throbber
Case 1:16-cv-00455-RGA Document 222 Filed 08/07/17 Page 1 of 4 PageID #: 17997
`
`M O R R I S , N I C H O L S , A R S H T & T U N N E L L L L P
`1201 NORTH MARKET STREET
`P.O. BOX 1347
`WILMINGTON, DELAWARE 19899-1347
`
`(302) 658-9200
`(302) 658-3989 FAX
`
`JACK B. BLUMENFELD
`(302) 351-9291
`(302) 425-3012 FAX
`jblumenfeld@mnat.com
`
`
`
`The Honorable Richard G. Andrews
`United States District Court
` for the District of Delaware
`844 North King Street
`Wilmington, DE 19801
`
`August 7, 2017
`
`VIA ELECTRONIC FILING
`
`Re:
`
`Acceleration Bay LLC; C.A. Nos. 16-453 (RGA); 16-454 (RGA); and 16-455 (RGA)
`
`Dear Judge Andrews:
`In light of the Court’s July 5, 2017 Order extending claim construction briefing through
`late November, Defendants request that the Court modify the existing schedule so that election
`of prior art, expert reports, Daubert, summary judgment and trial all proceed in an orderly
`fashion after claim construction is complete. Defendants also note that they have pending
`motions to dismiss and have not yet answered. Acceleration Bay opposes any amendments to
`the case schedule. A proposed order, including a table comparing the current schedule with
`Defendants’ proposed revised schedule, is attached as Exhibit A.
`
`Procedural Background. The current schedule was set in February 2017 and follows
`this Court’s traditional sequence, with a claim construction hearing on July 10, 2017, final
`election of asserted claims and prior art, and opening expert reports in September, and summary
`judgment and Daubert motions the following February. The first trial was set for April 2018.
`
`On July 5, 2017, the Court ordered that claim construction occur over five phases, with
`the final joint claim construction brief being due on November 30, 2017. C.A. No. 16-453, D.I.
`206; D.I. 274.1 On July 10, the Court held the first of the five claim construction hearings.
`Defendants’ motions to dismiss were heard that day as well. After rulings on the motions to
`dismiss, Defendants will need to answer. The Court has not scheduled hearings for the last four
`claim construction briefs, and presumably claim construction will not be complete until early
`2018.
`
`
`1 References to docket entries in this letter refer to C.A. No. 16-453.
`
`

`

`Case 1:16-cv-00455-RGA Document 222 Filed 08/07/17 Page 2 of 4 PageID #: 17998
`
`The Honorable Richard G. Andrews
`August 7, 2017
`Page 2
`
`
`
`Argument. Courts in Delaware and around the country have recognized that final
`election of prior art, expert reports, Daubert, and summary judgment should all follow claim
`construction. The practice is more cost effective and efficient because the Parties do not have to
`prepare expert reports with each party's proposed alternative constructions and without knowing
`the Court's claim constructions, which may be different from the parties' proposed constructions.
`
`At the scheduling conference, Defendants specifically raised the very issue of receiving a
`claim construction order before election of prior art and expert reports. See Ex. B, Feb. 17, 2017
`Tr. at 26, 27. The Court took this into account, and explained that it would set a claim
`construction hearing in July and try to issue a claim construction order by the end of August. Id.
`Defendants then agreed to a schedule that accounted for the Court's expected Markman decision
`– that schedule set final election of asserted claims and prior art, and opening expert reports for
`late September, at least three weeks after the expected Markman decision.
`
`The practice of having expert reports after the pleadings are settled and the issuance of
`claim construction rulings is particularly appropriate in these three cases. Plaintiff is asserting 21
`claims from six different patents, and has accused at least 8 distinct product lines across the three
`cases. The parties have vastly different claim construction positions on over 40 terms across the
`six patents. D.I. 236 (Joint Claim Construction Chart, Exhibit 2). Plaintiff specifically raised the
`issue of claim construction as a basis for opposing Activision’s Motion to Dismiss. D.I. 28
`(Plaintiff’s Answering Brief) at 18. Plaintiff has also steadfastly resisted the idea of limiting the
`length of expert reports, and has indicated at a meet and confer it would only consider limiting its
`expert reports to 5,000 pages in each of the three cases.
`
`Scheduling final elections of asserted claims and prior art, expert reports and dispositive
`motions after the pleadings are settled and after claim construction will streamline the case.
`Claim construction briefing will conclude in late November, and no hearing dates have been set.
`Thus, the parties are likely not to have final rulings on claim construction until early 2018.
`Under the current schedule, the parties will need to elect asserted claims and prior art and
`prepare expert reports before they have even completed claim construction briefing. They will
`have to complete all expert discovery and prepare Daubert and dispositive motions (due
`February 2, 2018) without claim construction rulings. Given the significance of claim
`construction, the parties would likely seek to amend or supplement their expert reports given the
`claim constructions. And certainly any summary judgment briefing or Daubert motion briefing
`already filed would need to be modified. It would be highly prejudicial to Defendants to force
`them to make a final election of prior art and prepare dispositive motions before the scope of the
`claims is determined. In contrast, Plaintiff provides no reason to prepare expert reports when the
`parties will likely seek to amend or supplement those reports after the claim construction ruling.
`Thus, waiting for claim construction to conclude and the pleadings to be closed before expert
`reports will lead to a more efficient and orderly resolution of disputes in these actions.
`
`

