`SIPCO, LLC, ET AL.
`
`v.
`
`EMERSON ELECTRIC CO., ET AL.
`
`IN THE UNITED STATES DISTRICT COURT
`FOR THE EASTERN DISTRICT OF TEXAS
`TYLER DIVISION
`
`§
`§
`§
`§
`§
`
`ORDER
`
`
`
`Case No. 6:15-CV-907-JRG-KNM
`
`This case is set for a scheduling conference in Marshall, Texas on February 22, 2016 at
`
`1:30 p.m. before the Honorable Rodney Gilstrap. The purpose of the scheduling conference will
`
`be to assign a claim construction hearing date and a trial setting. The parties shall be prepared to
`
`inform the Court whether they will consent to trial before the Magistrate Judge.
`
`The parties shall prepare and submit a proposed docket control order, a proposed
`
`discovery order and a proposed protective order, within the time periods contained in the
`
`schedule set forth hereinafter.1 These orders shall be guided by the sample docket control,
`
`discovery, and protective orders for patent cases, which can be found on the Court’s website.
`
`The sample orders include provisions that require input from the parties. If the parties are unable
`
`to reach agreement on these provisions, then the parties shall submit to the Court their competing
`
`proposals along with a summary of their disagreements in a single joint submission.
`
`The sample orders include provisions that are mandatory and are not subject to change
`
`without showing good cause. Good cause shall not be considered to be met simply by an
`
`indication of the parties’ agreement. Should either party believe good cause can be shown to
`
`alter an otherwise mandatory provision, then such party shall file a separate motion to alter the
`
`
`1 Timely submission of the parties’ proposed docket control order, proposed discovery
`order and proposed protective order will be viewed by the Court as complying with the
`conference requirement of Rule 26(f).
`
`
`
`Case 1:16-cv-02690-AT Document 38 Filed 01/26/16 Page 2 of 2
`
`provision after the parties have filed the proposed docket control and discovery orders with the
`
`mandatory provisions intact as previously required above.
`
`Furthermore, it is hereby ORDERED that the following schedule of deadlines is in effect
`
`until further order of this Court:
`
`Comply with P.R. 3-3 & 3-4 (Invalidity Contentions)
`
`*File Proposed Protective Order and Comply with Paragraphs 1 & 3
`of the Discovery Order (Initial and Additional Disclosures)
`
`The Proposed Protective Order shall be filed as a separate motion
`with the caption indicating whether or not the proposed order is
`opposed in any part.
`
`*File Proposed Docket Control Order and Proposed Discovery Order
`
`The Proposed Docket Control Order and Proposed Discovery Order
`shall be filed as separate motions with the caption indicating whether
`or not the proposed order is opposed in any part.
`
`Join Additional Parties
`
`*File Notice of Mediator
`
`Comply with P.R. 3-1 & 3-2 (Infringement Contentions)
`
`6 Weeks After
`Scheduling Conference
`
`3 Weeks After
`Scheduling Conference
`
`2 Weeks After
`Scheduling Conference
`
`1 Week After
`Scheduling Conference
`
`3 Days After
`Scheduling Conference
`
`2 Weeks Before
`Scheduling Conference
`
`
`
`
`- 2 -
`
`____________________________________
`RODNEY GILSTRAP
`UNITED STATES DISTRICT JUDGE
`
`SIGNED this 19th day of December, 2011.
`
`So ORDERED and SIGNED this 26th day of January, 2016.
`
`