`BEFORE THE PATENT TRIAL AND APPEAL BOARD
`
`
`
`
`INNOLUX CORPORATION
`Petitioner
`
`v.
`
`PATENT OF SEMICONDUCTOR ENERGY LABORATORY CO., LTD.
`Patent Owner
`
`
`
`
`
`CASES IPR2013-00028 (PATENT 6,404,480)
`
`IPR2013-00038 (PATENT 7,956,978)
`
`IPR2013-00060 (PATENT 7,697,102)
`
`IPR2013-00064 (PATENT 7,923,311)
`
`IPR2013-00065 (PATENT 7,923,311)
`
`IPR2013-00066 (PATENT 7,876,413)
`
`IPR2013-00068 (PATENT 8,068,204)
`
`
`
`
`JOINT NOTICE OF STIPULATION TO REVISED SCHEDULE
`
`
`
`
`
`
`
`
`
`As permitted by the Scheduling Order, as agreed to by the parties and as
`
`discussed during the conference call conducted with the Board on October 30,
`
`2013, the Board authorized moving DUE DATES 4-6 by one week in all of the
`
`pending IPRs. The Board also authorized combining Due Dates 3-5 in IPR2013-
`
`00028 and IPR2013-00038 to a single date on Due Date 5 provided that the parties
`
`agree to waive filing any motions to exclude evidence or file any observations on
`
`cross-examination and thus file only the Patent Owner's reply and any requests for
`
`oral argument on Due Date 5. The Patent Owner and Petitioner have agreed to the
`
`Board's proposal in IPR2013-00028 and IPR2013-00038 and also have stipulated
`
`to the following revised DUE DATES 2 and 3:
`
`
`
`IPR2013-00028
`IPR2013-00038
`
`Due Date 2
`
`N/A
`
`IPR2013-00060
`IPR2013-00064
`IPR2013-00065
`December 6, 2013
`
`IPR2013-00066
`IPR2013-00068
`
`December 2, 2013
`
`Due Date 3 December 2, 2013
`
`December 20, 2013
`
`December 16, 2013
`
`Due Date 4
`
`December 2, 2013
`
`December 27, 2013
`
`December 23, 2013
`
`Due Date 5
`
`December 2, 2013
`
`January 10, 2014
`
`January 6, 2014
`
`Due Date 6
`
`December 9, 2013
`
`January 17, 2014
`
`January 13, 2014
`
`
`
`2
`
`
`
`
`
`
`
`IPR2013-00028
`IPR2013-00038
`
`Due Date 7 December 16, 2013
`
`IPR2013-00060
`IPR2013-00064
`IPR2013-00065
`January 23, 2014
`
`IPR2013-00066
`IPR2013-00068
`
`January 21, 2014
`
`(No Change)
`
`(No Change)
`
`(No Change)
`
`Dated: October 31, 2013
`
`
`
`
`
`
`
`
`
`Respectfully submitted,
`
`/Sean C. Flood/
`Eric J. Robinson
`Sean C. Flood
`
`/Mark J. Murphy/
`Mark J. Murphy
`Edward D. Manzo
`Attorneys for Patent Owner
`
`/Gregory S. Cordrey/
`Scott A. McKeown
`Gregory S. Cordrey
`Attorneys for Petitioner
`
`3
`
`
`
`
`
`
`
`
`CERTIFICATE OF SERVICE
`
`I certify that the foregoing JOINT NOTICE OF STIPULATION TO
`
`REVISED SCHEDULE was served on the Petitioner by email at the following
`
`addresses on November 1, 2013.
`
`
`
`
`
`
`
`
`
`
`
`Eric Robinson
`
`Sean Flood
`erobinson@riplo.com
`sflood@riplo.com
`
`Stanley Schlitter
`Douglas Peterson
`sschlitt@steptoe.com
`dpeterson@oblon.com
`
`Mark Murphy
`Edward Manzo
`mark.murphy@huschblackwell.com
`edward.manzo@huschblackwell.com
`
`
`
`
`
`
`
`
`
`/Scott McKeown/
`
`
`
`
`
`