
`

This document is available on Docket Alarm but you must sign up to view it.


Or .

Accessing this document will incur an additional charge of $.

After purchase, you can access this document again without charge.

Accept $ Charge
throbber

Still Working On It

This document is taking longer than usual to download. This can happen if we need to contact the court directly to obtain the document and their servers are running slowly.

Give it another minute or two to complete, and then try the refresh button.

throbber

A few More Minutes ... Still Working

It can take up to 5 minutes for us to download a document if the court servers are running slowly.

Thank you for your continued patience.

This document could not be displayed.

We could not find this document within its docket. Please go back to the docket page and check the link. If that does not work, go back to the docket and refresh it to pull the newest information.

Your account does not support viewing this document.

You need a Paid Account to view this document. Click here to change your account type.

Your account does not support viewing this document.

Set your membership status to view this document.

With a Docket Alarm membership, you'll get a whole lot more, including:

  • Up-to-date information for this case.
  • Email alerts whenever there is an update.
  • Full text search for other cases.
  • Get email alerts whenever a new case matches your search.

Become a Member

One Moment Please

The filing “” is large (MB) and is being downloaded.

Please refresh this page in a few minutes to see if the filing has been downloaded. The filing will also be emailed to you when the download completes.

Your document is on its way!

If you do not receive the document in five minutes, contact support at support@docketalarm.com.

Sealed Document

We are unable to display this document, it may be under a court ordered seal.

If you have proper credentials to access the file, you may proceed directly to the court's system using your government issued username and password.


Access Government Site

We are redirecting you
to a mobile optimized page.





Document Unreadable or Corrupt

Refresh this Document
Go to the Docket

We are unable to display this document.

Refresh this Document
Go to the Docket