throbber
Case 1:14-cv-01430-LPS Document 340 Filed 10/07/20 Page 1 of 3 PageID #: 21460
`WILMINGTON
`RODNEY SQUARE
`
`NEW YORK
`ROCKEFELLER CENTER
`
`Adam W. Poff
`P 302.571.6642
`F 302.576.3326
`apoff@ycst.com
`
`
`
`October 7, 2020
`
`
`
`
`BY E-FILING
`
`The Honorable Leonard P. Stark
`United States District Court
` for the District of Delaware
`844 N. King Street
`Wilmington, DE 19801
`
`Re:
`
`ELM 3DS Innovations, LLC v. Samsung Electronics Co., Ltd., et al.,
`C.A. No. 14-cv-1430-LPS
`
`Dear Chief Judge Stark:
`
`Samsung respectfully submits this response to Elm’s letter regarding the parties’
`stipulation to amend the schedule (D.I. 339).
`
`There is no dispute for the Court to resolve, and indeed, Elm and Samsung jointly
`submitted the agreed-upon stipulation to amend the schedule. Nevertheless, Elm decided to file
`its own letter purporting to summarize the circumstances requiring the amendment. Samsung
`would ordinarily not burden the Court with a responsive letter where there is no dispute before
`Your Honor except that Elm’s letter omits important facts and mischaracterizes the record,
`requiring correction.
`
`First, Elm accuses Samsung of ignoring deadlines and disregarding the Court’s order
`requiring completion of the chart on accused products for selecting representative products. That
`is not true. Samsung complied with the Court-ordered June 19 deadline, as evidenced by three
`joint status reports informing the Court of the parties’ progress in addressing the requested
`information.1 (See D.I. 310, 314, and 318.) And, in the final joint status report, the parties
`agreed that there were no outstanding issues to resolve.2 (See D.I. 318.)
`
`
`1 Elm incorrectly states that the Court “largely granted” its motion to compel; Samsung agreed to
`complete the chart after Elm presented it for the first time with its May 19 letter (D.I. 286), and
`the Court entered an order memorializing that agreement (D.I. 293).
`
` Elm misleadingly states that Samsung has “refused” to produce documents until the parties
`have selected representative products, but that has been the agreed-upon plan all along and one
`of the very reasons for a representative products agreement. Elm has even informed the Court
`
` 2
`
`Young Conaway Stargatt & Taylor, LLP
`Rodney Square | 1000 North King Street | Wilmington, DE 19801
`P 302.571.6600 F 302.571.1253 YoungConaway.com
`
`

