`Case 1:14-cv-01432-LPS Document 224-1 Filed 09/09/19 Page 1 of 2 PageID #: 15602
`
`IN THE UNITED STATES DISTRICT COURT
`FOR THE DISTRICT OF DELAWARE
`
`
`
`
`
`C.A. No. 14-cv-1430-LPS
`
`JURY TRIAL DEMANDED
`
`
`
`
`
`C.A. No. 14-cv-1431-LPS
`
`JURY TRIAL DEMANDED
`
`
`
`
`
`C.A. No. 14-cv-1432-LPS
`
`JURY TRIAL DEMANDED
`
`
`
`
`Defendants.
`
`[PROPOSED] ORDER
`
`
`
`AND NOW, this ____ day of September, 2019, the Court having considered the parties’
`
`September ____, 2019 request to amend the claim construction schedule;
`
`1.
`
`The Court adopts the following claim construction briefing schedule proposed by
`
`the parties:
`
`(a) The parties shall exchange revised opening briefs on October 7, 2019;
`
`
`
`
`
`Case 1:14-cv-01432-LPS Document 224-1 Filed 09/09/19 Page 2 of 2 PageID #: 15603
`
`(b) The parties shall exchange answering claim construction briefs on November 4, 2019;
`
`and
`
`(c) The parties shall file a joint claim construction brief and related materials by
`
`November 11, 2019.
`
`2.
`
`The Court will hear argument on claim construction on January ___, 2020 at
`
`___:____ __.m.
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`____________________________________
`The Honorable Leonard P. Stark
`