`

`Case 1:16-cv-00455-RGA Document 222 Filed 08/07/17 Page 3 of 4 PageID #: 17999
`
`The Honorable Richard G. Andrews
`August 7, 2017
`Page 3
`
`
`
`Expert reports, Daubert Motions, and motions for summary judgment will all be
`substantially less burdensome on both the parties and Court after claim construction. This is all
`the more so because at least 14 of the 21 Asserted Claims may be held invalid as indefinite or as
`directed to unpatentable subject matter. See Ex. C. The parties and Court will benefit from
`knowing the Court’s constructions and what claims have survived claim construction before the
`parties elect asserted claims and prior art, prepare expert reports and file Daubert and summary
`judgment motions.2
`
`On the other hand, proceeding with expert reports without claim constructions and before
`the claims and defenses are presented in the pleadings provides no guarantee that the schedule
`will not be moved later. Given Plaintiff's infringement contentions and responses to
`interrogatories, Defendants are concerned that Plaintiff's expert reports will be inadequate or
`identify brand new theories not previously disclosed in Plaintiff's infringement contentions or
`responses to interrogatories. Defendants have prevailed on multiple motions to compel
`regarding Plaintiff's explanation of how the Accused Products allegedly infringe. In response to
`the latest Motion, the Special Master explained that "if Plaintiff's expert reports set forth
`infringement contentions that had not been previously disclosed, it may be appropriate to
`reconsider Defendants' motion for sanctions and appropriate relief." Special Master Order No. 6.
`
`The current schedule leaves little time for the Special Master to thoroughly review
`Plaintiff’s expert reports before summary judgment papers are due. Defendants are justifiably
`concerned that Plaintiff will seek to add new theories in its expert reports. As noted, Plaintiff
`will likely object to page limits on expert reports and has indicated it may serve incredibly
`voluminous expert reports. With this large volume of expert reports, the Special Master will
`likely need to resolve disputes regarding whether Plaintiff has added new theories of
`infringement. Such resolution is not practical until after the claim construction rulings are
`issued.
`
`Finally, Plaintiff has not identified any prejudice from an extension of the schedule. The
`patents issued more than a decade ago and Plaintiff does not sell or manufacture any products
`and seeks only reasonable royalty damages. There can be no prejudice to it from a few months
`delay to ensure that the remainder of the case is prepared efficiently and correctly.
`
`Pursuant to Federal Rule of Civil Procedure 16(b)(4), Defendants, therefore, request that
`all currently pending scheduling order dates be reset. Defendants’ proposed schedule in Exhibit
`A anticipates that the Court would have ruled on all pending motions to dismiss and issued
`rulings on all claim construction issues by February 2018. Otherwise, the proposed schedule
`maintains the same amount of time between the various events.
`
`2 Defendants’ Motions to Dismiss also may significantly reduce the scope of the case.
`Defendants have moved to dismiss Plaintiff's claims against Sony products. About half of all
`accused products in this case are games on the Sony platform, and as explained in the motion to
`dismiss, Plaintiff lacks standing to sue on those products. Given the lack of standing, there
`should be no expert reports at all on the Sony products.
`
`

`

`Case 1:16-cv-00455-RGA Document 222 Filed 08/07/17 Page 4 of 4 PageID #: 18000
`
`The Honorable Richard G. Andrews
`August 7, 2017
`Page 4
`
`
`
`
`
`JBB:cjl
`Enclosure
`cc:
`Clerk of Court (Via Hand Delivery; w/enclosure)
`
`All Counsel of Record (Via Electronic Mail; w/enclosure)
`11229034
`
`Respectfully,
`
`/s/ Jack B. Blumenfeld
`
`Jack B. Blumenfeld (#1014)
`
`
`

This document is available on Docket Alarm but you must sign up to view it.


Or .

Accessing this document will incur an additional charge of $.

After purchase, you can access this document again without charge.

Accept $ Charge
throbber

Still Working On It

This document is taking longer than usual to download. This can happen if we need to contact the court directly to obtain the document and their servers are running slowly.

Give it another minute or two to complete, and then try the refresh button.

throbber

A few More Minutes ... Still Working

It can take up to 5 minutes for us to download a document if the court servers are running slowly.

Thank you for your continued patience.

This document could not be displayed.

We could not find this document within its docket. Please go back to the docket page and check the link. If that does not work, go back to the docket and refresh it to pull the newest information.

Your account does not support viewing this document.

You need a Paid Account to view this document. Click here to change your account type.

Your account does not support viewing this document.

Set your membership status to view this document.

With a Docket Alarm membership, you'll get a whole lot more, including:

  • Up-to-date information for this case.
  • Email alerts whenever there is an update.
  • Full text search for other cases.
  • Get email alerts whenever a new case matches your search.

Become a Member

One Moment Please

The filing “” is large (MB) and is being downloaded.

Please refresh this page in a few minutes to see if the filing has been downloaded. The filing will also be emailed to you when the download completes.

Your document is on its way!

If you do not receive the document in five minutes, contact support at support@docketalarm.com.

Sealed Document

We are unable to display this document, it may be under a court ordered seal.

If you have proper credentials to access the file, you may proceed directly to the court's system using your government issued username and password.


Access Government Site

We are redirecting you
to a mobile optimized page.





Document Unreadable or Corrupt

Refresh this Document
Go to the Docket

We are unable to display this document.

Refresh this Document
Go to the Docket