`UNITED STATES DISTRICT COURT
`CENTRAL DISTRICT OF CALIFORNIA
`SOUTHERN DIVISION
`
`
`Case No. 8:17-CV-00981-JVS-JCG
`
`ORDER CONTINUING CLAIM
`CONSTRUCTION DEADLINES
`
`
`
`
`
`DOCUMENT SECURITY
`SYSTEMS, INC.,
`Plaintiff,
`v.
`
`
`SEOUL SEMICONDUCTOR CO.,
`LTD., and SEOUL
`SEMICONDUCTOR, INC.,
`Defendants.
`
`
`
`Case No. 2:17-CV-04263-JVS-JCG
`
`
`
`DOCUMENT SECURITY
`SYSTEMS, INC.,
`Plaintiff,
`
`v.
`CREE, INC.,
`Defendant.
`
`
`
`
`
`
`
`[PROPOSED] ORDER CONTINUING CLAIM CONSTRUCTION DEADLINES
`
`
`
`Case 2:17-cv-04263-JVS-JCG Document 60 Filed 05/01/18 Page 2 of 3 Page ID #:923
`
`DOCUMENT SECURITY
`SYSTEMS, INC.,
`Plaintiff,
`
`v.
`EVERLIGHT ELECTRONICS CO.,
`LTD., and EVERLIGHT
`AMERICAS, INC.,
`Defendants.
`
`
`
`Case No. 2:17-CV-04273-JVS-JCG
`
`
`
` Case No. 2:17-CV-06050-JVS-JCG
`
`
`
`DOCUMENT SECURITY
`SYSTEMS, INC.,
`Plaintiff,
`
`v.
`LITE-ON, INC., and LITE-ON
`TECHNOLOGY CORPORATION,
`Defendants.
`
`
`
`
`
`
`
`
`
`
`
`
`
`[PROPOSED] ORDER CONTINUING CLAIM CONSTRUCTION DEADLINES
`
`1 2 3 4 5 6 7 8 9
`
`10
`11
`12
`13
`14
`15
`16
`17
`18
`19
`20
`21
`22
`23
`24
`25
`26
`27
`28
`
`
`
`Case 2:17-cv-04263-JVS-JCG Document 60 Filed 05/01/18 Page 3 of 3 Page ID #:924
`
`
`Upon consideration of the parties’ Joint Stipulation to Continue the Claim
`Construction Schedule, IT IS HEREBY ORDERED THAT:
`The claim construction deadlines in the above-captioned cases are modified
`as follows:
`
`EVENT
`Exchange of Preliminary
`Constructions under Patent Rule
`4-2
`
`CURRENT DATES NEW DATES
`April 18, 2018
`May 30, 2018
`
`Joint Claim Construction and
`Prehearing Statement under
`Patent Rule 4-3
`
`Completion of Claim
`Construction Discovery under
`Patent Rule 4-4
`
`Concurrent Opening Claim
`Construction briefs Under Patent
`Rule 4-5
`
`Concurrent Reply Claim
`Construction Briefs under Patent
`Rule 4-5
`
`Claim Construction Hearing
`under Patent Rule 4-6
`
`May 2, 2018
`
`May 25, 2018
`
`June 15, 2018
`
`July 13, 2018
`
`July 30, 2018
`
`
`June 12, 2018
`
`
`July 6, 2018
`
`
`July 27, 2018
`
`
`August 24, 2018
`
`
`September 10, 2018
`At 3:00 p.m.
`
`
`IT IS SO ORDERED.
`
`Dated: May 01, 2018
`
`
`
`
`
`
`
`
`
`
`
`
`
`________________________________
`The Honorable James V. Selna
`United States District Judge
`
`
`
`
`
`1
`
`[PROPOSED] ORDER CONTINUING CLAIM CONSTRUCTION DEADLINES
`
`1 2 3 4 5 6 7 8 9
`
`10
`11
`12
`13
`14
`15
`16
`17
`18
`19
`20
`21
`22
`23
`24
`25
`26
`27
`28
`
`