`

`Case 1:14-cv-01430-LPS Document 340 Filed 10/07/20 Page 2 of 3 PageID #: 21461
`Young Conaway Stargatt & Taylor, LLP
`The Honorable Leonard P. Stark
`October 7, 2020
`Page 2
`
`
`Samsung diligently provided the information it had after an exhaustive, good-faith
`investigation. There are over a thousand accused products at issue in this case, many of which
`were discontinued years ago and require tedious manual searches for the data required for
`selecting representative products. It is not surprising that some data cannot be found, as Elm
`acknowledges, and that there were inadvertent errors in the large volume of complex data that
`was ultimately compiled. In any event, Elm concedes that Samsung has corrected any errors as
`they have been identified.3
`
`Second, Elm’s accusation of Samsung not meeting the substantial completion deadline is
`misleading and one-sided, taken out of the appropriate context. Samsung informed Elm before
`August 28 deadline that Samsung had inadvertently misidentified a custodian (who shares the
`same name with another employee), and needed additional time to collect documents from the
`correct custodian. Elm did not object. Samsung also informed Elm that it expected to produce
`documents shortly past the August 28 deadline as a result of unforeseen delays in processing
`large volumes of documents at home networks, pursuant to work-from-home practices and in
`light of the COVID-19 pandemic. Elm again did not object. And, Elm omits the critical fact that
`it itself failed to meet the August 28 deadline, having not yet produced inventor notebooks that it
`had agreed to provide.
`
`In light of these issues, and before the substantial completion deadline, Samsung (with
`Defendants Micron and SK hynix in related cases) approached Elm to amend the schedule, since
`it was apparent that all parties—including Elm—would benefit from additional extensions of
`time. Given the circumstances, Defendants reasonably expected to reach the agreement
`ultimately reflected in the instant stipulation to amend the schedule. But Elm simply refused at
`the time and threatened to seek relief, giving no explanation for why after weeks of consenting to
`Samsung’s production of certain documents after August 28, it suddenly objected to an amended
`schedule that would align with the parties’ existing expectations. It is evident from the joint
`stipulation that Elm agrees with an amended schedule that addresses supplemental document
`productions and corresponding discovery allowances for both sides. Elm clearly has no basis to
`object, as a contributor to the circumstances requiring the amendment. It is, therefore,
`disingenuous for Elm to now burden the Court with its erroneous accusation that Samsung has
`unilaterally disregarded the schedule.
`
`that such an agreement is intended to benefit both parties in streamlining the case (see D.I. 288),
`which includes alleviating Samsung’s burden in discovery. And, it is likewise inappropriate to
`attribute any delay to Samsung alone; for example, Samsung served an updated chart on July 17
`and Elm did not raise any concerns about it until August 21.
`
` Elm’s accusation that Samsung omitted “billions of dollars in relevant sales information”
`exaggerates the significance of this data. This data was for downstream product sales, i.e.,
`consumer products that incorporate the accused memory and image sensor components, which
`themselves sell for only a fraction of the downstream product sales. It is the quantity of
`downstream products sold that is relevant to show the total number of allegedly infringing units
`contained therein, not the entire market value of the downstream products. In any event,
`Samsung updated the chart with this data promptly after discovering its inadvertent omission.
`
` 3
`
`
`
`

`

`Case 1:14-cv-01430-LPS Document 340 Filed 10/07/20 Page 3 of 3 PageID #: 21462
`Young Conaway Stargatt & Taylor, LLP
`The Honorable Leonard P. Stark
`October 7, 2020
`Page 3
`
`
`Should Your Honor have any questions regarding these matters, counsel for Samsung are
`available at the Court’s convenience.
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`Respectfully submitted,
`
`/s/ Adam W. Poff
`
`Adam W. Poff (No. 3990)
`
`Counsel of Record (via E-Filing and E-Mail)
`
`
`
`
`
`
`
`
`cc:
`
`
`
`
`
`

This document is available on Docket Alarm but you must sign up to view it.


Or .

Accessing this document will incur an additional charge of $.

After purchase, you can access this document again without charge.

Accept $ Charge
throbber

Still Working On It

This document is taking longer than usual to download. This can happen if we need to contact the court directly to obtain the document and their servers are running slowly.

Give it another minute or two to complete, and then try the refresh button.

throbber

A few More Minutes ... Still Working

It can take up to 5 minutes for us to download a document if the court servers are running slowly.

Thank you for your continued patience.

This document could not be displayed.

We could not find this document within its docket. Please go back to the docket page and check the link. If that does not work, go back to the docket and refresh it to pull the newest information.

Your account does not support viewing this document.

You need a Paid Account to view this document. Click here to change your account type.

Your account does not support viewing this document.

Set your membership status to view this document.

With a Docket Alarm membership, you'll get a whole lot more, including:

  • Up-to-date information for this case.
  • Email alerts whenever there is an update.
  • Full text search for other cases.
  • Get email alerts whenever a new case matches your search.

Become a Member

One Moment Please

The filing “” is large (MB) and is being downloaded.

Please refresh this page in a few minutes to see if the filing has been downloaded. The filing will also be emailed to you when the download completes.

Your document is on its way!

If you do not receive the document in five minutes, contact support at support@docketalarm.com.

Sealed Document

We are unable to display this document, it may be under a court ordered seal.

If you have proper credentials to access the file, you may proceed directly to the court's system using your government issued username and password.


Access Government Site

We are redirecting you
to a mobile optimized page.





Document Unreadable or Corrupt

Refresh this Document
Go to the Docket

We are unable to display this document.

Refresh this Document
Go to the Docket